Olympic Development Group, Inc. v. American Druggists' Ins. Co., 70115
Decision Date | 30 May 1985 |
Docket Number | No. 70115,70115 |
Citation | 175 Ga.App. 425,333 S.E.2d 622 |
Parties | OLYMPIC DEVELOPMENT GROUP, INC. et al. v. AMERICAN DRUGGISTS' INSURANCE COMPANY. |
Court | Georgia Court of Appeals |
Wayne F. Carmichael, Norcross, for appellants.
Douglas N. Campbell, Laura S. Conrad, Atlanta, for appellee.
Appellee-surety filed a complaint against appellants-indemnitors, alleging the following: That appellee executed a surety bond with Prichard Mining Company as principal; that, in consideration thereof, appellants agreed to indemnify appellee against any and all liability appellee would incur as a result of executing the bond; that the bond was forfeited and appellee was required to pay the amount of the forfeiture; and that appellants were indebted to appellee in the amount of the unpaid premiums and principal on the bond, attorney fees and costs of litigation. On May 22, 1984, the trial court granted partial summary judgment in favor of appellee as to appellants' liability for the amount of unpaid premiums on the bond. On October 19, 1984, partial summary judgment was granted in favor of appellee as to the liability of the appellants for the principal on the bond, attorney fees and costs of litigation. Appellants filed their notice of appeal on November 19, 1984, seeking to appeal from both of the trial court's orders granting partial summary judgment in favor of appellee.
1. Appellee has filed a motion to dismiss appellants' appeal from the trial court's order dated May 22, 1984, on the ground that no notice of appeal was filed within thirty days after the issuance of that order.
The grant of partial summary judgment as to one or more but fewer than all the claims or parties is reviewable by direct appeal if the notice of appeal is filed within 30 days of the rendition of such judgment. O.C.G.A. § 9-11-56(h); Tri-County Feed & Seed v. Savannah Valley Prod. Credit Assn., 158 Ga.App. 815, 816(1), 282 S.E.2d 344 (1981); Ferguson v. United Ins. Co. of America, 163 Ga.App. 282(1), 293 S.E.2d 736 (1982). The losing party in such a situation may also appeal after rendition of final judgment in the case. Culwell v. Lomas & Nettleton Co., 242 Ga. 242, 248 S.E.2d 641 (1978); Newton v. K.B. Property Mgt. of Ga., 166 Ga.App. 901, 903, 306 S.E.2d 5 (1983); Gulf Oil Co. v. Mantegna, 167 Ga.App. 844, 845-846, 307 S.E.2d 732 (1983). However, in the instant case, appellants did not file a timely direct appeal, nor do they now appeal from a final order. The second order dated October 19, 1984, which granted partial summary judgment in favor of appellee does not constitute the final judgment in the case as it explicitly reserves determination of the issue of the liability of one of the other defendants. See Insurance Co. of N. America v. Fowler, 148 Ga.App. 509, 512(3), 251 S.E.2d 594 (1978); O.C.G.A. § 5-6-34. Accordingly, appellants' appeal from the trial court's order of May 22, 1984 is not properly before this court. Appellee's motion to dismiss appellants' appeal from the order of May 22, 1984, is granted.
2. Resolution of appellants' assertion that the trial court erred in granting appellee's second motion for partial summary judgment necessitates a rather lengthy summary of a complex factual situation.
Prichard Mining Company (Prichard) desired to obtain a strip-mining permit from the State of Kentucky (Kentucky). Mining permit applicants must submit a surety bond in favor of Kentucky, which bond is to ensure that the area disturbed by the mining will be restored. To this end, Prichard submitted to appellee-surety company an application for a surety bond. As a necessary part of that application, appellant Shine individually, and appellant Olympic Development Group, Inc. (Olympic), by Shine as its president, executed an indemnity agreement (the Prichard Indemnity Agreement), promising to indemnify appellee should appellee suffer any loss from default by Prichard, the bond principal, in the payment of the bond premiums, performance of reclamation of the land, or from any other expenses that might arise pursuant to appellee's issuance of the bond. Appellants also executed a collateral security agreement whereby there was deposited with appellee a certificate of deposit (the Prichard Certificate of Deposit) to be held by appellee until it was released from all liability on the bond. On April 20, 1977, a surety bond (the Prichard Bond) was issued by appellee as surety in the amount of $38,000, assuring the performance of Prichard's obligations under Kentucky law in connection with the activities to be conducted upon the issuance of a mining permit. The bond was submitted to Kentucky in support of Prichard's permit application, and Prichard was eventually issued a mining permit.
During the summer of 1978, Kentucky issued to Prichard several notices of violation in the reclamation of the permitted area. Following unsuccessful negotiations with Prichard, Kentucky filed a complaint against the company, seeking forfeiture of the Prichard Bond. Sometime during the spring of 1980, another coal mining company, Chatsworth Coal Company (Chatsworth) attempted to take over the mining permit held by Prichard. In order to issue the permit sought by Chatsworth, Kentucky required of Chatsworth a surety bond in addition to the Prichard Bond already in place. Accordingly, Chatsworth executed appellee's combined application for surety bond and general agreement of indemnity, as well as a collateral security agreement. The collateral for this indemnity agreement was a certificate of deposit in the amount of $12,768 (the First Chatsworth Certificate of Deposit). On March 24, 1980, a surety bond was issued in the amount of $21,280 by appellee as surety, naming Chatsworth as principal (the First Chatsworth Bond). Chatsworth submitted an application in Prichard's name for a permit to mine the area already permitted to Prichard. Appellee contacted appellant Shine concerning Chatsworth's proposal to assume responsibility under the Prichard permit and its issuance of the First Chatsworth Bond.
Subsequently, Kentucky rejected Chatsworth's application in the name of Prichard. By letter dated March 31, 1980, Kentucky notified Chatsworth that its application would have to be in its own name instead of that of Prichard. Due to Kentucky's rejection of this application, the First Chatsworth Bond was returned to Chatsworth and never became effective.
Apparently, around April 1, 1980, appellee executed an endorsement which sought to change the identity of the principal of the Prichard Bond from Prichard to Chatsworth Coal. However, there is no evidence that the endorsement was ever submitted to Kentucky in conjunction with the first Chatsworth permit application. In fact, the evidence shows that the first Chatsworth permit application had been rejected before the endorsement was executed. Moreover, Ms. Keller of the Kentucky National Resources and Environmental Protection Cabinet, whose duties included overseeing the Prichard permit application, stated in her deposition that at all times the principal of the "Prichard Bond" remained Prichard, and the identity of the bond principal was never transferred.
In an attempt to comply with Kentucky's permit application requirement and to avoid forfeiture of the Prichard Bond held by Kentucky, an agent of appellee telephoned appellant Shine on April 28, 1980, and told him that appellee was issuing a new bond to Chatsworth and that the old collateral, the Prichard Certificate of Deposit, would be used. Appellants agreed to this arrangement. A letter sent on behalf of appellee to appellant Shine confirming the telephone conversation read as follows:
[.] (Emphasis supplied.)
As agreed, appellants signed a second collateral security agreement (Second Collateral Agreement), wherein the Prichard Certificate of Deposit was to be held "in accordance with the original collateral receipt and agreement." On the same date, appellee issued a bond in the amount of $59,280, naming Chatsworth as principal (the Second Chatsworth Bond), and Chatsworth filed a new application for a mining permit.
Subsequently, Chatsworth's second application for a mining permit was withdrawn because Chatsworth was unable to obtain a necessary waiver from a dwelling owner. The...
To continue reading
Request your trial-
Bowman v. WALNUT MTN. PROP. OWNERS ASSOC.
...expressed controls over all technical or arbitrary rules of construction. OCGA § 13-2-3; Olympic Dev. Group v. American Druggists' Ins. Co., 175 Ga.App. 425, 429(2), 333 S.E.2d 622 (1985). Here, 68 percent of the lot owners expressly intended to exercise their rights to renew and extend the......
-
Spivey v. Safeway Ins. Co.
...raised in the petition for declaratory judgment, and granting summary judgment in favor of Safeway. Olympic Dev. Group v. American Druggists' Ins. Co., 175 Ga.App. 425, 333 S.E.2d 622 (1985). Even though there was no summary judgment motion before the trial court, summary judgment may be gr......
-
Cleveland v. Fulton County
...the trial court's grant of summary judgment to all appellees on the federal claims. "In [Olympic Dev. Group, Inc. v. American Druggists' Ins. Co., 175 Ga.App. 425(1), 333 S.E.2d 622 (1985) ], this court held that where the appellants had failed to bring a timely appeal from a grant of parti......
-
Jones v. White
...of appeal filed within 30 days of entry of the judgment. See OCGA § 9–11–56(h); Olympic Dev. Group v. American Druggists' Ins. Co., 175 Ga.App. 425(1), 333 S.E.2d 622 (1985). We have previously held that where the appellants had failed to bring a timely appeal from a grant of partial summar......
-
Project update 1995: illustrative provisions of a general indemnity agreement taken in connection with contract surety bonds.
...(Colo.Ct.App. 1989); Harvey v. United Pac. Ins. Co., 856 P.2d 240 (Nev. 1993); Olympic Dev. Group Inc. v. American Druggists' Ins. Co., 333 S.E.2d 622 (Ga.Ct.App. 1985), cert. denied (Sept. 3, 1985); Transamerica Premier Ins. v. Nelson, 878 P.2d 314 (Nev. 1994); St. Paul Fire & Marine I......