National Constructors, Inc. v. Ellenberg
Decision Date | 02 October 1996 |
Docket Number | 96-325,Nos. 96-833,s. 96-833 |
Citation | 681 So.2d 791 |
Parties | 21 Fla. L. Weekly D2126 NATIONAL CONSTRUCTORS, INC. a/k/a de Construction Management, Appellant, v. Todd ELLENBERG and Christine Ellenberg, his wife, Appellees. |
Court | Florida District Court of Appeals |
Kenneth R. Duboff, Miami, for appellant.
Robert E. Paige, Coral Gables, for appellees.
Before NESBITT, JORGENSON and GREEN, JJ.
This is a consolidated appeal of two final orders of the trial court. National Constructors, Inc. ("National") appeals the Amended Final Judgment entered on the cross-claim of Todd and Christine Ellenberg for breach of contract as well as the Final Judgment awarding the Ellenbergs $11,075.00 in attorney's fees. We vacate both judgments for the reasons which follow and remand for further proceedings.
The Ellenbergs' home was damaged by Hurricane Andrew in August 1992. In October 1992, the Ellenbergs retained National, a general contractor, to repair their home at a preliminary cost of $136,201.00. 1 This litigation began when K & K Drywall, Inc., a drywall subcontractor of National, sued both National for nonpayment of work performed and the Ellenbergs for the foreclosure of a mechanic's lien. National filed a cross-claim against the Ellenbergs for breach of contract, unjust enrichment and indemnification. In response, the Ellenbergs filed a countercross-claim against National for breach of contract and indemnification. After a non-jury trial, the trial court found in favor of K & K Drywall on its claims against both National and the Ellenbergs. 2 As to the respective cross-claims for breach of contract, the court found that National had breached its contract with the Ellenbergs by not completing the repairs contracted for, but found that the Ellenbergs were entitled only to $1.00 in nominal damages where they had the unfinished work completed by another contractor at a lower cost. The trial court, however, did additionally find that the Ellenbergs would be unjustly enriched by not paying for the repair work actually completed by National. Accordingly, the court awarded National $7,107.46 on its claim for unjust enrichment against the Ellenbergs. 3 The remaining claims for indemnification were dismissed without prejudice.
As a result of the findings on the respective cross-claims of National and the Ellenbergs, the trial court declared the Ellenbergs to be the prevailing party for purposes of an award of attorney's fees pursuant to the terms of the contract between these parties. Accordingly, the trial court awarded the Ellenbergs $11,075.00 in attorney's fees. This appeal followed.
On this appeal, National essentially asserts first that the lower court erred in its determination that the Ellenbergs were the prevailing parties for purposes of an award of attorney's fees where National had otherwise substantially completed the contract and obtained a greater "net judgment" on its cross-claim. 4 In Ocean Ridge Dev. Corp. v. Quality Plastering, Inc., 247 So.2d 72 (Fla. 4th DCA 1971),the court stated:
Substantial performance is that performance of a contract which, while not full performance, is so nearly equivalent to what was bargained for that it would be unreasonable to deny the promisee the full contract price subject to the promisor's right to recover whatever damages may have been occasioned him by the promisee's failure to render full performance.
Id. at 75; see also Casa Linda Tile & Marble Installers, Inc. v. Highlands Place 1981, Ltd., 642 So.2d 766, 768 (Fla. 4th DCA 1994) (); Braverman v. Van Bower, Inc., 583 So.2d 381, 382 (Fla. 3d DCA) (, )review denied, 592 So.2d 683 (Fla.1991). In the context of contracts for construction, the doctrine of substantial performance is applicable only where the contractor has not willfully or materially breached the terms of his contract or has not intentionally failed to comply with the specifications. Lazovitz, Inc. v. Saxon Constr., Inc., 911 F.2d 588, 592 (11th Cir.1990); Lockhart v. Worsham, 508 So.2d 411, 412 (Fla. 1st DCA 1987) () (citing 17A C.J.S. Contracts § 509(b) (1974)); Rousselle v. B & H Constr. Co., 358 So.2d 614, 615 (Fla. 1st DCA 1978) () (citing 13 Am.Jur.2d, Building and Construction Contracts § 81 (1964)).
We note and the Ellenbergs candidly concede that the trial court never made a specific finding as to whether National substantially completed the repairs to the Ellenbergs' home. National asserts that it completed 95% of the job. The Ellenbergs, on the other hand, contend that the repair work left unfinished by National was substantial. The question...
To continue reading
Request your trial-
In re Standard Jury Instructions—Contract & Business Cases
...breached the terms of his contract or has not intentionally failed to comply with the specifications.” National Constructors, Inc. v. Ellenberg, 681 So.2d 791, 793 (Fla. 3d DCA 1996). 5. “There is almost always no such thing as ‘substantial performance’ of payment between commercial parties......
-
Energy Smart Indus., LLC v. Morning View Hotels-Beverly Hills, LLC
...whatever damages are suffered by the promisee on account of the promisor's non-material breach. Nat'l Constructors, Inc. v. Ellenberg, 681 So.2d 791, 793 (Fla. 3d DCA 1996) (quoting Ocean Ridge Dev. Corp. v. Quality Plastering, Inc., 247 So.2d 72, 75 (Fla. 4th DCA 1971) ). However, even ass......
-
Nat'l Equestrian League, LLC v. White
...1971)). . . . [T]he doctrine of substantial performance applies only where the promisor's nonperformance was unintentional. Nat'l Constructors, Inc., 681 So.2d at 793; Lockhart v. Worsham, 508 So.2d 411, 412 (Fla. DCA 1987); Lazovitz, Inc. v. Saxon Constr., Inc., 911 F.2d 588, 592 (11th Cir......
-
Wolfe v. 224 Via Marila, LLC
...4th DCA 2018) )); Kuhnsman v. Wells Fargo Bank, N.A. , 311 So. 3d 980, 984 (Fla. 2d DCA 2020) (same); Nat'l Constructors, Inc. v. Ellenberg , 681 So. 2d 791, 794 (Fla. 3d DCA 1996) (same). Seller contends that it provided buyer with the necessary exception documents with the original title ......