Mountain Envtl., Inc. v. Abatement Int'l/Advatex Assocs., Inc.

Decision Date02 July 2003
Docket NumberNo. 2002–629.,2002–629.
Citation149 N.H. 671,826 A.2d 556
CourtNew Hampshire Supreme Court
Parties MOUNTAIN ENVIRONMENTAL, INC., v. ABATEMENT INTERNATIONAL/ADVATEX ASSOCIATES, INC. and another.

Cook & Molan, P.A., of Concord (Frank E. Kenison on the brief and orally), for the plaintiff.

Rath, Young and Pignatelli Professional Association, of Concord (Brian T. Tucker on the brief and orally), for the defendants.

DUGGAN, J.

The defendants, Abatement International/Advatex Associates, Inc. (Advatex) and the American Guarantee and Liability Insurance Corp. (AGLIC), appeal orders of the Superior Court (Abramson , J.) denying in part their motion to dismiss and granting the motion for summary judgment of the plaintiff, Mountain Environmental, Inc. (Mountain). The defendants raise several issues involving Mountain's claim against a performance bond obtained by Advatex and guaranteed by AGLIC, while Mountain cross-appeals the court's granting in part the defendants' motion for summary judgment. On the basis of Advatex's first issue, regarding Mountain's failure to comply with statutory notice procedures, we reverse.

The background of this case is substantially similar to that of Fastrack v. Abatement International, 149 N.H. 661, 827 A.2d 1019, 2003 WL 21503438 (2003), which we also decide today. Advatex is the general contractor for an asbestos abatement and building demolition contract at the Pease International Tradeport, under a contract with the Pease Development Authority (PDA), a political subdivision of the State of New Hampshire. Advatex obtained a bond, with AGLIC acting as surety, guaranteeing payment for all labor, equipment, materials and services used in PDA contracts up to $1,660,000.

Advatex subcontracted many of its duties to New Hampshire Demolition (NHD), which in turn subcontracted much of its asbestos abatement work to Mountain. The subcontract between NHD and Mountain dictated that NHD would pay Mountain $124,800 for its work. Mountain performed its duties, but NHD only paid $41,000 of the contract price.

After failing to collect the balance of $83,800 from NHD, Mountain sought to collect from the defendants under their bond. Pursuant to procedures outlined within the bond itself, Mountain sent a certified notice of its claim to Advatex, AGLIC, NHD and the PDA. Neither Advatex nor AGLIC made or denied payment for any amount due. Accordingly, Mountain filed suit in the superior court on February 5, 2001, requesting damages for the outstanding balance of the contract price. Mountain subsequently amended its suit to include an additional claim for the amount of the judgment that one of Mountain's subcontractors, Fortuna Stone of Maine, had obtained against it.

The defendants moved to dismiss, arguing that because the bond for the PDA project was required under RSA 447:16 (2002), Mountain was obligated to follow the statutory notice procedures for statutory bonds set forth in RSA 447:17 (2002) and RSA 447:18 (2002)—specifically, the requirement that a claimant file a notice with the clerk of the superior court. The court denied the motion in part, finding that (1) Mountain had "substantially complied" with the statutory requirements, and (2) the bond's express terms for notice, in any case, waived the statutory requirements. The court, however, granted the second part of the defendant's motion, dismissing the portion of the claim representing Fortuna Stone's judgment. In a later order, the court granted summary judgment for Mountain on its claim for $83,800.

On appeal, the defendants challenge the denial in part of their motion to dismiss, and the granting of summary judgment in favor of Mountain, while Mountain cross-appeals the dismissal of the Fortuna Stone claim.

We first consider the issue of notice. The defendants argue that Mountain's claim must be dismissed because it did not comply with the statutory notice procedures of RSA 447:17 and RSA 447:18. Because this case involves the same bond and the same statutes as Fastrack , we incorporate the reasoning of that case, and reject the waiver and substantial compliance arguments relied upon by the court below. See Fastrack, 149 N.H. at ––––, 727 A.2d 1019. We turn, thus, to the alternative grounds for affirmance advanced by Mountain.

Mountain claims that it complied with these statutes because both the superior court and the defendants had "actual notice" of its claim within the statutory deadlines. It also contends that its commencement of suit against the defendants in the superior court on February 5, 2001, was the functional equivalent of filing a claim with the clerk of the superior court as required by RSA 447:17.

The trial court's interpretation of a statute is a question of law, which we review de novo . See Crowley v. Frazier, 147 N.H. 387, 389, 788 A.2d 263 (2001). Likewise, the interpretation of a contract, such as the bond at issue, is ultimately a question of law for this court to decide. See Appeal of Reid, 143 N.H. 246, 249, 722 A.2d 489 (1998).

Th...

To continue reading

Request your trial
2 cases
  • Gen. Insulation Co. v. Eckman Constr.
    • United States
    • New Hampshire Supreme Court
    • January 28, 2010
    ...is to provide parties with an opportunity to settle the claim without resorting to litigation." Mountain Envtl. v. Abatement Int'l/Advatex Assocs., 149 N.H. 671, 674, 826 A.2d 556 (2003). Another purpose is to allow the prime contractor to pay his subcontractors "without fear of additional ......
  • Lone Pine Hunters' Club, Inc. v. Town of Hollis
    • United States
    • New Hampshire Supreme Court
    • July 2, 2003

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT