Monolith Portland Midwest Co. v. RECONSTRUCTION F. CORP., Civ. No. 11816.
Decision Date | 20 February 1952 |
Docket Number | Civ. No. 11816. |
Citation | 102 F. Supp. 951 |
Court | U.S. District Court — Southern District of California |
Parties | MONOLITH PORTLAND MIDWEST CO. v. RECONSTRUCTION FINANCE CORP. |
Gibson, Dunn & Crutcher, Richard E. Davis, and Joseph T. Enright, Los Angeles, Cal., for plaintiff.
Lillick, Geary & McHose, and Allan E. Charles, Los Angeles, Cal., for defendant.
The issue raised here is, "Whether or not a prime War Contractor, aggrieved of the findings of the contracting agency on his claim which had been filed pursuant to the war Contract Settlement Act of 1944, 41 U.S.C.A. §§ 101-125, is entitled to a jury trial when he seeks relief under Section 13(b) (2), 41 U.S.C.A. § 113(b) (2), of the Act?"
The facts of the present case are found in two former opinions, Monolith Portland Mid. Co. v. R. F. C., 9 Cir., 1949, 178 F.2d 854, and Monolith Portland Mid. Co. v. R. F. C., 9 Cir., 1951, 95 F.Supp. 570.
Since the Act is silent on the right to jury trial, it becomes necessary to review the Act, its history, and the nature of the action to discover the intent of Congress.
The purpose for which the Act was passed is clear. 41 U.S.C.A. § 101. To preserve the national economy, Congress had to provide a quick, efficient and equitable method of settling terminated war contracts and of expediting reconversion. One of the objectives was to achieve uniformity not only among Governmental agencies charged with termination settlements and interim financing, 41 U.S.C.A. § 101(c) but also among instrumentalities of Government which Congress appointed to hear and decide such claims. See 41 U.S.C.A. §§ 106(b) and (d).
The primary method established by Congress for the disposition of claims was by way of settlement. This was to be conducted by the contracting agency itself. Congress was hopeful that the majority of claims would be terminated in these settlement procedures, but recognized that some contractors would not agree to the settlement offers and therefore provided methods for the determination of claims and the review thereof.
Unable to determine how many contractors would seek a review, Congress provided by Section 13(b), 41 U.S.C.A. § 113 (b), of the Act, the methods by which a war contractor could obtain this review. It provided that the contractor may, at his election:
A review of the Congressional debates and Committee reports discloses that § 13 (b), 41 U.S.C.A. § 113(b) did not create any great conflict among the members. It was generally agreed that adopting a procedure for a review of the contracting agency's determination, would be fair both to the Government and to the war contractors. In discussing this section on the floor of the House, Congressman Walters, one of the authors of the bill said: Congressional Record, 78th Congress, 2nd session, 1944, Vol. 90, part 2, p. 6052, column 3. Emphasis added.
In the Senate we find a report from the Special Committee on Post-War Economic Policy and Planning, with its recommendations, read into the Record by Senator George. In part, it reads as follows:
"In subsection (b) (2) an amendment is suggested to preserve State Court jurisdiction over the RFC and its subsidiaries." Congressional Record 78th Congress, 2nd session, 1944, Vol. 90, part 3, p. 3907, column 2. Emphasis added.
As seen, the bill as finally passed contained the proposed amendments.1
It is clear that throughout the entire discussions on Section 13(b), 41 U.S.C.A. § 113(b), the section has been referred to as a method of appealing from the determination of the contracting agency. It is equally clear that the Record is void of any mention of the right to jury trial.
The primary purpose of Section 13(b), 41 U.S.C.A. § 113(b), is to provide an aggrieved war contractor with a method of reviewing the contracting agency's determination of their claims. If the true nature of the action is that of an "appeal" from an administrative determination2 Rumsey Mfg. Corp. v. United States Hoffman Machinery Corp., 2 Cir., 1951, 187 F.2d 927, 929, then in the absence of an express statutory grant, no jury trial is available.
Plaintiff argues that, basically this is an action at law predicated upon certain contractual rights and therefore the right to jury trial is guaranteed. They further argue that the act provides that when a war contractor is aggrieved of the findings of the contracting agency he may "bring suit" against the Reconstruction Finance Corporation "in any court of competent jurisdiction in accordance with existing law," and that these words show that Congress intended that the action be one at common law with the concomitant right to jury trial. What plaintiff has failed to observe is that the right to bring the action is not on the contract, but is expressly limited to an action on the claim or part thereof. The clear expression by Congress that the action is to be pursued on the "claim" and not on the contract distinguishes the nature of the action from the ordinary common law action for breach of contract.
Although no direct authority can be found on the issue before us, authority directly in point can be found in an analogous situation, namely condemnation.
In our prior decision, Monolith case, supra, 95 F.Supp. at page 579, we indicated that the effect of the application of the Contract Settlement Act and the War Mobilization and Conversion Act upon war contracts was analogous to condemnation. It is clear there is no constitutional right to trial by jury in a condemnation action in the absence of a specific statutory grant. Bauman v. Ross, 1896, 167 U.S. 584, 593, 17 S.Ct. 969, 42 L.Ed. 270; Dohany v. Rogers, 1929, 281 U.S. 362, 369, 50 S.Ct. 299, 74 L.Ed. 904; U. S. v. Hess, 8 Cir., 1934, 70 F.2d 142; U. S. v. Hess, 8 Cir., 1934, 71 F.2d 78; Iriarte v. U. S., 1 Cir., 1946, 157 F.2d 105.3
The primary question in condemnation proceedings is the same as here, i. e. "fair compensation." Its determination, in the absence of express statutory provisions to the contrary, is to be made by the court without the aid of a jury trial.
To summarize then, we find that actions brought under Section 13(b), 41 U.S.C.A. § 113(b), of the War Contract Settlement Act of 1944 are primarily in the nature of an appeal to review the findings of an administrative agency. It is not an ordinary action for breach of contract since the action is expressly limited to an action on the "claim or part thereof". At best, it is analogous to a condemnation action since the primary issues are the same in both actions. The nature of the action is not one, therefore, which demands the granting of a jury trial.
There are other reasons which lead this court to the conclusion that Congress did not intend to have these claims tried before a jury. Stated briefly they are as follows:
(1) The act provides for concurrent jurisdiction in (a) the Appeal Boards, (b) the Court of Claims (c) the District courts and (d) the State courts, under certain situations of which this case is one. Since neither the Appeal Boards nor the Court of Claims afford jury trials, uniformity would require that the action on these claims be heard by the Court alone.
(2) Throughout the entirety of Section 13, 41 U.S.C.A. § 113, reference is made to the Appeal Boards or Court of Claims or Court in such manner as to infer that this means the "Judge" of the Court sitting alone. Although this factor alone is not persuasive in showing the legislative intent, combined with all the other factors it logically leads to the conclusion. Allen v. United States, D. C., 1926, 10 F.2d 807, 809.
(3) Congress took great pains to specify the qualifications of those who were to sit on the newly created Appeal Boards. The Act provides that they shall be "qualified and experienced attorneys, engineers, accountants, or persons possessing sufficient business experience or professional skill." 41 U.S.C.A. § 113(d). To have required less would have resulted in inequities either to the Government or to the contractors, a situation which Congress sought to prevent. It seems rather doubtful that such great care in spelling out these qualifications would have been taken, if Congress had at the very same time contemplated trial by jury as an alternative remedy.
In light of all the above factors, it is the opinion of this court that the purpose of adopting Section 13(b), 41 U.S.C.A. § 113(b), was to provide aggrieved war contractors with a method of reviewing or appealing the contracting agency's determination and that such review was to...
To continue reading
Request your trial-
Tucson Airport Authority v. General Dynamics Corp.
...claims resulting from the government's termination of wartime contracts. See 41 U.S.C. § 101; Monolith Portland Midwest Co. v. Reconstruction Finance Corp., 102 F.Supp. 951, 952 (C.D.Cal.1952). Section 103(m) prohibits the government from modifying or disregarding any final and conclusive s......
-
Monolith Portland Mid. Co. v. Reconstruction F. Corp.
...R.F.C. moved to strike the request. This court denied a trial by jury and its opinion thereon is reported in Monolith, etc., Co. v. R. F. C., D.C.S.D. Cal.1952, 102 F.Supp. 951. The case was tried beginning November 5, 1952, and ending February 20, 1953. Extensive printed briefs were filed ......
-
Monolith Portland Mid. Co. v. RECONSTRUCTION F. CORP.
...agency", and that therefore "in the absence of an express statutory grant, no jury trial is available." Monolith Portland Midwest Co. v. R. F. C., D.C.Cal., 1952, 102 F.Supp. 951, 953. As we have seen, however, the appeal subparagraph (1) of § 113(b) is separate and distinct from subparagra......