Morrisville Lumber Co., Inc. v. Okcuoglu

Decision Date01 May 1987
Docket NumberNo. 85-463,85-463
Citation148 Vt. 180,531 A.2d 887
CourtVermont Supreme Court
PartiesMORRISVILLE LUMBER CO., INC., v. Cetin A. and Judy OKCUOGLU.

Stevens & Elliott, Stowe, for plaintiff-appellant.

Peter B. Brittin of Stearns & Thorndike, Stowe, for defendants-appellees.

Before ALLEN, C.J., HILL, PECK and GIBSON, JJ., and BARNEY, C.J. (Ret.), Specially Assigned.

ALLEN, Chief Justice.

This appeal is from a grant of summary judgment in favor of defendants. We affirm.

In September 1981, defendants entered into a written contract with Nourjian Building Company (Nourjian) for the construction of a vacation home in Stowe. Defendants agreed to a contract price of $225,000. Nourjian was to complete performance by February 1982. Plaintiff, Morrisville Lumber Company, provided building materials and supplies on an open account to Nourjian. Nourjian had two accounts with plaintiff: a "general" account and an "Okcuoglu" account. A contract dispute between defendants and Nourjian over certain modifications and the completion date ultimately led to Nourjian's termination in August 1982. Defendants thereafter completed construction on their own. Plaintiff seeks to recover from the defendants the unpaid balance for the materials and supplies which it had provided to Nourjian.

In August 1982, plaintiff filed a contractor's lien against defendants' home for the amount due on its "Okcuoglu" account; it did not include the amounts due on Nourjian's "general" account upon which materials for defendants' house were also charged. The lien was never perfected. In September 1982, plaintiff brought suit against Nourjian for the materials and supplies it had provided under both accounts. The plaintiff obtained a judgment by default against Nourjian for the amounts due for materials furnished on the job, which has not been satisfied.

The plaintiff then brought this action against defendants for the amounts plaintiff had been unable to collect from Nourjian. Plaintiff and defendants each filed motions for summary judgment which were denied. A later request for reconsideration of the motions was also denied. After additional discovery, defendants filed a renewed motion for summary judgment which was also denied. Thereafter, the court, on its own motion, reconsidered its earlier denial and granted summary judgment in favor of defendants.

Plaintiff's first argument is procedural. Plaintiff contends that the trial court erred by reconsidering, on its own motion without a hearing, its earlier denial of defendants' motion for summary judgment. As indicated, the trial court had denied summary judgment on three separate occasions prior to granting the motion in favor of defendants. It is plaintiff's contention that V.R.C.P. 60(b) exclusively governs relief to be granted from the denial of a summary judgment motion, that no criteria required by Rule 60(b) for relief were present, and that Rule 60(b) has no provision allowing a court to reconsider an earlier denial on its own motion.

Plaintiff's argument necessarily implies that the denial of a summary judgment motion is a final judgment. The denial of a motion for summary judgment, however, is an interlocutory order, and is not appealable as a matter of right. See In re Pyramid Co., 141 Vt. 294, 299, 449 A.2d 915, 917 (1982); 6 J. Moore's Federal Practice §§ 56.20, 56.21 (1986). Upon denial, the claim remains pending for trial. V.R.C.P. 60(b) deals exclusively with relief from final judgments and is not controlling in the present case. Dudley v. Snyder, 140 Vt. 129, 131, 436 A.2d 763, 764 (1981).

Plaintiff nevertheless contends that it was inappropriate for the court to have reviewed and granted defendants' motion where it had been earlier denied. Procedurally, this was not error. The court had additional materials before it. See United States v. Horton, 622 F.2d 144, 148 (5th Cir.1980) (trial judge properly reconsidered motion for summary judgment where additional material was before court); 6 J. Moore's Federal Practice § 56.14 (1986). A hearing was not required. V.R.C.P. 56(c), Reporter's Notes, 1984 amendment.

Our standard on review of a motion for summary judgment is the same standard as applied by the trial court: summary judgment is only appropriate when the materials before the court clearly show that there is no genuine issue as to any material fact. Cavanaugh v. Abbott Laboratories, 145 Vt. 516, 520, 496 A.2d 154, 157 (1985). Plaintiff submitted three theories to the trial court to establish that genuine issues of material fact existed necessitating trial. Plaintiff argued first that Nourjian was defendants' agent, second, that defendants were unjustly enriched as a result of plaintiff's materials, and third, that plaintiff was a third-party beneficiary of the Nourjian contract with defendants.

The trial court properly determined that no genuine issue of material fact existed concerning Nourjian's alleged status as defendants' agent.

Paragraph 10.1 of the Nourjian contract with defendants specified that "the contractor (Nourjian) shall supervise and direct the work, using his best skill and attention. The Contractor shall be solely responsible for all construction ... and for coordinating all portions of the work under the contract." Paragraph 10.2 provided that "the Contractor shall provide and pay for all labor, materials, [and] equipment...." Plaintiff relies heavily on the fact that Nourjian testified in deposition that he believed he was the defendants' agent. His belief, however, does not preclude the court's determination as a matter of law that no agency relationship existed, where such a determination was clear from the evidence before the court. See, e.g., Frank W. Whitcomb Construction Corp. v. Cedar Construction Co., 142 Vt. 541, 544, 459 A.2d 985, 987-88 (1983); Templeton Construction Corp. v. Kelly, 130 Vt. 420, 425, 296 A.2d 242, 245 (1972). Nourjian was an independent contractor, and the contract explicitly provided that defendants were to exercise no control over Nourjian's activities.

Plaintiff's second argument is that it is entitled to equitable relief because defendants have been unjustly enriched through the use of materials that are now part of defendants' home, and because the contractor's lien statute, 9 V.S.A. § 1921, does not provide an adequate legal remedy.

The plaintiff relies on Circus Studios, Ltd. v. Tufo, 145 Vt. 219, 485 A.2d 1261 (1984), to support its unjust enrichment claim. In Circus Studios, this Court held the defendants liable on an implied contract theory. Id. at 222, 485 A.2d at 1263. The defendants had accepted and used plaintiff's work product and dealt directly with the party to whom they were held liable. In the present case, the defendants neither accepted any materials from, nor dealt directly with, the subcontractor. Testimony indicated that the defendants did not even know with whom their general contractor would be dealing.

The equitable doctrine of unjust enrichment rests upon the principle that a person should not be allowed to enrich himself unjustly at the expense of another. Legault v. Legault, 142 Vt. 525, 531, 459 A.2d 980, 984 (1983). Examining whether defendants were unjustly enriched...

To continue reading

Request your trial
44 cases
  • In re Carter
    • United States
    • Vermont Supreme Court
    • February 27, 2004
    ...summary judgment motion because a decision denying summary judgment is not a final judgment. See Morrisville Lumber Co. v. Okcuoglu, 148 Vt. 180, 182, 531 A.2d 887, 888 (1987). For purposes of petitioner's challenge to his conviction, the record in the superior court consists only of the re......
  • In re Carter, No. 01-502
    • United States
    • Vermont Supreme Court
    • February 27, 2004
    ...summary, judgment motion because a decision denying summary judgment is not a final judgment. See Morrisville Lumber Co. v. Okcuoglu, 148 Vt. 180, 182, 531 A.2d 887, 888 (1987). For purposes of petitioner's challenge to his conviction, the record in the superior court consists only of the r......
  • James G. Davis Constr. Corp. v. FTJ, Inc.
    • United States
    • Virginia Supreme Court
    • May 14, 2020
    ...have typically denied recovery where the owner in fact paid on its contract with the general contractor."); Morrisville Lumber Co. v. Okcuoglu , 148 Vt. 180, 531 A.2d 887, 889 (1987) ("The retention of a benefit is not unjust where defendants have paid for it. Defendants were not unjustly e......
  • Continental Bank, Nat. Ass'n v. Village of Ludlow
    • United States
    • U.S. District Court — District of Massachusetts
    • October 31, 1991
    ...debt to another. Pike Ind. Inc. v. Middlebury Associates, 140 Vt. 67, 70-71, 436 A.2d 725, 727 (1981); Morrisville Lumber Co. Inc. v. Okcuoglu, 148 Vt. 180, 184, 531 A.2d 887, 890 (1987); Falzarano v. United States, 607 F.2d 506, 511 (1st Cir. 1979) (interpreting the National Housing Act, 1......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT