N. Fiorito Co. v. State

Decision Date27 October 1966
Docket NumberNo. 37780,37780
Citation419 P.2d 586,69 Wn.2d 616
PartiesN. FIORITO COMPANY, a corporation, Appellant, v. The STATE of Washington, Respondent.
CourtWashington Supreme Court

Short, Cressman & Cable, Paul R. Cressman, William L. Hintze, Seattle, for appellant.

John J. O'Connell Atty. Gen., John J. Champagne, Asst. Atty. Gen., Olympia, for respondent.

HAMILTON, Judge.

Appellant (plaintiff) a heavy construction contractor, commenced this action against respondent, the State of Washington, seeking to recover added expenses and penalties incurred due to delay in completion of a highway construction contract. Trial was had before the court sitting without a jury. At the conclusion of appellant's case, the trial court granted respondent's motion for an involuntary nonsuit, and thereafter entered findings of fact, conclusions of law, and judgment dismissing appellant's action. This appeal followed.

The crucial and decisive issue in this case is factual. Appellant alleged and contends that the delay in completing the contract in question was occasioned by respondent's failure to promptly evolve a remedy for a slide condition occurring on and during the highway construction project. Respondent, on the other hand, asserts the delay was caused by appellant's failure to diligently prosecute the work. The trial court, in ruling upon respondent's motion, weighed and evaluated the testimony and exhibits adduced during appellant's presentation and resolved the factual issue adversely to appellant, stating in the course of and at the conclusion of an oral decision:

The record establishes that the slide was a mere incident in the performance of this contract and it was not the cause of the delay except in a very minor degree and that the real cause of the failure to perform within the time limit was: lack of effort; lack of attention; lack of sufficient personnel or equipment or both on the job.

* * * Upon the whole record we find as a fact, that the slide was only an incident encountered in the construction work and that it was in no sense the cause of the contractor, Plaintiff, failing to complete the job until June 22, 1961, as indicated in the complaint.

Thereafter, the trial court entered findings of fact embracing all essential facts, including the following:

That on or about July 29, 1959, a slide occurred between stations 19 and 24, which slide occurred through no fault of any of the parties hereto. That on or about August 1, 1959, the defendant, State of Washington, changed the grade on the highway to be constructed under said contract at the point of said slide. That as a result of said grade change, substantially less material had to be removed by the plaintiff contractor. That at sometime between July 29, 1959, and August 18, 1959, the defendant, State of Washington, provided the plaintiff contractor with a method of slide removal, and that during said period substantially all of the plaintiff personnel and equipment were working at full capacity. Finding of Fact No. 7.

That at the time that the slide occurred on July 29, 1959, the plaintiff contractor was substantially behind in his progress under said contract and that said slide created only a minimum disturbance in the contract progress schedule. Finding of Fact No. 9.

Upon appeal, appellant assigns error to the foregoing findings and the granting of nonsuit. With respect to its assignments of error, appellant cites Shulkin v. Zappone, 63 Wash.2d 201, 386 P.2d 133 (1963), and argues that the trial court (a) failed to consider the evidence in the light most favorable to it, (b) misconstrued pertinent evidence, and (c) made findings which are not supported by substantial evidence.

At the outset, it will be helpful to an understanding of our disposition of the appeal to once again set forth and clarify the functioning of the trial court, in a nonjury trial, in passing upon and granting a motion directed to the sufficiency of the evidence at the conclusion of a plaintiff's case. As we stated in O'Brien v. Schultz, 45 Wash.2d 769, 278 P.2d 322 (1954), such a motion under appropriate circumstances may be granted for two very distinct and different reasons.

One, the trial court may Weigh the evidence properly adduced in the course and in support of plaintiff's case, and make A factual determination that plaintiff has failed to establish a prima facie case by credible evidence, or that the credible evidence establishes facts which preclude plaintiff's recovery. In so weighing the evidence, the trial court, as the trier of the facts, is not required to accept all of plaintiff's evidence as true or accord to plaintiff the most favorable inferences that may be drawn from the evidence. On the contrary, in reaching its decision as to the viability of plaintiff's case, the trial court necessarily must appraise the credibility of the testimony and the force of any exhibits, and may believe or disbelieve plaintiff's evidence, resolve testimonial conflicts, evaluate circumstantial evidence, draw reasonable and allowable inferences, and otherwise appropriately determine, as a trier of the facts, the facts revealed and sustainable by the evidence then before the court. If the trial court adopts this approach and makes apposite findings setting forth the pertinent facts as if found them to be, this court, on appeal, will accept such findings of fact as verities, unless a review of the evidence demonstrates them to be without substantial evidentiary support. And, if, in turn, the relevant and sustainable findings support the judgment of dismissal, this court will not disturb the judgment, for we cannot substitute our findings for those of the trial court. Expressions and various applications of this approach may be found in Richards v....

To continue reading

Request your trial
38 cases
  • Brewer v. Copeland
    • United States
    • Washington Supreme Court
    • 13 Noviembre 1975
    ...'35 mph was a safe speed at the time.' The court was empowered to draw reasonable inferences from that testimony. N. Fiorito Co. v. State, 69 Wash.2d 616, 419 P.2d 586 (1966); Rognrust v. Seto, 2 Wash.App. 215, 467 P.2d 204 (1970). One such inference it could draw was that had the witness h......
  • In re Dependency of Schermer
    • United States
    • Washington Supreme Court
    • 11 Octubre 2007
    ...to the plaintiff and rule, as a matter of law, that the plaintiff has failed to establish a prima facie case. N. Fiorito Co. v. State, 69 Wash.2d 616, 618-19, 419 P.2d 586 (1966); see also 4 KARL B. TEGLAND, WASHINGTON PRACTICE: RULES PRACTICE CR 41, at 55 (5th ed.2006). The court must find......
  • Peiffer v. Cutting
    • United States
    • Washington Court of Appeals
    • 18 Diciembre 2018
    ...as to how the trial court ruled, the reviewing court will look to the trial court’s oral or written opinion. N. Fiorito Co. v. State , 69 Wash.2d 616, 620, 419 P.2d 586 (1966). ¶ 59 Although the basis on which Pro-Cut moved for the dismissal is not clear, there is no doubt that the trial co......
  • Renovest Co. v. Hodges Development Corp., 89-559
    • United States
    • New Hampshire Supreme Court
    • 6 Diciembre 1991
    ...It has also been applied by courts in States where the rules of civil procedure do not include it. See N. Fiorito Co. v. State, 69 Wash.2d 616, 618-19, 419 P.2d 586, 588 (1966). We hold that when the trial judge is sitting as the trier of fact, he or she appropriately may make findings of f......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT