Nar Bus. Park, LLC v. Ozark Auto. Distribs., LLC

Citation430 F.Supp.3d 443
Decision Date30 December 2019
Docket NumberCase No. 17-cv-6223
Parties NAR BUSINESS PARK, LLC, Plaintiff, v. OZARK AUTOMOTIVE DISTRIBUTORS, LLC, Defendant.
CourtU.S. District Court — Northern District of Illinois

Michael T. Nigro, Nigro, Westfall & Gryska PC, Glendale Heights, IL, for Plaintiff.

Joseph R. Marconi, Carlos A. Vera, Johnson & Bell, Ltd., Chicago, IL, for Defendant.

MEMORANDUM OPINION AND ORDER

Robert M. Dow, Jr., United States District Judge

Before the Court are Defendant's motion for summary judgment [95] and Plaintiff's cross-motion for partial summary judgment [105] on Plaintiff's Counts I and II; Plaintiff's [113] and Defendant's [115] cross motions for summary judgment on Defendant's two counterclaims; and Plaintiff's motion for leave to file a sur-reply [111]. For the reasons set forth below, the Court grants Defendant's motion for summary judgment [95] on Plaintiff's Counts I and II, and judgment is accordingly entered in Defendant's favor on those counts. The Court also grants Plaintiff's motion for leave to file a sur-reply [111]. Plaintiff's partial cross motion for summary judgment [105] on Count I is denied. Plaintiff's and Defendant's respective cross-motions for summary judgment [113, 115] on Defendant's Counterclaims I and II are each granted in part and denied in part. Judgment is entered in Plaintiff's favor and against Defendant on Defendant's Counterclaim II. The case is set for further status on January 15, 2020 at 9:00 a.m.

I. Background

The Court takes the relevant facts from the parties' Local Rule 56.1 statements of undisputed material facts and supporting exhibits: [57], [72–73], [77], [79-1–7], [80], [85], [97], [103], [106], and [108–10]. The Court construes the facts in the light most favorable to the nonmoving party on any given issue. The following facts are undisputed unless otherwise noted. "When we cite as undisputed a statement of fact that a party has attempted to dispute, it reflects our determination that the evidence cited in the response does not show that the fact is in genuine dispute." King v. Chapman , 4 F.Supp.3d 1017, 1022 (N.D. Ill. 2013).

Plaintiff NAR purchased a large parcel ("Parcel") in Naperville, IL in 2006 or 2007. [103 at 3, ¶ 12.] The topographically low-lying land was, at the time, used for farming. [Id. ] Roughly contemporaneously, Plaintiff contracted with Naperville to excavate another (unrelated) site. [Id. , ¶ 13.] Killing two birds with one stone, Plaintiff transported the excavated land to the Parcel, filling it in. [Id. ] The extent to which Plaintiff measured the soil density in the Parcel is disputed, as are the measures taken to ensure that the land was properly filled. [Id. , ¶¶ 14–15.] The quality of excavated soil taken from the other parcel is also in dispute. [108 at 3, ¶ 5.]

Plaintiff contracted with Ozark Automotive Distributors1 on September 17, 2012; it agreed to sell the Parcel for $5,171,400. [103 at 2, ¶ 10.] The parties also agreed, however, that a condition precedent to the land sale was a construction contract. [Id. ] The construction contract contemplated a 400,000 square foot automotive distribution center upon the empty Parcel. [Id. ]; [Id. , ¶ 8.] Defendant's distribution centers receive and ship inventory to Defendant's retail stores; these centers generally service dozens of stores. [80 at 8, ¶ 13.]

Before the construction contract was executed, Defendant hired a geotechnical engineering consultant, Terracon Consultants, Inc. ("Terracon"), to test the soil and determine the feasibility of completing a construction project on the Parcel. [103 at 4, ¶ 16.] Terracon tested 24 soil-depths at various locations on the Parcel and submitted a report on March 15, 2013 that summarized its findings. [Id. at 5, ¶ 17]; see also generally [97 - 6]. Terracon was concerned about the existing fill, finding that the "composition, moisture content and standard penetration test blow counts * * * were variable" and therefore unsuitable for laying foundations for the construction project. See [97 - 6 at 10]; see also [103 at 5, ¶¶ 18–19]. Terracon recommended that the foundation not be built on the existing fill, and instead opined that "excavations for the building foundations should extend through the fill to the underlying native soils." [103 at 5, ¶ 18]. Terracon also recommended that if these excavations uncovered soft or low-density native soils, then the native soils should be excavated until "suitable bearing soils" were uncovered. [103 at 5, ¶ 19]. The Terracon Report was included in the bidding documents, and Plaintiff admits that it received the report and never objected or requested clarification. [103 at 5–6, ¶¶ 20–21.]

Plaintiff and Defendant executed a construction contract on July 2, 2013. [103 at 3, ¶ 8.] The contract consisted of the "Lump Sum Contract," an addendum, General Conditions, and various architectural Specifications. [72 at 3, ¶¶ 8–9]; [103 at 5, ¶ 21.] The default provisions of the contract placed the risk of loss on Plaintiff: "Contractor at its sole cost, risk, and expense shall construct, supply equipment, provide, purchase, pay for, and furnish all of the Work in accordance with the Contract Documents." [57 -1 at 22, Art. 2.] In exchange for providing construction services, Plaintiff was to receive $21,309,412.21. [97 -1 at 4, Art. 4.] The parties do not dispute that the contract incorporated structural engineering and architectural "Specifications." [103 at 5, ¶ 21.] Those Specifications, in turn, incorporated the Terracon Report by reference, requiring that the Terracon Report "be included as an integral part of the project specifications. Site preparation and foundation construction shall be in accordance with the recommendations of said report." [103 at 6, ¶ 22]; see also generally [97 -7]. The contract also included an integration clause, defining the contract documents as the entire agreement between the parties. [103 at 7, ¶ 25.]

Plaintiff began work on the project on August 20, 2013. [72 at 3, ¶ 11.] Almost immediately, Plaintiff ran into trouble with the fill. [103 at 9, ¶ 32.] On August 28, 2013, Plaintiff formally requested that Defendant increase the contract sum in light of the extensive excavations (also called "undercuts") required to conform to the Terracon Report. [Id. at 8–9, ¶¶ 30-31]. Two days later, Defendant responded that it would not modify the contract sum because the recommendations of the Terracon Report were well-known when the contract was signed and incorporated by reference as part of the contract itself. [Id. , ¶¶ 32–33.] Plaintiff again sought to increase the contract sum in light of the undercutting in September 2013 and was again rebuffed. [Id. , ¶ 34]. Plaintiff completed the excavations and continued with its construction. See [108 at 10–12, ¶¶ 19–20, 22, 24.] It is undisputed that in other instances, the contract sum was increased by over $1,000,000 for various changes and modifications. See, e.g. , [110 at 2].

Plaintiff had 365 days to complete the work—that is, until August 20, 2014. See [97 -1 at 3, Art. 3.1]. Unfortunately, not all of the project components were completed on time. The parties do not dispute that as of August 20, 2014 Plaintiff had not done the following: (1) completed a sidewalk (or issued a bond to the city of Naperville in lieu of completing the sidewalk); (2) completed some landscaping work; (3) repaired an adjacent road; (4) completed an entrance for a neighboring facility; (5) paved a cul-de-sac; and (6) repaved part of a parking lot. [80 at 4, ¶ 10.] The parties dispute whether Plaintiff should be held liable for these delays. [Id. , ¶ 9]. The parties also agree that two other tasks—fixing a problem with the "hazardous room" and finalizing the "record drawings"—were outstanding and delayed certification but disagree whether they were within Plaintiff's or Defendant's responsibilities.2 [85 at 3–4, ¶¶ 5, 6.] Regardless, a permanent Certificate of Occupancy (CO) was not issued until December 15, 2015. [80 at 7, ¶ 11.] During this lag-time, Defendant sent three letters to Plaintiff complaining that the work had not been substantially completed, and (in some letters) outlining the outstanding work. [73 at 85–91.] Notwithstanding Plaintiff's delays in getting the permanent CO, Plaintiff was able to obtain a temporary CO on August 26, 2014 (that is, less than a week after the Contract Date). See [72 at 4–5, ¶¶ 15–16 (disputing that Plaintiff had completed its work by that date, but not disputing that a temporary CO was issued) ]. Likewise, Defendant was more-or-less able to get its distribution center up-and-running on schedule. See [id. , ¶ 16 ("[Defendant] does not dispute that it could occupy and use the distribution center on August 26, 2014.") ]

In July 2017, Plaintiffs sued Defendant in state court for breach of contract,3 arguing that the extensive undercutting was not within the scope of work. Plaintiffs now seek $334,486.07 for its undercutting work.4 [104 at 14.] Plaintiff also seeks $103,487.36 that Defendants have withheld in partial satisfaction of its liquidated damages counterclaim (discussed below). Defendant removed to federal court [1] and counterclaimed to enforce the liquidated damages provision in the contract: Defendants seek $2,000 for each day that the permanent CO was delayed after August 20, 2014—483 days (and $966,000) in all. [41 at 16, ¶¶ 13–14.] Defendant also wants Plaintiff to indemnify it for any losses it may accrue in Plaintiff's original breach of contract claim and attorneys' fees. [Id. at 17, ¶¶ 19–20.]

Before the Court are four cross motions for summary judgment. Defendant seeks full summary judgment [95] on Plaintiff's Claim I; Plaintiff cross moved for partial summary judgment [105] on that claim, arguing that it is at the very least entitled to the withheld funds. Plaintiff has abandoned its Claim II. See [104 at 20]. Plaintiff has also filed a sur-reply on Defendant's motion for summary judgment over Claim I...

To continue reading

Request your trial
12 cases
  • Conviser v. Depaul Univ.
    • United States
    • U.S. District Court — Northern District of Illinois
    • January 9, 2023
    ...indemnification. See NAR Bus. Park, 430 F.Supp.3d at 461. After all, why would DePaul defend a claim brought by Plaintiffs against DePaul? Id. indemnification clause, furthermore, goes on to require that the indemnified party provide notice of the existence of claims to the indemnifying par......
  • Vargas v. Price
    • United States
    • U.S. District Court — Northern District of Illinois
    • February 23, 2021
    ...that the evidence cited in the response does not show that the fact is in genuine dispute." NAR Business Park, LLC v. Ozark Automotive Distributors, LLC, 430 F. Supp. 3d 443, 446-47 (N.D. Ill.) (quotation marks and citation omitted). Plaintiff is a Hispanic male born in 1970. [75, at 1 ¶ 2]......
  • Crescent Plaza Hotel Owner L.P. v. Zurich Am. Ins. Co.
    • United States
    • U.S. District Court — Northern District of Illinois
    • February 18, 2021
    ...determinative and, as a result, the court can apply Illinois law as it is the law of the forum. See NAR Bus. Park, LLC v. Ozark Auto. Distbs., LLC, 430 F. Supp. 3d 443, 451 (N.D. Ill. 2019). ...
  • Crews v. Martinez
    • United States
    • U.S. District Court — Northern District of Illinois
    • March 31, 2022
    ...evidence cited in the response does not show that the fact is in genuine dispute.” NAR Bus. Park, LLC v. Ozark Auto. Distribs., LLC, 430 F.Supp.3d 443, 446-47 (N.D. Ill.). On May 20, 2017, at approximately 9:45 p.m., Illinois State Troopers Vincent Martinez and Joshua Blankenship (“Defendan......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT