Norwich Roman Catholic Diocesan Corp. v. Southern New England Contracting Co.

Citation164 Conn. 472,325 A.2d 274
CourtSupreme Court of Connecticut
Decision Date08 March 1973
PartiesThe NORWICH ROMAN CATHOLIC DIOCESAN CORPORATION v. The SOUTHERN NEW ENGLAND CONTRACTING COMPANY et al.

Milton L. Jacobson, Norwich, with whom was William R. Moller, West Hartford, for appellant (plaintiff).

Martin S. Michelson, Hartford, with whom were James Royster, Hartford, and, on the brief, Richard M. Feingold, Hartford, for appellee (named defendant).

Before HOUSE, C. J., and SHAPIRO, LOISELLE, MacDONALD and BOGDANSKI, JJ.

BOGDANSKI, Associate Justice.

On April 4, 1966, the defendant Southern New England Contracting Company, hereinafter called the contractor, entered into a written contract with the plaintiff, Norwich Roman Catholic Diocesan Corporation, hereinafter called the diocese, for the construction of a school building, including site work and a sanitary system. The contract provided for arbitration of any claims or disputes in accordance with the 'Standard Form of Arbitration Procedure of the American Institute of Architects.' That procedure specified that a party wishing to arbitrate should designate whether the arbitration should be administered under the above quoted authority and, if administered by the American Arbitration Association, that its rules should govern. The contractor applied to the American Arbitration Association for arbitration. Accordingly, three arbitrators were appointed and they held extensive hearings on the matters submitted.

The following dispute was submitted for arbitration: (1) The diocese refused to classify as 'mass rock' 23,372 cubic yards of excavated material which was 'in fact' mass rock and to pay for it at the agreed unit cost of $6.60 per cubic yard, for which the contractor claimed $154,255.20; (2) the diocese refused to pay for extra costs, labor, and materials necessitated by undisclosed and excessive water conditions, for which the contractor claimed $23,822.70; and (3) the diocese failed to make a final payment under the contract, exclusive of extra work, in the amount of $58,589.35. In addition, the contractor sought interest of 6 percent on the amount found due. Item three was abandoned in the arbitration proceedings. The arbitrators awarded the contractor (1) $134,607 for the excavation of 20,395 cubic yards of mass rock at $6.60 per cubic yard; (2) $20,577.77 for undisclosed and excessive water conditions; and (3) interest of 6 percent on the $20,577.77 award from November 13, 1967, to the date of the award. The diocese applied to the Superior Court in New London County to vacate the award. The contractor, in turn, applied for confirmation of the award. The referee to whom the case was referred, acting as the court, rendered judgment confirming the award. From that judgment the diocese has appealed to this court.

The diocese's first assignment of error, challenging the finding, has not been briefed and is treated as abandoned. State v. Grayton, 163 Conn. 104, 109, 302 A.2d 246; State v. Benson, 153 Conn. 209, 217, 214 A.2d 903. Its remaining assignments of error are directed at the referee's conclusions and his rulings on evidence and claims of law.

The referee found that the arbitrators were given broad powers under the rules of the American Arbitration Association, that § 30 of the rules provided that the arbitrators should be the judges of the admissibility of evidence and that conformity to the legal rules of evidence was not necessary, and that § 42 of the rules provided that the arbitrators might grant any remedy or relief which they deem just and equitable and within the terms of the parties' agreement.

The referee concluded that the submission defined the authority of the arbitrators, that the arbitrators were not asked to interpret the contract, that the award conformed to the submission, and that it was not the function of the referee to review the evidence considered by the arbitrators to determine the validity of the award.

Our courts favor arbitration as a means of settling differences and uphold the finality of arbitration awards except where an award clearly falls within the proscriptions of § 52-418 of the General Statutes. International Union v. Fafnir Bearing Co., 151 Conn. 650, 653, 201 A.2d 656; United Electrical Radio & Machine Workers v. Union Mfg. Co., 145 Conn. 285, 288, 141 A.2d 479. That section provides as follows: 'Vacating award. In any of the following cases the superior court . . . or, when said court is not in session, any judge thereof, shall make an order vacating the award upon the application of any party to the arbitration: (a) If the award has been procured by corruption, fraud or undue means; (b) if there has been evident partiality or corruption on the part of the arbitrators or either of them; (c) if the arbitrators have been guilty of misconduct in refusing to postpone the hearing upon sufficient cause shown or in refusing to hear evidence pertinent and material to the controversy or of any other action by which the rights of any party have been prejudiced; (d) if the arbitrators have exceeded their powers or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made . . ..'

In seeking to vacate the award in this case under subsection (d) of the statute, the diocese contends that the arbitrators exceeded their powers in refusing to interpret paragraphs of the contract specifications concerning definitions of 'mass rock' and 'cross sectioning.' The diocese also asserts that when it offered these documents as exhibits the referee improperly sustained the contractor's objection to them.

Charges that arbitrators have acted fraudulently or corruptly, or have been guilty of misconduct in refusing to hear pertinent evidence or of any other action prejudicial to the rights of any party are not cognizable under § 52-418(d) and are properly brought under other subsections of...

To continue reading

Request your trial
29 cases
  • State v. Onofrio
    • United States
    • Connecticut Supreme Court
    • September 4, 1979
    ...a trial judge to deprive an aggrieved party of a proper record for an appeal." Accord Norwich Roman Catholic Diocesan Corporation v. Southern New England Contracting Co., 164 Conn. 472, 478, 325 A.2d 274; Drazen Lumber Co. v. Casner, supra, 156 Conn. 405-406, 242 A.2d 754; National Broadcas......
  • O & G/O'Connell Joint Venture v. Chase Family Ltd. Partnership No. 3
    • United States
    • Connecticut Supreme Court
    • April 14, 1987
    ...of Education v. Waterbury Teachers Assn., supra, 168 Conn. at 62, 357 A.2d 466; Norwich Roman Catholic Diocesan Corporation v. Southern New England Contracting Co., 164 Conn. 472, 476-77, 325 A.2d 274 (1973). Since the parties consent to arbitration, and have full control over the issues to......
  • Saphir v. Neustadt
    • United States
    • Connecticut Supreme Court
    • April 3, 1979
    ...defendants' substantial compliance with their obligations under the covenant. See Norwich Roman Catholic Diocesan Corporation v. Southern New England Contracting Co., 164 Conn. 472, 478, 325 A.2d 274 (1973). There was no error in the court's ruling, and, in sum, we find no error on the plai......
  • Belanger v. Matteson
    • United States
    • Rhode Island Supreme Court
    • October 29, 1975
    ...is entered into and the parties are free to limit those powers by agreement. Norwich Roman Catholic Diocesan Corp. v. Southern New England Contracting Co., 164 Conn. 472, 476-77, 325 A.2d 274, 276 (1973). It is incumbent upon the court in these matters to measure the award against the grant......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT