Nodaway Drainage Dist. No. 1 v. Illinois Surety Co.
Decision Date | 24 November 1913 |
Citation | 252 Mo. 543,160 S.W. 999 |
Parties | NODAWAY DRAINAGE DIST. NO. 1 v. ILLINOIS SURETY CO. |
Court | Missouri Supreme Court |
In Banc. Appeal from Circuit Court, Holt County; William C. Ellison, Judge.
Action by the Nodaway Drainage District No. 1, a corporation, against the Illinois Surety Company, a corporation. From a judgment for plaintiff, defendant appeals. Affirmed.
The following is the statement and opinion of BOND, J., in division:
Statement.
The petition states that the plaintiff is a corporation of this state organized for drainage purposes, with jurisdiction of a contiguous body of swamp and overflowed lands in the counties of Holt, Nodaway, and Andrew, and is engaged in constructing works and improvements in its district; that "the John Gilligan Company" is a Nebraska corporation engaged in contracting for building and constructing bridges, drainage dyking systems, and other public improvements; that the Illinois Surety Company is a corporation of that state, engaged in furnishing suretyship for contractors and others; that plaintiff, after adopting a general drainage system and plan of improvement for its district, contracted for work, in accordance therein, with one John Gilligan. The particulars of the work to be performed by him and the respective covenants and stipulations of the parties to said contract are fully set out and described.
The petition further alleges that the consideration to be paid by the plaintiff for the work described in said contract was $40,000, which was apportioned, to wit, $36,850 for construction of ditches, $3,150 for construction of bridges; that payments were to be made to the contractor upon estimates of his work reported to plaintiff by its chief engineer or his assistant; that rights of way should be obtained without cost to the contractor, and delays caused by litigation over rights of way were not to be counted against him; that the contractor should give bond in the sum of $10,000 to secure his covenants; that the work should begin September 1, 1906, and be completed in one year, barring inevitable accidents and two exceptions, the work on "Floyd cut-off" and "Blood Hill cut-off," for which six months' additional time was allowed.
The petition further states that the defendant, the Illinois Surety Company, entered into a bond guaranteeing the faithful performance of the contract made by said John Gilligan with the plaintiff; that the contractor, John Gilligan, thereafter incorporated himself and others as the "John Gilligan Company," and took charge of the work until after the time for its completion had expired.
The petition then alleges breaches of the bond: In that, in the particular respects set forth in the petition, the contractor did not faithfully keep and perform the conditions and terms of his contract. That the Illinois Surety Company was duly notified of the defaults and omissions of the contractor. That thereafter the following modifying contract was entered into, and the following indorsement placed thereon, by the defendant, the Illinois Surety Company:
The petition further states that "the John Gilligan Company" mentioned in the above contract did not well and truly perform the obligations imposed on it thereby, in the particulars fully set out in the petition; that before the lapse of the time therein specified the said John Gilligan Company wholly abandoned the further performance of its contract, and wrongfully failed and refused to comply with its terms, covenants, and stipulations, although often requested so to do by plaintiff; that the said John Gilligan Company then left the said work and improvements in a bad, worthless condition, and a total loss to the plaintiff.
The petition further stated that the plaintiff notified the defendant, the Illinois Surety Company, fully of the failures and omissions of the John Gilligan Company as to the performance of his contract with plaintiff, and that the Illinois Surety Company did nothing directly or indirectly towards securing the performance of said agreement.
The petition further states that the plaintiff was compelled to pay sums of money to other persons as the reasonable value of work done by them as to matters and things wherein the John Gilligan Company had failed to comply with its contract. (All set out in detail in the petition.)
The petition further states that by reason of the matters thereinbefore alleged the defendant, under its bond as surety, exhibited with the petition, had become indebted to plaintiff for an amount in excess of the penalty thereof. It prayed judgment for $10,000 specified in said bond and for an assessment of damages for that sum.
The answer of the defendant is summarized in appellant's brief to wit:
The last clause of the answer was, on motion, stricken out; defendant excepting, the reply took issue. The jury found for plaintiff for the penalty of the bond and assessed the damages in that amount. The defendant duly perfected its appeal to this court. The errors assigned and the evidence relevant to rulings thereon will be considered and stated hereafter.
I. The first error assigned by the appellant is the action by the trial court in striking out that portion of its answer which alleged as a defense that its principal, the Gilligan Company, had not been licensed to do business in this state, wherefore its contract with the plaintiff was void, and hence the bond entered into by defendant securing the performance of said contract was also void. That is quite a novel proposition independent of its moral aspect. Whether the Gilligan Company could have enforced its contract against plaintiff, or vice versa, is a matter between it and the plaintiff, as to which the present defendant is not interested. This action is for breach of the contract made by this defendant with the plaintiff by the terms and stipulations of the bond sued upon. This defendant was authorized to do business in this state by executing bonds to secure the performance of the obligations assumed by other persons or corporations, for which this defendant received a valuable consideration and probably indemnity. The contract between the plaintiff and defendant expressed in the bond sued upon was, in all respects, lawful and made between competent parties. Its legal effect was an unconditional undertaking on the part of the defendant that the Gilligan Company should faithfully perform the work and duties imposed upon it by an agreement between...
To continue reading
Request your trial-
Johnston v. Star Bucket Pump Co.
...v. Railroad, 112 Mo. loc. cit. 494, 20 S. W. 631, 34 Am. St. Rep. 403; Drainage Dist. v. Surety Co., 252 Mo. loc. cit. 564 et seq., 160 S. W. 999; Lasar Mfg. Co. v. Pelligreen Const. Co., 179 Mo. App. loc. cit. 455, 162 S. W. 691; Heman v. Mfg. Co. 58 Mo. App. loc. cit. 485, and cases cited......
-
Hogan v. Public Service Co.
... ... (1) The court erred in that by the refusal of ... ...
-
Lackey v. United Railways Company of St. Louis
... ... appellants ... (1) The ... court should have given appellant's ... ...
-
Johnston v. Star Bucket Pump Company
... ... (1) ... Even if defendant's counterclaim be ... Drainage Dist ... v. Surety Co., 252 Mo. 565; Moore v ... ...