Murdock Mach. & Engineering Co. of Utah v. U.S.

Decision Date26 April 1989
Docket NumberNo. 88-1287,88-1287
Citation873 F.2d 1410
Parties35 Cont.Cas.Fed. (CCH) 75,653 MURDOCK MACHINE & ENGINEERING COMPANY OF UTAH, Appellant, v. The UNITED STATES, Appellee.
CourtU.S. Court of Appeals — Federal Circuit

Robert H. Koehler, Patton, Boggs & Blow, Washington, D.C., argued, for appellant. With him on the brief, was Joseph S. Mahaley.

James M. Kinsella, Commercial Litigation Branch, Dept. of Justice, Washington, D.C., argued, for appellee. With him on the brief, were John R. Bolton, Asst. Atty. Gen., David M. Cohen, Director and Thomas W. Petersen, Asst. Director. Also on the brief, was Martha A. Klein, Sr. Trial Atty., Office of Counsel, Dept. of the Navy, of counsel.

Before BISSELL, Circuit Judge, BALDWIN, Senior Circuit Judge, and MAYER, Circuit Judge.

BISSELL, Circuit Judge.

Murdock Machine & Engineering Company of Utah (Murdock) appeals from the decisions of the Armed Services Board of Contract Appeals (ASBCA), Murdock Mach. & Eng'g Co. of Utah, ASBCA Nos. 20409, 27860, 28031, 88-1 BCA p 20,354 (1987), denying Murdock's consolidated appeals. We reverse the ASBCA's decisions in Appeal Nos. 27860 and 28031 and remand. The jurisdictional question raised in Appeal No. 20409 need not be reached because of our reversal in the other two appeals. Appeal No. 20409, accordingly, is dismissed.

BACKGROUND

A more detailed background appears in the ASBCA's opinion. See id. In 1971, the government awarded Murdock a $10,659,612 fixed-price contract for supplying the United States Navy (Navy) with anti-submarine rocket (ASROC) launchers and related spare parts. Early in the performance of the contract, Murdock experienced substantial production problems, fell behind in its delivery schedule, and informed the Navy that contract performance could On April 7, 1975, the NCAB granted Public Law 85-804 relief and converted the contract to a cost reimbursement/no-fee contract. The NCAB prepared and sent a draft decision to Murdock for comment, verbally notified Murdock and the Navy of its decision, and advised the parties to promptly initiate actions to comply with the requirements established by the decision.

not be continued due to lack of financial resources. Concerned with timely receipt of ASROC launchers for new ships, the Navy procuring command provided Murdock with a $2,500,000 government-guaranteed loan and encouraged Murdock to apply for extraordinary contractual relief pursuant to Public Law 85-804, 50 U.S.C. Secs. 1431-35 (1982). After evaluating Murdock's request, the Navy procuring command recommended that the Navy Contract Adjustment Board (NCAB) grant Public Law 85-804 relief and convert Murdock's contract to a cost reimbursement/no-fee contract because continued production of the ASROC launchers was "essential to the national defense."

Shortly thereafter, the Navy located another source of ASROC launchers, thus, obviating the need for production of new launchers by Murdock. The Navy procuring command notified Murdock and the NCAB that the command was withdrawing its recommendation for Public Law 85-804 relief because the ASROC contract was no longer "essential to the national defense." On April 17, 1975, the contracting officer (CO) sent Murdock a 10 day right to cure notice, and on May 16, 1975, terminated the contract for default because of Murdock's financial inability to perform and its anticipatory breach. Murdock appealed the CO's decision (No. 20409). Murdock filed for bankruptcy and its trustee submitted another claim alleging breach of contract by the Navy. When the CO failed to issue a decision, Murdock appealed (No. 27860). After the CO issued a decision, Murdock appealed a second time (No. 28031). The ASBCA denied Murdock's consolidated appeals. Murdock, 88-1 BCA p 20,354 at 102,935.

OPINION

Murdock contends that the Navy's termination for default of its contract to produce rocket launchers was improper in that the government materially breached the contract under terms established by the April 7, 1975 decision of the NCAB. We agree.

In Appeal Nos. 27860 and 28031, the ASBCA held that the April 7, 1975, decision of the NCAB was not "self-executing." Because the NCAB's decision (1) had not been communicated to the appropriate officer for implementation, (2) was not implemented by a contractual document, and (3) was not signed by the NCAB chairman, all of which were required by regulation, the decision was not final. Id. (citing Armed Services Procurement Regulations (ASPR) Secs. 17-202.2, 17-208.4(a), (b), and 17-208.2(b)(ii) (1973), see 1973 Gov't Cont.Rep. (CCH) p 35,252-257.56, which have been superseded by the Federal Acquisition Regulations located in Title 48, Chapter 1, subpart 50, of the Code of Federal Regulations).

As to the first point, ASPR 17-208.4 only requires that the NCAB's decision be communicated to the appropriate official. Regulation 17-208.4 neither suggests nor supports that a decision does not become final until such communication occurs.

The ASBCA cited ASPR Sec. 17-208.2(b)(ii) as necessitating implementation by contractual document before the decision could be considered final. This section only requires that the contractual documents implementing the decision be submitted to the Naval Sea Systems Command "within 30 days after the close of the month during which it is executed." Id. None of the regulations cited by the ASBCA require implementation by a contractual document before the NCAB's decision could be considered final.

We also disagree with the ASBCA that a decision of the NCAB could not be final without the chairman's signature. See ASPR 17-208.4. There is nothing in the regulations that permits the chairman to act other than in accordance with the NCAB's decision. The chairman possesses no independent authority to reconsider, modify, correct, or reverse the decisions of the NCAB. See ASPR 17-202.2.

The ASBCA erred. The NCAB's April 7, 1975, decision was final and converted the fixed-price contract to a cost reimbursement/no-fee contract that obligated the government to pay Murdock its costs incurred in performing the contract. (

*) The government materially breached the contract by failing to reimburse Murdock. That breach relieved Murdock of the default termination and its consequences. Malone v. United States, 849 F.2d 1441, 1446 (Fed.Cir.1988). The termination for default clause in Murdock's contract, see 32 C.F.R. Secs. 7.103-11, 8.707 (1971), automatically converted Murdock's wrongful default termination into a termination for convenience. Id. A remand to the ASBCA is proper for a determination of quantum under the contract's termination for convenience clause. See 32 C.F.R. Secs. 7.103.21(c), 8.701(a) (1971).

COSTS

The government shall pay Murdock's costs.

REVERSED-IN-PART, DISMISSED-IN-PART, and REMANDED.

BALDWIN, Senior Circuit Judge, concurring in the result.

I concur in the result reached in appeals 27860 and 28031. Although I agree that appeal 20409 must be dismissed, I disagree that the government's motion to dismiss for lack of subject matter jurisdiction need not be reached. Ante at 1. I therefore write separately.

The government has moved this court to dismiss appeal 20409 for lack of subject matter jurisdiction. On June 3, 1988, the court denied, without prejudice, the government's initial motion. That motion was renewed in the briefs and at oral argument. The majority seeks to ignore this motion by refusing to "reach" the question. Appeal 20409 is then dismissed without explanation or reason. As Justice Rehnquist (joined by Chief Justice Burger and Justice Powell) remarked when dissenting from the Court's summary affirmance in Buchanan v. Evans, 423 U.S. 963, 96 S.Ct. 381, 46 L.Ed.2d 293 (1975), "[m]y dissent from that sort of [action] is based on my conviction that it is extraordinarily slipshod judicial procedure as well as my conviction that it is incorrect." Id. at 975, 96 S.Ct. at 387.

I fail to understand how the court cannot reach the question of subject matter jurisdiction, as it is the first consideration in all cases. See, e.g., Mansfield, Coldwater & Lake Michigan Ry Co. v. Swan, 111 U.S. 379, 4 S.Ct. 510, 28 L.Ed. 462 (1884). Unlike the majority, I would grant the...

To continue reading

Request your trial
6 cases
  • U.S. v. Murdock Mach. and Engineering Co. of Utah
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • April 3, 1996
    ...1987 WL 46273. On appeal, the United States Court of Appeals for the Federal Circuit reversed. Murdock Mach. & Eng'g Co. v. United States, 873 F.2d 1410, 1413 (Fed.Cir.1989). The Federal Circuit held that the NCAB's April 1975 decision on Murdock's P.L. 85-804 Request was final and converte......
  • Fort Howard Senior Hous. Assocs., LLC v. United States
    • United States
    • U.S. Claims Court
    • May 29, 2015
    ...if the contractor can establish that the government materially breached the contract. See Murdock Mach. & Engineering Co. of Utah v. United States, 873 F.2d 1410, 1413 (Fed. Cir. 1989) (citing Malone v. United States, 849 F.2d 1441, 1446 (Fed. Cir. 1988)). Tested by these standards, the cou......
  • Murdock Mach. and Engineering Co. of Utah, In re, 92-4022
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • April 6, 1993
    ...claims for relief. The trustee then took the case to the Federal Circuit, which reversed the ASBCA. Murdock Mach. & Eng'g Co. v. United States, 873 F.2d 1410, 1413 (Fed.Cir.1989). That court held that the ASROC contract had in fact been converted into a cost-reimbursement/no fee contract an......
  • International Gunnery Range Services, Inc. v. Widnall, 94-1444
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • August 24, 1995
    ...final and not subject to review, either by an agency board of contract appeals or by a court. Murdock Machinery & Engineering Co. of Utah v. United States, 873 F.2d 1410, 1413 n. 1 (Fed.Cir.1989); Coastal Corp. v. United States, 713 F.2d 728, 731 In attempting to show that it was not exceed......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT