WHITHAM, Justice.

Appellee, Dean Maurer, recovered judgment in quantum meruit against his former employer, appellant, Mitsubishi Aircraft International, Inc. We conclude that Maurer's services were covered by an express contract, that Maurer was not wrongfully discharged, that Mitsubishi did not breach the contract and thus prevent Maurer's completion of performance, and that, therefore, Maurer cannot recover the additional compensation sought. Accordingly, we reverse and render.

In December 1978, Mitsubishi employed Maurer as a sales representative. There was no written employment agreement; however, Mitsubishi's 1978 Sales Salary/Incentive Plan was a part of Maurer's employment agreement. Under the 1978 plan, Mitsubishi paid its sales representatives a minimum salary plus a commission for each aircraft sold. In January 1979, Mitsubishi published its 1979 Sales Salary/Incentive Plan. The 1979 plan became part of Maurer's employment agreement. The 1979 plan provided commission payments for turboprop aircraft, as well as used aircraft. Though the plan had a category for jet aircraft, it did not reveal what the commission structure was going to be for jet aircraft.

Contemporaneous with its announcement to market a jet aircraft, Mitsubishi published an amendment to the 1979 plan which provided a commission structure for the sale of the jet aircraft. The amendment provided as follows:

C. Payments For Jet Orders Which Will Not Be Firmed Up Until 1980 and Will Be Allocated As Follows:

1. 20% with 2nd Deposit (i.e. Firm Order).

2. 20% with Final Deposit (6 Months Prior to Delivery).

3. 60% upon Delivery.

Personnel may only receive these if they are in employment of [Mitsubishi] at applicable time. (emphasis added).

Maurer was shown the amendment in June 1979. The 1979 amendment became part of Maurer's employment agreement. Thereafter, Maurer obtained letters of intent and initial deposits for the purchase of jet aircraft by three customers. No commission was due at this stage under the 1979 amendment. Maurer was asked to resign and did so. At the time of Maurer's termination, the second deposit had not been paid by any of the three customers. Under the 1979 amendment, no part of the commission was due until the second deposit had been paid. Thus, Maurer was not in the employ of Mitsubishi "at applicable time" to receive any commission on the sale of jet aircraft. Commissions associated with these three customers were paid to the sales representative who took Maurer's place.

The trial court found that Maurer's services with respect to transactions with the three customers were "extra services" and that these extra services were not within the scope of any contract between Maurer and Mitsubishi. The trial court then concluded that as a matter of law Maurer was entitled to judgment for these extra services. In its first and second points of error, Mitsubishi contends that the evidence was (1) legally insufficient and (2) factually insufficient to support the trial court's findings. Under its first point, Mitsubishi argues that the trial court erred as a matter of law in its conclusion that Maurer was entitled to judgment for these extra services. A "legally insufficient" point is a "no evidence" point presenting a question of law. In deciding that question, the appellate court must consider only the evidence and the inferences tending to support the finding and disregard all evidence and inferences to the contrary. If a "no evidence" point is sustained and the proper procedural steps have been taken, the finding under attack may be disregarded entirely and judgment rendered for the appellant unless the interests of justice require another trial. Garza v. Alviar, 395 S.W.2d 821, 823 (Tex.1965). Applying these principles to the present case, we conclude that we must sustain Mitsubishi's first point and reverse and render judgment for Mitsubishi.

From the trial court's findings and conclusions of law it is obvious that judgment was rendered on quantum meruit. The right to recover in quantum meruit is based upon a promise implied by law to pay for beneficial services rendered and knowingly accepted. Black Lake Pipe Line Co. v. Union Construction Co., 538 S.W.2d 80, 86 (Tex.1976). If the work in question is covered by an express contract, there can be no recovery in quantum meruit. 538 S.W.2d at 86; Woodard v. Southwest States, Inc., 384 S.W.2d 674, 675 (Tex.1964); Teague v. Edwards, 159 Tex. 94, 315 S.W.2d 950, 952 (1958); General Homes, Inc. v. Denison, 625 S.W.2d 794, 796 (Tex.App.--Houston [14th Dist.] 1981, no writ).

Thus, we reach the question whether Maurer's work in question was covered by an express contract. An at-will employment contract is continuously subject to modification at the behest of either party. L.G. Balfour Co. v. Brown, 110 S.W.2d 104, 107-08 (Tex.Civ.App.--Forth Worth 1937, no writ). In the present case, Mitsubishi made the 1979 amendment known to Maurer and Maurer thereafter continued in Mitsubishi's employment and engaged in the three customer transactions. Maurer admits that the 1979 amendment was part of his employment contract:

Q: And under the '79 Amended Sales/Incentive program for the [three customers] deals, for the orders which you solicited for those deals, what was the amount of commission to which you were entitled under the incentive program?

A: It was $27,500.00

* * *

* * *

Q: And that's the plane [sic] that you were shown in June of 1979 when the jet was starting to be marketed, correct?

A: Yes, sir.

Q: And that's the plan that described how you would be compensated for the sales of the jet?

A: That's correct.

Thus, we conclude that Maurer accepted the 1979 amendment as a modification of his at-will employment contract. We conclude further, therefore, that Maurer's work in question was covered by an express contract.

Maurer,...

To continue reading

Request your trial
12 cases
  • Balfour Beatty Rail, Inc. v. Kan. City S. Ry. Co.
    • United States
    • U.S. District Court — Northern District of Texas
    • March 25, 2016
    ...When there exists a valid express contract covering the subject matter, there can be no implied contract. Id. ; Mitsubishi Aircraft Int'l, Inc. v. Maurer , 675 S.W.2d 286, 288 (Tex.App.–Dallas 1984, no writ). If the work for which recovery is sought is covered by and falls within the scope ......
  • Arthur J. Gallagher & Co. v. Dieterich
    • United States
    • Texas Court of Appeals
    • October 27, 2008
    ...situation, other cases that have cited Balfour construe it as such. See, e.g., Hathaway, 711 S.W.2d at 229; Mitsubishi Aircraft Int'l, Inc. v. Maurer, 675 S.W.2d 286, 288 (Tex. App.-Dallas 1984, no writ); Geodominion Petroleum, Inc. v. Boone Exploration, Inc., No. 13-06-00430-CV, 2008 WL 35......
  • Caton v. Leach Corp.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • March 21, 1990
    ...Inc. v. Denison, 625 S.W.2d 794, 796 (Tex.App.--Houston [14th Dis.] 1981, no writ). Our decision is governed by Mitsubishi Aircraft Int'l, Inc. v. Maurer, 675 S.W.2d 286 (Tex.App.--Dallas 1984, no writ), in which the Texas court held against In the present case Maurer was an employee at-wil......
  • Hampden Corp. v. Remark, Inc.
    • United States
    • Texas Court of Appeals
    • June 25, 2014
    ...cases involving employee/employer relationships and one federal case involving a non-employee sales agent. See Mitsubishi Aircraft Int'l, Inc. v. Maurer, 675 S.W.2d 286 (Tex. App.—Dallas 1984, no writ) (involving employee sales representative); L.G. Balfour Co. v. Brown, 110 S.W.2d 104 (Tex......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT