Modern American Mortg. Corp. v. Skyline Park, 78-1410

Decision Date02 April 1980
Docket NumberNo. 78-1410,78-1410
PartiesMODERN AMERICAN MORTGAGE CORP. and First Federal Savings & Loan Assoc., Plaintiffs-Appellants, Cross-Appellees, v. SKYLINE PARK, a Texas General Partnership, et al., Defendants-Appellees, v. George W. TUCKER, d/b/a Empire Construction Co., Defendant-Appellee, Cross-Appellant.
CourtU.S. Court of Appeals — Fifth Circuit

Jay M. Goltz, Dallas, Tex., for plaintiffs-appellants, cross-appellees.

Crocker & McDonald, Toy A. Crocker, Dallas, Tex., for George W. Tucker.

Blankenship & Potts, Hal Potts, Ralph W. Currie, Dallas, Tex., for Skyline Park, Sam A. Leake, and Sarah H. Leake.

Appeals from the United States District Court for the Northern District of Texas.

Before MORGAN, REAVLEY and HATCHETT, Circuit Judges.

HATCHETT, Circuit Judge:

This appeal concerns a mortgagee, owner, and contractor, in a contractual dispute relating to the Federal Housing Administration's Insurance of Mortgages under the National Housing Act, 12 U.S.C. § 1701 et seq. The district court in a diversity judgment granted relief against the appellee contractor but denied relief as to the appellee owner. Because our interpretation of the contract finds the mortgagee responsible for its own loss, we find neither the owner nor the contractor liable. Accordingly, we affirm in part and reverse in part.

Appellant, Modern American Mortgage Corp., the Lender, is the mortgagee. Appellee, Skyline Park, a Texas General Partnership, (Sam A. Leake, individually, Sarah H. Leake, individually) is the owner. Appellee, George W. Tucker, d/b/a Empire Construction, is the contractor.

On November 17, 1970, FHA issued its Commitment for Insurance of Advances for the private financing of a mobile park, Skyline Park. Pursuant to this commitment, a mortgage loan transaction, consisting of a Building Loan Agreement, Construction Contract, Completion Assurance Agreement, and Note and Deed of Trust, was executed and delivered between the mortgagee, the owner, and the contractor.

The Building Loan Agreement contains the basic terms and conditions under which the mortgagee was responsible for advancing funds for the construction of the project. The only parties to the agreement were the mortgagee and the owner. The agreement provides that the mortgagee would make the loan, that the owner would complete the project by November 8, 1971, and that the owner would furnish the mortgagee the assurance of completion in the form specified by FHA regulations. 24 C.F.R. § 207.19(c)(7). *

The Construction Contract was between the owner and the contractor. It states that the contractor should furnish to the owner a Completion Assurance Agreement, in the amount of $49,643. Article 6 says "Such assurance of completion shall run to the Owner and Lender as obligees and shall contain a provision whereby the security agrees that any claim or right of action that either the Owner or Lender might have thereunder may be assigned to the Commissioner." The Construction Contract defines substantial completion as the "date that the FHA Chief Underwriter signs the final Project Inspection Report." The Construction Contract further states that in the event of failure of the owner to perform his obligations to the mortgagee, and "in the event the mortgagee elects not to undertake completion, the contractor's obligations under this contract shall terminate."

The Completion Assurance Agreement provides that the contractor deposit with the mortgagee a fund of $49,643, in the form of an irrevocable letter of credit, to assure the contractor's completion of the project. The agreement states that this fund was to be used by the mortgagee "to indemnify the Owner or the Lender, as the case may be, for any expenses, loss or damage suffered or sustained as the result of any default by the contractor in the performance of the Construction Contract." (Emphasis added). The fund could only be disbursed upon prior written approval of the Federal Housing Commissioner, or his authorized agent. The agreement states that it was additional security for the performance by the contractor of his obligations.

The Note and Deed of Trust, states that the owner assumed no personal liability for the payments.

The Completion Assurance Agreement letter of credit expired in part on June 1, 1972, and in full on June 1, 1973. The mortgagee requested more than once that the contractor renew the letter of credit, but such requests were refused.

Though the project was essentially completed from a construction perspective, problems with the utility hook-ups, beyond the scope of this suit, prohibited the FHA Chief Underwriter from signing the final Project Inspection Report.

The mortgagee was in default in March, 1974, by reason of nonpayment of principal, interest, and escrow funds, and the property was foreclosed at a sale conducted under the loan documents. After foreclosure, the FHA deducted the amount of the assurance of completion fund from the amount the mortgagee was otherwise entitled to under the FHA Mortgage Insurance.

The mortgagee brought this action to establish joint and several liability against the owner and contractor for losses incurred after foreclosure and upon assignment of the mobile home project to FHA. Liability was sought to be established on the basis of the Building Loan Agreement, the Construction Contract, and the Completion Assurance Agreement.

After a non-jury trial, the district court found that the parties agreed that the owner's responsibility was confined to insuring the deposits of the irrevocable letter of credit in the amount of $49,643. The court found the contractor liable for the $49,643 and the owner not liable.

The trial court found liability on the basis that the contractor failed to fully perform the Construction Contract; that the contractor breached the Completion Assurance Agreement by not replacing the expired letter of credit; and that the contractor's failure to perform the Construction Contract was the cause of the mortgagee's loss.

The mortgagee accepts the trial court's finding concerning the contractor and additionally asserts that the contractor was liable until the project was completed.

This court must decide whether the trial court properly interpreted the contract. Our duty is to interpret the contract under the applicable law. Based on our interpretation, we affirm the finding of the trial court that the owner is not liable.

To determine whether the trial court properly found the contractor liable, we need decide: (1) whether the trial court erred in finding that the contractor failed to fully complete the Construction Contract; and (2) whether the trial court erred in finding that the contractor breached the Completion Assurance Agreement.

The parties agree that the Texas law is controlling. We are thus bound to interpret the four simultaneously executed documents as one contract, attempting to reconcile the various parts to discern the intent of the parties. Guadalupe-Blanco River Authority v. City of San Antonio, 145 Tex. 611, 200 S.W.2d 989 (1947); Republic Ins. Co. v. Hope, 557 S.W.2d 603 (Tex.Civ.App.1977).

Because this case involves a dispute in contractual interpretation where extrinsic evidence, in the form of relevant testimony, was considered, our standard of review is determined by Thornton v. Bean Contracting Co., Inc., 592 F.2d 1287 (5th Cir. 1979) where this court decided:

(Generally) the interpretation of a contract is a question of law, not fact, and appellate review is not limited to the 'clearly erroneous' rule. First National Bank of Miami v. Insurance Co. of North America, 495 F.2d 519 (5th Cir. 1974); Makofsky v. Cunningham, 576 F.2d 1223 (5th Cir. 1978). An exception to this rule is the situation in which extrinsic evidence has been used in interpreting an ambiguous contract. See Valley Cement Industries, Inc. v. Midco Equipment Co., 570 F.2d 1241 (5th Cir. 1978); Makofsky, supra.

592 F.2d at 1290.

We hold that the trial court was clearly erroneous in finding that the contractor failed to complete the Construction Contract and in finding that the contractor breached the Completion Assurance Agreement by not replacing the expired letter of credit. Fed.R.Civ.P. 52(a).

I.

The contractor fully completed his obligation under the Construction Contract. Article 2D of the Construction Contract provides: "The date of substantial completion shall be the date the FHA Chief Underwriter signs the final Project Inspection Report . . . ." Under our interpretation of the contract, that definition of substantial completion is applicable only to the owner and mortgagee. The definition of substantial completion applicable to the contractor is found in art. 2C of the Construction Contract: "substantially completed in accordance with the Drawings and Specifications." The contractor finished everything called for in the drawings and specifications. He satisfied the definition of completion applicable to him. The mobile home park project was not completed because the utility companies failed to install the utility mains. The contractor was not at fault. He fully met his obligation to install the service lines to which the utility mains would connect. Both the owner and the mortgagee acknowledged that the contractor satisfied his Construction Contract obligations. At oral argument, the owner admitted that the contractor had fully performed. The owner also disclosed at oral argument, that in an affidavit in another lawsuit, he had admitted that the contractor not only completed the Construction Contract, but that the contractor had performed extra work in repairing certain damages done by the utility companies. The mortgagee also stated at oral argument that the contractor fulfilled his obligation. In its brief to this court, the mortgagee conceded that "there had never been a failure by Tucker to perform under the Construction Contract."

We conclude that the trial court erred in finding...

To continue reading

Request your trial
4 cases
  • Neal v. Hardee's Food Systems, Inc.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • 29 Noviembre 1990
    ...parties, for the same purposes, and as part of the same transaction, are to be construed together. See Modern American Mort. Corp. v. Skyline Park, 614 F.2d 1009, 1012 (5th Cir.1980); In re Olm Associates, 98 B.R. 271, 274 (N.D.Tex.1989); Jim Walter Homes, Inc. v. Schuenemann, 668 S.W.2d 32......
  • Richland Plantation Co. v. Justiss-Mears Oil Co., Inc.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • 25 Marzo 1982
    ...apparently conflicting provisions and attempting to give effect to all of them, if possible. Modern American Mortgage Corp. v. Skyline Park, 614 F.2d 1009, 1012 (5th Cir. 1980); Republic Insurance Co. v. Hope, 557 S.W.2d 603, 607 (Tex.Civ.App.-1977, no writ). That does not necessarily requi......
  • McCarthy Bros. Const. Co. v. Pierce
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • 22 Octubre 1987
    ...applies to determine McCarthy's eligibility for the incentive fee. In this regard, McCarthy relies on Modern American Mortgage Corp. v. Skyline Park, 614 F.2d 1009 (5th Cir.1980), which, apparently interpreting a similar contract, held that the Article 2D definition of substantial completio......
  • McCarthy Bros. Const. Co. v. Pierce, 84-1830C (A).
    • United States
    • U.S. District Court — Eastern District of Missouri
    • 14 Enero 1986
    ...Report eleven days after the contract's completion date. Plaintiff relies very heavily on Modern Am. Mortg. Corp. v. Skyline Park, 614 F.2d 1009 (5th Cir.1980) (hereinafter Skyline Park) to support its contention that Article 2D applies to National Church and HUD. This Court, however, belie......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT