Moulden & Sons, Inc. v. Osaka Landscaping & Nursery, Inc.

Decision Date23 August 1978
Docket NumberNo. 2715-II,2715-II
Citation21 Wn.App. 194,584 P.2d 968
CourtWashington Court of Appeals
Parties, 25 UCC Rep.Serv. 454 MOULDEN & SONS, INC., a corporation, Respondent, v. OSAKA LANDSCAPING & NURSERY, INC., a corporation, Appellant.

John W. Dayhoff, Tacoma, for appellant.

Duane S. Radliff, Enumclaw, for respondent.

SOULE, Judge.

Plaintiff brought an action to recover the unpaid portion of the price of a quantity of cinders delivered to the defendant. Defendant counterclaimed for expenses incurred because the plaintiff initially delivered cinders which failed to meet the size specifications. Plaintiff recovered on its action and defendant's claim was dismissed. Defendant appeals the dismissal of its counterclaim.

In July of 1973, Osaka Landscaping & Nursery, Inc., (defendant), placed an oral order with Moulden & Sons, Inc., (plaintiff), for the delivery of cinders which were to be no larger than 1/4 inch in size. These cinders were to be used in fulfilling a contractual obligation of the defendant, as a subcontractor, to install a playfield for the Mukilteo School District. The cinders were delivered to the work site in August and September of 1973. Defendant spread the cinders and installed the playfield. Following the annual rainy season of 1973-74 and the children's use of the playground, it was discovered that substantial portions of the cinders were larger than the size ordered. This resulted in the children receiving scratches as they played on the cinder playfield. The school district informed the contractor and defendant of this nonconformity. Defendant, in turn, notified plaintiff in September of 1974. 1 Subsequently, by a letter dated November 6, 1974, defendant demanded that plaintiff correct the problem or defendant would do so and charge plaintiff for the expense.

Plaintiff then made an unsuccessful attempt at sifting out the larger cinders. Finally, in December of that year, plaintiff agreed to replace the cinders at its own expense. However, the parties gave conflicting evidence as to who was to bear the cost of regrading the cinders. Plaintiff contended that defendant had agreed to hire one Fred LaCount to perform this task and assume the cost thereof. Defendant testified that he only suggested that LaCount be hired to do the work, but did not agree to bear the cost of such a hiring. Nevertheless, in January, 1975, LaCount performed the bulk of the grading necessary for the reinstallation of the playfield. He apparently returned in the following May to provide some finishing touches. On June 11, LaCount tendered a bill for his services to defendant, who, in turn, deducted this cost (plus the cost of extra labor incurred as a result of the breach) from the amount due to plaintiff on the original contract and tendered payment for the difference to plaintiff on July 30. Plaintiff rejected that tender and this action resulted.

The only issue raised on appeal is whether the trial court correctly denied defendant's counterclaim for the cost of LaCount's regrading plus the extra labor costs incurred due to the plaintiff's breach. 2

Defendant's counterclaim was denied apparently on the basis that: (1) plaintiff had cured the breach; and (2) the defendant had failed to make a seasonable demand for reimbursement of the expense of reinstalling the playfield. Defendant argues that the plaintiff had no right to "cure" the breach since this was a revocation of acceptance situation, and that its demand for reimbursement was seasonable. We reverse the trial court's denial of defendant's counterclaim for the reasons set out below.

Defendant initially contends that a seller has no right to provide any "cure" in a revocation situation. While such a contention is not without support, 3 there is also authority to the contrary. 4 However, under the facts of this case, we need not decide that question. While a seller may not have a right to cure the nonconformity in a revocation situation, the defendant by its letter of November 6, 1974, conferred upon the plaintiff-seller the opportunity to cure the breach. As a result, the primary issue in this case comes down to whether the plaintiff did "cure" the breach as that term is used in RCW 62A.2-508.

The trial court stated as a finding of fact, that the plaintiff had cured the breach. The fact that a court designates its determination as a "finding" does not make it so if it is in reality a conclusion of law. Under Washington practice, a conclusion of law mislabeled as a finding, will be treated as a conclusion. McClendon v. Callahan, 46 Wash.2d 733, 284 P.2d 323 (1955); Hauser v. Arness, 44 Wash.2d 358, 267 P.2d 691 (1954); 2 Orland, Wash.Prac., § 311, p. 338, n. 38 (1972).

In Leschi v. Highway Comm'n., 84 Wash.2d 271, at 283, 525 P.2d 774, 783 (1974), a finding of fact was defined as an

assertion that a phenomenon has happened or is or will be happening independent of or anterior to any assertion as to its legal effect.

In applying that definition to the facts at hand, it is clear that whether the plaintiff had provided new cinders would be a finding of fact. However, whether the replacement of the cinders constituted a "cure" is a determination of the legal effect of that action and is thus a conclusion of law. 5 Therefore, the pertinent standard of review is whether the conclusion of law, that a cure resulted, is supported by the evidence. McClendon v. Callahan, supra.

Since the Uniform Commercial Code does not define the term "cure," resort must be made to other case law and the policy of the Code's remedy provisions. A case which concerned substantially similar issues as the one at hand was Great American Music Machine, Inc. v. Mid-South Record Pressing Co., 393 F.Supp. 877, 882 (D.C.Tenn.1975). In that case, the defendant was under contract to manufacture and supply to the plaintiff a large quantity of record albums. When the albums were received, an inspection revealed substantial defects. Defendant agreed to replace the albums with a new pressing. Plaintiff accepted this replacement delivery and brought suit for, among other things, the incidental expense of the extra handling costs attributable to the defective first pressing. The court allowed recovery of these expenses, finding that the mere

delivery of the second batch of records did not constitute a cure within the meaning of . . . (RCW 62A.2-508) . . . as the damage had already occurred and the time set for performance had expired.

In the case before us, once the initial delivery was found to be nonconforming, the buyer had incurred the damage of the inevitable cost of regrading the replacement cinders and unless that damage was remedied as well as the goods replaced, the buyer would not be put into the same position as if no breach had occurred, thus no cure could result.

This analysis is in line with the policy of the Code of providing remedies which place the nonbreaching party in the...

To continue reading

Request your trial
59 cases
  • Robel v. Roundup Corp.
    • United States
    • Washington Supreme Court
    • December 12, 2002
    ...of law and fact because "curtilage" could only be determined by examining facts of case); Moulden & Sons, Inc. v. Osaka Landscaping & Nursery, Inc., 21 Wash.App. 194, 197, 584 P.2d 968 (1978) (holding trial court's finding of fact that plaintiff had cured the breach was actually a conclusio......
  • Palm Bay Int'l, Inc. v. Marchesi Di Barolo S.P.A.
    • United States
    • U.S. District Court — Eastern District of New York
    • July 11, 2011
    ...& Co. v. Wendell J. Miller Mortgage Company, Inc., 457 F.Supp. 996, 999 (S.D.N.Y.1978). In Moulden & Sons, Inc. v. Osaka Landscaping & Nursery, Inc., 21 Wash.App. 194, 584 P.2d 968 (1978), the incidental damages complained of necessarily arose with the discovery of the nonconforming goods. ......
  • Continental Ins. Co. v. Paccar, Inc.
    • United States
    • Washington Court of Appeals
    • July 21, 1980
    ...Pac. Ins. Co., 2 Wash.App. 985, 992-93, 472 P.2d 611 (1970). We will treat it as such. Moulden & Sons, Inc. v. Osaka Landscaping & Nursery, Inc., 21 Wash.App. 194, 197, 584 P.2d 968 (1978). In order for the trial court to have concluded that an ambiguity was created by Continental's cancell......
  • Casterline v. Roberts
    • United States
    • Washington Court of Appeals
    • May 15, 2012
    ...fact are determinations of “whether ... evidence show[s] that something occurred or existed.” Moulden & Sons, Inc. v. Osaka Landscaping & Nursery, Inc., 21 Wash.App. 194, 197, 584 P.2d 968 (1978). Conclusions of law are “determination [s] ... made by a process of legal reasoning from facts ......
  • Request a trial to view additional results
1 books & journal articles

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT