Miss. State Port Auth. at Gulfport v. Eutaw Constr. Co.
Decision Date | 09 June 2022 |
Docket Number | 2020-IA-00881-SCT |
Citation | 340 So.3d 303 |
Parties | The MISSISSIPPI STATE PORT AUTHORITY AT GULFPORT v. EUTAW CONSTRUCTION COMPANY, INC. |
Court | Mississippi Supreme Court |
ATTORNEYS FOR APPELLANT: M. BRANT PETTIS, BEN H. STONE, MARK E. BOND, JAMES E. LAMBERT, III, Gulfport
ATTORNEYS FOR APPELLEE: DORSEY R. CARSON, JR., Jackson, ERIC F. HATTEN, LINDSAY K. ROBERTS, KATHRYN P. GOFF, KELLI M. SLATER
BEFORE KITCHENS, P.J., MAXWELL AND CHAMBERLIN, JJ.
CHAMBERLIN, JUSTICE, FOR THE COURT:
¶1. This matter involves the award of a construction contract by the Mississippi State Port Authority at Gulfport (the MSPA) to the low-bidder, W.C. Fore Trucking, Inc. (Fore). Eutaw Construction Company, Inc. (Eutaw), another bidder, challenged that award, and the Circuit Court of the First Judicial District of Hinds County reversed the MSPA's decision to award the contract to Fore. The MSPA appealed. Finding error, this Court reverses and renders the decision of the circuit court.
FACTS AND PROCEDURAL HISTORY
¶2. The Mississippi Legislature created the MSPA as an agency responsible for the development and operation of the state port located in Gulfport, Mississippi. See Miss. Code Ann. § 59-5-1 through -69 (Rev. 2013). Following the aftermath of Hurricane Katrina and pursuant to its statutory responsibility, the MSPA undertook a massive restoration of the state port consisting of various construction projects. One of those projects was the West Pier +25 Fill-Phase 1, Project No. 005 (the Project), the construction project at issue here.1
¶3. The MSPA issued a bid solicitation for the Project on February 1, 2012. The deadline to submit a bid was 10:00 a.m. on March 2, 2012. On February 24, 2012, the MSPA issued Addendum No. 1 to the bid solicitation. This addendum doubled the quantity of riprap and aggregate base course for the purpose of constructing a temporary haul ramp for the Project. Additionally, Addendum No. 1 required bidders to submit bids on a revised bid form, which recognized the addendum's change to the bid solicitation.2
¶4. On March 6, 2012, the MSPA publically opened the bid envelopes submitted for the Project. Among the eleven bidders were Eutaw and Fore. Fore's bid was $19,956,587.98, which was the lowest bid. Eutaw submitted the second-lowest bid of $22,905,525. Unbeknownst to the other bidders, however, the MSPA wrote a letter to Fore on March 7, 2012, informing Fore of errors in its bid.
¶5. The errors identified by the MSPA in its March 7, 2012 letter are recited here verbatim:
In the letter, the MSPA recited the relevant rule from the Procurement Manual of the Mississippi Department of Finance and Administration, Rule 3.106.12.4, that governs the MSPA's evaluation and decision after the opening of sealed bids and the discovery of errors in a submitted bid but before the time of the award of the contract. Rule 3.106.12.4 provides as follows:
12 Miss. Admin. Code Pt. 6, R. 3.106.12.4 (adopted Jan. 1, 2018), Westlaw.
The MSPA further decided that the correction of this error would not prejudice the other bidders. The total bid for these items, $159,732.50 and $35,000, were the same on both the original and revised bid forms submitted by Fore. Only the price per unit changed.
¶7. The second error involved incorrect calculations of certain line item total costs.4 Specifically, Fore incorrectly multiplied the quantity and the unit price of certain line items. In its letter, the MSPA determined these The MSPA decided that it was in the State's best interest to allow these errors to be corrected.
¶8. The third error involved a discrepancy between the sum of the line item totals and the "total amount of base bid" that Fore expressed in its bid. Fore listed the "total amount of base bid" as $19,956,587.98. The sum of the line item totals, however, was $19,121,886.96. The original bid form and the revised bid form both provided that "[i]n the case of discrepancy between the sum of the items and the Total Amount of Bid, the sum of the items shall be considered to be the Total Amount of Bid." Based on that language, the MSPA determined that the "controlling total amount" of Fore's bid was $19,116,447.98, i.e., the sum of the line item totals ($19,121,886.96) less the overages resulting from the calculation errors addressed under the second error ($5,439.98). The MSPA further determined that the intended correct bid amount was not evident from the Bid submitted. Accordingly, the MSPA decided that it "will accept Fore Trucking's Bid of $19,116,44[7].98 or allow Fore Trucking to withdraw its Bid under the provisions of Rule 3.106.12.4(3) of the Procurement Manual."
¶9. On March 8, 2012, Fore sent a reply letter to the MSPA that acknowledged the errors it had made. Attached to Fore's reply letter was the revised bid form that included the pertinent corrections pursuant to the March 7, 2012 MSPA letter. This time, along with the other corrections, Fore listed the "total amount of base bid" as $19,116,447.98, as advised by the MSPA. The MSPA then declared Fore the lowest bidder and awarded it the Project contract.
¶10. On March 12, 2012, Eutaw formally submitted a bid protest to the MSPA that challenged the MSPA's decision to award the contract to Fore. In its bid protest, Eutaw indicated that it had "reason to believe" Fore was a nonresponsive bidder. The MSPA found Eutaw's bid protest without merit and issued a denial shortly after Eutaw submitted its bid protest. Eutaw filed a supplemental bid protest, but the MSPA did not respond. Eutaw then appealed the MSPA's decision to the circuit court.5
¶11. Eutaw's appeal to the circuit court began on April 24, 2012 when it filed its "Notice of Appeal and Bill of Exceptions." The MSPA, on May 29, 2012, sought to dismiss this appeal by arguing that Eutaw could only proceed via writ of certiorari. In response, Eutaw filed its original and amended petition for writ of certiorari in a new case. Again, the MSPA filed a motion to dismiss and argued lack of jurisdiction.
¶12. Eutaw moved to consolidate the two cases, and the circuit court consolidated them on November 20, 2012. The circuit court heard oral arguments on February 21, 2013. The MSPA filed a third motion to dismiss but withdrew that filing after the circuit court—on February 28, 2014—ultimately decided to grant Eutaw's amended petition for writ of certiorari and agreed to hear the merits of the...
To continue reading
Request your trial-
Magee v. State
... ... -COA, So.3d , , 2021 WL 4271912, at *2 (Miss. Ct. App. Sept. 21, 2021).9. The Court of Appeals ... ...
-
Gregory Constr. Servs. v. Miss. Dep't of Fin. & Admin.
... ... GROUNDS AND REAL PROPERTY MANAGEMENT; AND MISSISSIPPI STATE VETERANS AFFAIRS BOARD APPELLEES No. 2021-SA-00765-COACourt ... complaining party." Miss. State Port Auth. at ... Gulfport v. Eutaw Const. Co., 340 So.3d ... ...