Next Gen Capital, LLC v. Consumer Lending Assocs., LLC

Decision Date19 December 2013
Docket NumberNo. 1 CA–CV 12–0624.,1 CA–CV 12–0624.
Citation676 Ariz. Adv. Rep. 16,316 P.3d 598,234 Ariz. 9
PartiesNEXT GEN CAPITAL, LLC, Plaintiff/Appellee, v. CONSUMER LENDING ASSOCIATES, LLC, dba “Loan ‘N Go” or “American Loan 'N Go”, Defendant/Appellant.
CourtArizona Court of Appeals

OPINION TEXT STARTS HERE

Polsinelli Shughart, P.C., By, Andrew S. Jacob, Andrew B. Turk, Phoenix, Counsel for Defendant/Appellant.

Molever Conelly PLLC, By Loren Molever, Scottsdale, Counsel for Plaintiff/Appellee.

Presiding Judge MAURICE PORTLEY delivered the opinion of the Court, in which Judge JOHN C. GEMMILL and Judge KENT E. CATTANI joined.

OPINION

PORTLEY, Judge.

¶ 1 Consumer Lending Associates, L.L.C. (CLA) challenges the summary judgment granted in favor of Next Gen Capital, L.L.C. (Next Gen) on a breach of lease claim. Finding no genuine dispute of material fact or legal error, we affirm the judgment.

BACKGROUND

¶ 2 CLA, a Nevada company, is engaged in the business of transferring money, whether by cashing checks or making short-term loans. CLA entered into a commercial lease in Arizona in June 2007 with the predecessor to Next Gen. 1 The five-year lease contained a provision that limited CLA's primary use of the premises to short-term loans and check cashing, and its ancillary use to money transfers.

¶ 3 CLA was operating under statutes authorizing “deferred presentment companies,” colloquially known as “payday loans” pursuant to Arizona Revised Statutes (“A.R.S.”) sections 6–1251 to –1263.2 The statutes authorizing payday loans, however, expired on July 1, 2010, by its sunset provision. 2000 Ariz. Sess. Laws, ch. 141, § 3 (2d Reg.Sess.); A.R.S. § 6–1263 (“The deferred presentment licensing program established by this chapter ends on July 1, 2010 pursuant to § 41–3102.”). Upon expiration of the authorizing statute, CLA promptly vacated the premises. Next Gen demanded that CLA pay rent due through the end of the lease term, but CLA refused and claimed the lease had terminated “by operation of Arizona law.”

¶ 4 Next Gen sued CLA for breach of contract and claimed damages. CLA answered and asserted defenses, including frustration of purpose and failure to mitigate damages. Next Gen subsequently moved for summary judgment and argued that CLA was liable for unpaid rent and related charges until the end of the lease term. After briefing and argument, the superior court granted the summary judgment motion.

¶ 5 CLA then filed a motion for new trial and argued that factual issues precluded summary judgment and Next Gen had the burden to establish mitigation of damages. The court denied the motion 3 and entered judgment awarding Next Gen $144,899.06 in damages, plus interest, attorneys' fees and costs.

DISCUSSION
I.

¶ 6 CLA argues that the doctrine of frustration of purpose excuses its breach. Because the issue is a question of law, we review it de novo. See 7200 Scottsdale Rd. Gen. Partners v. Kuhn Farm Mach., Inc., 184 Ariz. 341, 347, 909 P.2d 408, 414 (App.1995) (“Whether a party to a contract is entitled to relief under the doctrine of frustration of purpose is generally treated as a question of law.”).

¶ 7 We recognize that the doctrine of frustration of purpose is “essentially an equitable doctrine.” Id. Moreover, long ago we recognized that the doctrine “has been severely limited to cases of extreme hardship so as not to diminish the power of parties to contract, and ... have required proof from the party seeking to excuse himself that the supervening frustrating event was not reasonably foreseeable.” Garner v. Ellingson, 18 Ariz.App. 181, 183, 501 P.2d 22, 24 (1972) (citing Lloyd v. Murphy, 25 Cal.2d 48, 153 P.2d 47, 50 (1944).)

¶ 8 In 7200 Scottsdale Road General Partners, we examined Restatement (Second) of Contracts § 265 (1981), “particularly comment a,” to determine whether the party claiming frustration of purpose has demonstrated that the duty has been discharged. 184 Ariz. at 347–48, 909 P.2d at 414–15. Following the comments to § 265, we found four requirements that must exist before relief may be granted for frustration of purpose. Id. at 348, 909 P.2d at 415. First, the frustrated purpose “must have been a principal purpose of that party and must have been so within the understanding of both parties. Id. (quoting Restatement (Second) of Contracts § 265 cmt. a (1981)). Second, the frustration “must be so severe that it is not to be regarded as within the risks assumed ... under the contract.” Id. (quoting Restatement (Second) of Contracts § 265 cmt. a (1981)). Third, “the non-occurrence of the frustrating event must have been a basic assumption [on which the contract was made].” Id. (quoting Restatement (Second) of Contracts § 265 cmt. a (1981)). And, finally, “relief will not be granted if it may be inferred from either the language of the contract or the circumstances that the risk of the frustrating occurrence, or the loss caused thereby, should properly be placed on the party seeking relief.” Id. (citing Restatement (Second) of Contracts § 265 cmts. b & c (1981)).

¶ 9 Here, the superior court found that CLA could not satisfy the third requirement because it knew or should have known that the statute it was operating under would expire on July 1, 2010. We agree.

¶ 10 When CLA entered into the lease in 2007, the statute authorizing the payday loan business stated it would expire on July 1, 2010. A.R.S. § 6–1263. CLA, as a result, had notice that, absent further legislative action, it could not continue to operate past that date. See Pioneer Trust & Sav. Bank v. Zonta, 74 Ill.App.3d 614, 30 Ill.Dec. 512, 393 N.E.2d 548, 551 (1979) (“The parties are presumed to know the law at the time the lease is made.”); see also Hoff v. Sander, 497 S.W.2d 651, 653 (Mo.Ct.App. 1973) (“In the eyes of the law plaintiffs did know of the zoning restrictions [and] are therefore precluded from contending they, or defendant, were mistaken about the permissible use of the premises.”). Moreover, the lease did not acknowledge the scheduled expiration of the payday loan statute or otherwise allow the lease to terminate if the law expired as it was intended to when the provisions became law. And, there was no intervening legislative action that extended or continued the law past July 1, 2010.

¶ 11 It is clear that it was reasonably foreseeable in 2007 that CLA would have to end its payday loan operation in Arizona by July 1, 2010. Although the parties could have contracted around the statute, they did not. Under the circumstances, the frustration of purpose doctrine does not apply. See Mohave Cnty. v. Mohave–Kingman Estates, Inc., 120 Ariz. 417, 422–23, 586 P.2d 978, 983–84 (1978) (holding frustration of purpose inapplicable because the risk of a change in the zoning ordinance was reasonably foreseeable and one defendant could have contracted against it); see also City of Miami Beach v. Championship Sports, Inc., 200 So.2d 583, 586–87 (Fla.Dist.Ct.App.1967) (holding a lessee liable for rent in the absence of evidence that a disabling injury to a boxer was unanticipated). Consequently, the superior court did not err when it determined that the frustration of purpose doctrine did not allow CLA to escape its obligation under the lease. 4

II.
A.

¶ 12 CLA also argues that a genuine issue of material fact exists as to whether Next Gen made reasonable efforts to mitigate its damages. We disagree.

¶ 13 “A basic principle of the law of damages is that one who claims to have been injured by a breach of contract must use reasonable means to avoid or minimize the damages resulting from the breach.” W. Pinal Family Health Ctr., Inc. v. McBryde, 162 Ariz. 546, 548, 785 P.2d 66, 68 (App.1989). Because CLA was the breaching party, CLA “ha[d] the burden of proving that mitigation was reasonably possible but not reasonably attempted.” Fairway Builders, Inc. v. Malouf Towers Rental Co., 124 Ariz. 242, 255–56, 603 P.2d 513, 526–27 (App.1979) (applying the mitigation doctrine to a construction contract and holding, as a matter of law, that the appellant failed to meet its burden of proof on mitigation).

¶ 14 To support its summary judgment motion, Next Gen submitted the affidavit of Pamela Johns (“Johns”), which included a spreadsheet detailing her calculation of $144,899.06 in damages. Johns stated that Next Gen had rented the abandoned premises to another tenant, thereby mitigating its damages by $6,276.34, and that the efforts to re-lease the premises cost Next Gen $4,810.00 in commissions.

¶ 15 CLA challenged the damages claim. CLA, however, did not submit any conflicting evidence. Although CLA subsequently argued that Next Gen had the burden to demonstrate that it made reasonable efforts to market the premises before moving an existing tenant into the vacant premises, CLA did not submit any evidence that Next Gen failed to take reasonable steps and that further mitigation was probable. See State ex rel. Corbin v. Challenge, Inc., 151 Ariz. 20, 26, 725 P.2d 727, 733 (App.1986) (“Conclusory statements are simply insufficient to raise any genuine issues of material fact under Rule 56(e), Arizona Rules of Civil Procedure.”); see generally Ariz. R. Civ. P. 56(e)(4) (noting that the adverse party's affidavit must “set forth specific facts showing a genuine issue for trial”). Accordingly, because there was no genuine issue of material fact, summary judgment was appropriate. See GM Dev. Corp. v. Cmty. Am. Mortgage Corp., 165 Ariz. 1, 8, 795 P.2d 827, 834 (App.1990) (holding that an uncontradicted affidavit describing the plaintiff's efforts to mitigate discharged the movant's burden and supported the grant of summary judgment); see also Wingate v. Gin, 148 Ariz. 289, 292, 714 P.2d 459, 462 (App.1985) (granting summary judgment based upon uncontroverted evidence of the landlord's reasonable efforts to re-lease). 5

B.

¶ 16 Notwithstanding its failure to submit mitigation evidence, CLA argues that Next Gen had the burden to prove that it mitigated its damages. Arizona courts, however,...

To continue reading

Request your trial
5 cases
  • Jones v. GEICO Cas. Co.
    • United States
    • U.S. District Court — District of Arizona
    • 13 d5 Agosto d5 2021
    ...600 (Ariz.Ct.App. 2013). First, the “frustrated purpose” must have been the party's principal purpose and understood as such by both parties. Id. Second, the frustration must have been more severe than the risks assumed under the contract. Id. Third, the non-occurrence of the frustrating ev......
  • SPUS8 Dakota LP v. KNR Contractors LLC
    • United States
    • U.S. District Court — District of Arizona
    • 25 d5 Fevereiro d5 2022
    ... ... Having determined that KNR breached, the Court next ... considers the parties' arguments regarding the ... v. Consumer ... Lending Assocs., L.L.C, 234 Ariz. 9, 12 ¶ 13 ... ...
  • SPUS8 Dakota LP v. KNR Contractors LLC
    • United States
    • U.S. District Court — District of Arizona
    • 9 d2 Agosto d2 2022
    ...but does not articulate arguments based on the clearly established test in Next Gen Cap., L.L.C. v. Consumer Lending Assocs., L.L.C., 234 Ariz. 9, 11 (App. 2013). (Doc. 158 at 11-12.) For its part, KNR does not even address the issue in its Reply brief. (Doc. 168.) Accordingly, the Court wi......
  • F.S.T. Farms Inc. v. Vanderwey
    • United States
    • Arizona Court of Appeals
    • 26 d4 Dezembro d4 2019
    ...could have argued that the condemnation excused his performance under the Sharecrop Agreement. See, e.g., Next Gen Capital, L.L.C. v. Consumer Lending Assocs., L.L.C., 234 Ariz. 9, 11, ¶¶ 7-8 (App. 2013); Restatement (Second) of Contracts §§ 261-65. But he chose not to pursue that affirmati......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT