Mishara Const. Co., Inc. v. Transit-Mixed Concrete Corp.

Decision Date17 April 1974
Docket NumberTRANSIT-MIXED
Parties, 70 A.L.R.3d 1259, 14 UCC Rep.Serv. 556 MISHARA CONSTRUCTION COMPANY, INC. v.CONCRETE CORP.
CourtUnited States State Supreme Judicial Court of Massachusetts Supreme Court

David C. Hawkins, Worcester, for plaintiff.

Andrew T. Campoli, Pittsfield, for defendant, submitted a brief.

Before TAURO, C.J., and REARDON, BRAUCHER, HENNESSEY and KAPLAN, JJ.

REARDON, Justice.

In this action of contract a verdict was returned for the defendant. The case is here on the plaintiff's exceptions.

The plaintiff Mishara Construction Company, Inc. (Mishara) was the general contractor under contract with the Pittsfield Housing Authority for the construction of Rose Manor, a housing project for the elderly. In September, 1966, the plaintiff negotiated with the defendant Transit-Mixed Concrete Corp. (Transit) for the supplying of ready-mixed concrete to be used on the project. An agreement was reached that Transit would supply all the concrete needed on the project at a price of $13.25 a cubic yard, with deliveries to be made at the times and in the amounts as ordered by Mishara. This agreement was evidenced by a purchase order signed by the parties on September 21, 1966. That purchase order identified the Rose Manor project and indicated that delivery was to be made '(a)s required by Mishara Construction Company.' Performance under this contract was satisfactory to both parties until April, 1967. In that month a labor dispute disrupted work on the job site. Although work resumed on June 15, 1967, a picket line was maintained on the site until the completion of the project in 1969. Throughout this period, with very few exceptions, no deliveries of concrete were made by Transit notwithstanding frequent requests by Mishara. After notifying Transit of its intention, Mishara purchased the balance of its concrete requirements elsewhere. Mishara sought in damages the additional cost of concrete incurred by virtue of the higher price of the replacement product, as well as the expenses of locating an alternate source.

The plaintiff's exceptions relate to the introduction of certain evidence and the failure of the trial judge to give certain requested instructions. Requests 2 and 3 sought instruction that the requirements that a definite quantity of goods and a definite duration of performance be specified in an enforceable contract are satisfied if the contract is one which calls for deliveries as required on a particular project. Since this is a contract for the sale of goods it is governed by the Uniform Commercial Code. G.L. c. 106. 'Requirements contracts' of the kind the plaintiff contends was present here are explicitly recognized as valid by the Code in G.L. c. 106, § 2--306(1). 1

The Official Comment No. 2 to that section makes clear the drafters' intention that when quantity is phrased only in terms of output or requirements the contract 'is not too indefinite since it is held to mean the actual good faith output or requirements' of the buyer or seller. Such a view is consistent with the established law of Massachusetts. Royal Paper Box Co. v. E. R. Apt Shoe Co., 290 Mass. 207, 195 N.E. 96 (1935). Neofotistos v. Harvard Brewing Co., 341 Mass. 684, 171 N.E.2d 865 (1961). Nor is a supply contract tied to a particular project too indefinite with respect to duration. This is not a case in which no time for performance is set out in the contract, and in which the court by long established rule will imply a reasonable time. Cf. Cohen v. Wintman, 236 Mass. 471, 472, 128 N.E. 778 (1920); G.L. c. 106, § 2--309(1). Although no specific date is named in the contract, the time is sufficiently determined by the occurrence of a specified event, i.e., the completion of the project. In Phelps v. Shawprint, Inc., 328 Mass. 352, 103 N.E.2d 687 (1952), in which payments were to continue so long as certain defendants were associated with the defendant corporation, it was said at pp. 354--355, 103 N.E.2d at p. 689: 'The contract was not silent on this aspect for it carried its own meansure of time. . . . Such a contract is not too indefinite or uncertain to be enforceable at least for partial breaches even though it is impossible to predict precisely when the contingency will occur that will bring the contract to an end.' See Proctor v. Union Coal Co., 243 Mass. 428, 137 N.E. 659 (1923); G.L. c. 106, § 2--309, comment No. 1. Therefore both of Mishara's requests were correct as matters of law. We believe, however, that these points were adequately covered in the judge's charge albeit in less than perfect form. There was no error in the failure to give instructions in precisely the form requested. Palmer Russell Co. v. Rothenberg, 328 Mass. 477, 482--483, 104 N.E.2d 433 (1952). Campbell v. Shea, 332 Mass. 422, 425, 125 N.E.2d 922 (1955).

Request 9 was an instruction that the contract was not terminable until Mishara had received all the concrete it required for the project. Again, although this was a correct statement of the law, we believe it was not error for the judge to refuse it. As has been shown, the specification of deliveries as needed on the project was a sufficiently definite statement of the time for performance. Therefore this was not a contract which contemplated ongoing and open-ended performance which would be terminable on reasonable notice. G.L. c. 106, § 2--309, and comment No. 1. Simmons v. American Dry Ginger Ale Co., Inc., 335 Mass. 521, 140 N.E.2d 649 (1957). Since, however, there was no indication from the evidence or the judge's charge that this was such a contract, there was no need to charge that it was not. A request correct in law but no appropriate to the conditions of a case is properly refused. Altavilla v. Old Colony St. Ry., 222 Mass. 322, 110 N.E. 970 (1916). McNeil v. Middlesex & Boston St. Ry., 233 Mass. 254, 256, 123 N.E. 676 (1919). Since it is unlikely that the jury would on their own initiative come to the conclusion that this was a contract which could properly be terminated prior to completion of performance by either party, it would have been misleading for the judge to charge that it was not terminable by the defendant. See Dixon v. New England R.R., 179 Mass. 242, 247, 60 N.E. 581 (1901).

Nor was there error in the refusal to give request 13, that on the evidence the jury 'must find that (the) defendant breached its contract with (the) plaintiff by failing to deliver' Mishara's concrete requirements. The principal issue in the case was the defendant's claimed excuse of impossibility of performance. The determination of that issue depended on facts and circumstances which were for the jury to decide. While we suppose one could develop a nice technical argument that impossibility does not nullify a breach but rather provides an excuse for it, to give the instruction requested would surely have misled the jury on the ultimate question of liability. Moreover, the failure to give it was of no detriment to the plaintiff of which it can complain. See Howes v. Grush, 131 Mass. 207 (1881). Dixon v. New England RR., supra.

The remainder of the plaintiff's exceptions relate to the proffered defence of the impossibility of performance. Objection was made to the introduction of all evidence regarding the existence of a picket line at the job site and the difficulty which Transit did encounter or might have encountered in attempting to make deliveries through that picket line. Furthermore, Mishara requested an instruction that Transit 'was required to comply with the contract regardless of picket lines, strikes or labor difficulties.' 2 As a result Mishara would have completely withdrawn the question of impossibility resulting from the picket line from the jury. We are asked to decide as matter of law and without reference to individual facts and circumstances that 'picket lines, strikes or labor difficulties' provide no excuse for nonperformance by way of impossibility. This is too sweeping a statement of the law and we decline to adopt it.

The excuse of impossibility in contracts for the sale of goods is controlled by the appropriate section of the Uniform Commercial Code, G.L. c. 106, § 2--615. 3 That section sets up two requirements before performance may be excused. First, the performance must have become 'impracticable.' Second, the impracticability must have been caused 'by the occurrence of a contingency the non-occurrence of which was a basic assumption on which the contract was made.' This section of the Uniform Commercial Code has not yet been interpreted by this court. Therefore it is appropriate to discuss briefly the significance of these two criteria.

With respect to the requirement that performance must have been impracticable, the official Code comment to the section stresses that the reference is to 'commercial impracticability' as opposed to strict impossibility. G.L. c. 106, § 2--615, comments 3--4. This is not a radical departure from the common law of contracts as interpreted by this court. Although a strict rule was originally followed denying any excuse for accident or 'inevitable necessity,' e.g., Adams v. Nichols, 19 Pick. 275 (1837), it has long been assumed that circumstances drastically increasing the difficulty and expense of the contemplated performance may be within the compass of 'IMPOSSIBILITY.' SEE ROWE V. PEABODY, 207 mass. 226, 233--234, 93 n.e. 604 (1911) (dictum); Fauci v. Denehy, 332 Mass. 691, 696--697, 127 N.E.2d 477 (1955). By adopting the term 'impracticability' rather than 'impossibility' the drafters of the Code appear to be in accord with Professor Williston who stated that 'the essence of the modern defense of impossibility is that the promised performance was at the making of the contract, or thereafter became, impracticable owing to some extreme or unreasonable difficulty, expense, injury, or loss involved, rather than that it is...

To continue reading

Request your trial
53 cases
  • Brotherhood of Maintenance of Way Employees v. Guilford Transp. Industries, Inc.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (1st Circuit)
    • October 28, 1986
    ...& Santa Fe Railway Co., 387 U.S. 397, 406, 87 S.Ct. 1608, 1613, 18 L.Ed.2d 847 (1967).38 See Mishara Constr. Co. v. Transit-Mixed Concrete Corp., 365 Mass. 122, 310 N.E.2d 363 (Mass.1974) (recognizing that when labor dispute is unexpected and occurrence of the dispute presents unusual diffi......
  • U.S. v. Winstar Corp.
    • United States
    • United States Supreme Court
    • July 1, 1996
    ...an advantage for which he could not be said to have bargained in making the contract"); Mishara Construction Co. v. Transit-Mixed Concrete Corp., 365 Mass. 122, 129, 310 N. E. 2d 363, 367 (1974) ("The question is . . . Was the contingency which developed one which the parties could reasonab......
  • Upsher-Smith Laboratories v. Mylan Laboratories
    • United States
    • U.S. District Court — District of Minnesota
    • July 9, 1996
    ...If it was, performance was required; if not, performance is excused. Id., quoting Mishara Construction Co., Inc. v. Transit-Mixed Concrete Corp., 365 Mass. 122, 310 N.E.2d 363, 367 (1974). Moreover, "if the factors which create the event are within the control of the party asserting commerc......
  • Rgj Associates, Inc. v. Stainsafe, Inc.
    • United States
    • U.S. District Court — District of Massachusetts
    • September 30, 2004
    ...K Mart had an enduring duty to determine the extent of its requirements in good faith"); Mishara Construction Co., Inc. v. Transit-Mixed Concrete Corporation, 365 Mass. 122, 310 N.E.2d 363, 365 (1974) (when quantity is measured in terms of requirements, it means "the actual good faith" requ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT