Myers v. Mundelein College

Decision Date11 June 2002
Docket Number No. 1-99-4129., No. 1-99-3190
Citation265 Ill.Dec. 154,771 N.E.2d 1113,331 Ill. App.3d 710
PartiesJudith R. MYERS, Yohoma Gray and Elvira Fernandez Hasty, Plaintiffs-Appellants, v. MUNDELEIN COLLEGE, Defendant-Appellee.
CourtUnited States Appellate Court of Illinois

Arthur J. O'Donnell and Kenneth N. Flaxman, Chicago, for Appellant.

Ellen M. Babbitt and Bruce W. Melton of Babbitt & Melton, Chicago, for Appellee.

Justice CAHILL delivered the opinion of the court:

This is the third appeal arising from breach of contract claims brought by three plaintiffs against defendant Mundelein College. The facts that underlie this present appeal are set out in Gray v. Loyola University of Chicago, 274 Ill.App.3d 259, 264, 210 Ill.Dec. 330, 652 N.E.2d 1306 (1995) (Gray I), and Gray v. Mundelein College, 296 Ill.App.3d 795, 695 N.E.2d 231 Ill.Dec. 260, 695 N.E.2d 1379 (1998) (Gray II). A final order conforming to the two appellate opinions was filed on January 11, 1999. No one appealed the order, which finally determined that Mundelein was liable for contract damages through 1996 in the case of plaintiffs Gray and Hasty, and that Mundelein had breached its contract with Myers. Myers had never sought damages.

Subsequently, on June 23, 1999, Gray and Hasty filed a motion asking for damages for the years 1997 and 1998. Myers field a motion under section 2-701(c) of the Illinois Code of Civil Procedure (Code) (735 ILCS 5/2-701(c) (West 2000)), asking for damages dating back to 1996. The chancery division judge who heard these motions' denied them, finding that he no longer had jurisdiction. Gray and Hasty did not appeal this order. Myers moved for reconsideration, and after denial, filed an appeal.

Gray and Hasty meanwhile filed a new complaint in chancery. This complaint alleged that Gray and Hasty were tenured faculty members entitled to lifetime employment by Mundelein, an obligation Mundelein breached. Copies of the chancery court's order and our decision in Gray II were attached as exhibits. The complaint alleged that damages incurred through December 31, 1996, had been awarded. The complaint sought a declaration that Gray and Hasty were entitled to damages for lost earnings from January 1, 1997, to the present. Mundelein moved to dismiss the complaint under section 2-615 of the Code. 735 ILCS 5/2-615 (West 2000). Mundelein argued that the complaint failed to state a claim amenable to declaratory judgment relief but, rather, was an action at law. The trial court dismissed the complaint under section 2-615. The trial court concluded that "plaintiffs have an action at law for further damages incurred due to the breach which is only proper in the Law Division."

Gray and Hasty argue on appeal that the dismissal of their declaratory judgment action was in error because there is an actual controversy between the parties arising from Mundelein's refusal to concede liability for future lost earnings caused by its breach of contract.

Myers' appeal challenges the denial of her motion in the original chancery action for additional relief under section 2-701(c) of the Code. Myers claims that the trial court has the power and the duty to grant monetary relief under section 2-701(c) of the Code. Mundelein responds that Gray and Hasty's future damage claims are not cognizable under the declaratory judgment act because only legal, not equitable, relief is sought. Mundelein contends with respect to Myers that her claim for damages is barred by our decision in Goldberg v. Valve Corp. of America, 89 Ill.App.2d 383, 233 N.E.2d 85 (1967). Mundelein alternatively argues that Myers' claim for damages is barred by the law of the case, based on our statement in Gray II that Myers was entitled only to declaratory and injunctive relief Gray II, 296 Ill.App.3d at 809-10, 231 Ill.Dec. 260, 695 N.E.2d 1379.

We entered an order consolidating the appeals. As to Gray and Hasty, we must determine whether the claim may proceed in the chancery division as a declaratory judgment action or must be pursued in the law division as a complaint for damages arising out of a breach of contract. As to Myers, we must determine whether section 2-701(c) entitled her to make a present claim for money damages where she failed to seek them in the original action.

Gray and Hasty argue that whether they are entitled to future damages is uncertain under Illinois law, giving rise to an actual controversy that "can only be solved through a declaratory judgment." We disagree.

Gray and Hasty claim that a federal district case, Lewis v. Loyola University of Chicago, No. 87 C 6329, 1988 WL 9094 (N.D.Ill.1988), aff'd, Lewis v. Loyola University of Chicago, 872 F.2d 424 (7th Cir. 1989), interpreted Illinois law to bar a second claim for damages from a breach of contract for which damages had already been awarded. Gray and Hasty contend that, if they had filed an action at law seeking damages, Mundelein would have made the same arguments as those in Lewis and that "these arguments, and the dispute about [Gray and Hasty's] entitlement to posttrial damages, present an `actual controversy' that is appropriately resolved in a declaratory judgment action." The contention overlooks a well-settled rule that a declaratory judgment action should not be used to secure advisory opinions or legal advice with respect to future litigation. Messenger v. Edgar, 157 Ill.2d 162, 170, 623 N.E.2d 310, 191 Ill.Dec. 65, 623 N.E.2d 310 (1993). The actual controversy requirement ensures that a court will not pass judgment on abstract propositions of law. Messenger, 157 Ill.2d at 170-71, 191 Ill. Dec. 65, 623 N.E.2d 310. We find Slack v. City of Salem, 31 Ill.2d 174, 201 N.E.2d 119 (1964), analogous.

In Slack, the plaintiff filed a complaint to restrain the holding of a referendum to approve or disapprove the issuance of revenue bonds. The plaintiff also sought a declaration that the statute authorizing the referendum was unconstitutional. Slack, 31 Ill.2d at 175, 201 N.E.2d 119. Our supreme court found that, until the voters approved the referendum to issue the bonds, "there is no controversy that is ripe for a declaratory judgment." Slack, 31 Ill.2d at 178, 201 N.E.2d 119. Similarly here, a court cannot make a finding on the effect of the Lewis case on Gray and Hasty's claim for damages unless and until the issue is raised by Mundelein.

We note that whether Gray and Hasty are entitled to posttrial damages arising from Mundelein's breach of contract does not turn solely on an interpretation of Lewis, but on an analysis of a rule first established in Hamlin, Hale & Co. v. Race, 78 Ill. 422 (1875), that damages for breach of contract beyond the date of trial are barred as speculative. This rule was reaffirmed in Mount Hope Cemetery Ass'n v. Weidenmann, 139 Ill. 67, 28 N.E. 834 (1891), and later modified in Doherty v. Schipper & Block, 250 Ill. 128, 95 N.E. 74 (1911), when our supreme court held that all damages for breach of contract must be recovered in a single action, barring future actions for damages. A subsequent appellate case, Corby v. Seventy-One-Hundred Jeffery Avenue Building Corp., 325 Ill. App. 442, 60 N.E.2d 236 (1945), did not follow Doherty.

In Corby, the plaintiff entered into an employment contract with the defendant that began on December 15, 1938, and ended on. July 15, 1948. The plaintiff sued for breach when he was terminated on September 19, 1940, two years into the 10-year term of employment. Corby, 325 Ill. App, at 445-46, 60 N.E.2d 236. After a December 31, 1942, bench trial, the plaintiff was awarded damages from September 19, 1940, the date of termination to July 15, 1948, the date of expiration of the contract. Corby, 325 Ill. App. at 455, 60 N.E.2d 236. The damage award was reversed on appeal. The Corby court found that, because the employment might be properly terminated at any time between the date of trial and the expiration date, damages after the date of trial "would be largely speculative." Corby, 325 Ill. App. at 457, 60 N.E.2d 236. In limiting the plaintiff to accrued damages as of the date of trial, the Corby court, citing to Mount Hope, said that the plaintiff could institute future proceedings "from time to time * * * for damages that he may have sustained, or he may wait until the expiration of the contract and recover for such damages, if any." Corby, 325 Ill. App. at 457, 60 N.E.2d 236.

These cases make clear that there is a difference between damages for events that have not yet occurred (and may never occur) and a new action for damages that have accrued since the original action was terminated. Illinois law clearly proscribes claims for damages that have not yet occurred, so-called "future damages." See Schoeneweis v. Herrin, 110 Ill.App.3d 800, 808, 66 Ill.Dec. 513, 443 N.E.2d 36 (1982); Jackson v. Hammer, 274 Ill.App.3d 59, 64, 210 Ill.Dec. 614, 653 N.E.2d 809 (1995) (damages may not be speculative, remote or uncertain). But the term "future" damages here is imprecise as to Gray and Hasty, who seek to recover damages that accrued after the first case was decided— subsequent lost income as a...

To continue reading

Request your trial
4 cases
  • Djikas v. Grafft
    • United States
    • United States Appellate Court of Illinois
    • 27 Octubre 2003
    ...originally decided so as to render the original decision nonfinal and nonappealable. See Myers v. Mundelein College, 331 Ill.App.3d 710, 712, 265 Ill.Dec. 154, 771 N.E.2d 1113, 1114 (2002) (request for further relief in the form of monetary damages proper even though filed approximately six......
  • Chelkova v. Southland Corp.
    • United States
    • United States Appellate Court of Illinois
    • 11 Junio 2002
  • DB Real Estate Assets I, LLC v. Dinatale
    • United States
    • United States Appellate Court of Illinois
    • 2 Septiembre 2014
    ...after the declaration of rights, although not previously prayed for by a complaint or counterclaim." Id.; Myers v. Mundelein College, 331 Ill. App. 3d 710, 715-16 (2002) (holding that a plaintiff who succeeded in obtaining a declaratory judgment was permitted to seek additional relief in th......
  • Bd. of Managers of Hidden Lake Townhome Owners Ass'n v. Green Trails Improvement Ass'n
    • United States
    • United States Appellate Court of Illinois
    • 20 Mayo 2014
    ...Burgard, 6 Ill. App. 2d at 219; see also Pacemaker Food Stores, Inc., 143 Ill. App. 3d at 785 (quoting Burgard); Myers v. Mundelein College, 331 Ill. App. 3d 710, 715-16 (2002) (holding that a plaintiff who succeeded in obtaining a declaratory judgment was permitted to seek additional relie......