Otto B. Ashbach & Sons, Inc. v. State

Decision Date06 July 1956
Docket NumberNo. 36664,36664
Citation247 Minn. 573,78 N.W.2d 446
PartiesOTTO B. ASHBACH & SONS, Inc., Respondent, v. STATE of Minnesota, Appellant.
CourtMinnesota Supreme Court

Syllabus by the Court.

1. Where trial court's construction of provisions of highway contract between plaintiff and State of Minnesota, relating to method of computing volume of rock-cut excavations performed under such contract appears sound and is not challenged on appeal, only issue presented for determination here is whether evidence sustains finding that plaintiff had not been compensated for 2,734 cubic yards of such excavation.

2. Testimony of parties considered and held sufficient to support trial court's finding on this issue.

3. Where under M.S.A. § 161.03, subd. 17, state has waived immunity from suit and conferred jurisdiction upon district courts of state to hear and try out controversies arising out of highway construction contracts in the same manner as provided for trial of other causes in such courts, Held it thereby places itself in the same class as other litigants and, like them, becomes subject to interest charges on any indebtedness which the court hearing such a cause may determine is due from it.

The judgment appealed from is affirmed.

Miles W. Lord, Atty. Gen., and John H. Rheinberger, Sp. Asst. Atty. Gen., for appellant.

Roland J. Faricy, Harry G. Costello, Jr., and B. Warren Hart, St. Paul, Faricy, Moore & Costello, St. Paul, of counsel, for respondent.

DELL, Chief Justice.

Action by Otto B. Ashbach & Sons, Inc., against the State of Minnesota to recover for a volume of excavation claimed due under a contract for highway construction work. The contract dated January 19, 1948, called for construction work by plaintiff on state trunk Highway No. 35, commencing 4.5 miles east of Soudan and extending to 3.5 miles southwest of Ely. The work to be performed consisted of (1) grading, excavating, and embanking; and (2) the placing of a twelve-inch gravel base and subbase on the section of highway included in the contract.

It was agreed that the contract had been satisfactorily completed by plaintiff, the controversy here centering around the meaning of the contract as it related to 'rock cuts' and whether plaintiff had been paid in full therefor. Section 11.02 of the contract provided that for 'rock cuts' plaintiff would be paid at the rate of $2.88 per cubic yard and further specified that:

'In rock cuts, the excavation will be measured as the volume within the grading section staked by the Engineer; plus the volume included between the staked backslopes and slopes distant 18 inches outside thereof, measured horizontally; plus the volume above a surface 18 inches below the staked grade of the roadbed, extended to the shoulder slopes. No overbreak beyond these limits will be measured.'

Plaintiff contended that under this provision the state in its measurements of rock-cut excavations had failed to include some 11,000 cubic yards thereof for which plaintiff claimed payment at the rate of $2.88 per cubic yard. The trial court was called upon to construe the contract and under its construction determined that plaintiff had not been paid for 2,734 cubic yards of such rock-cut excavations and accordingly that the defendant was indebted to plaintiff therefor in the sum of $7,873.92, plus interest, costs, and disbursements. Included in the trial court's findings were the following:

'8. That under Section 2105.2B, M.H.D. Specs., excavation is classified as Class 'A', 'B', or 'C'.

'That section 2105.2B1 defines Class 'A' excavation as consisting of 'all materials of an earthy nature, however compact they may be, such as earth, loam, clay, indurated clay, hardpan, silt, sand, and loose or cemented gravel; and boulders or detached rocks each having an average diameter of two (2) feet or less.'

'That Section 2105.2B2 defines Class 'B' as excavation consisting of 'all ledge rock, and all boulders and detached rock, each having an average diameter of more than two (2) feet.'

'That Section 2105.2B3, M.H.D. Specs., defines Class 'C' excavation as consisting of 'all materials listed under Class 'A' and 'B', and any other material which may be encountered regardless of its nature.'

'9. That Special Provisions 11.01, at page 13 of the Proposal, provides that 'All excavation, except Special Swamp Excavation, between the stations tabulated below will be classified as Class 'B' excavation. (Here follows a list of the stations referred to.)'

'10. That materials actually excavated by plaintiff within those stations listed above which were classified as Class 'B' excavation under the contract consisted of materials meeting the definition of Class 'B' excavation, as well as materials defined as Class 'A' excavation, under M.H.D. Specs.

'11. Section 11.02 of the Special Provisions provides that, 'In rock cuts, the excavation will be measured as the volume within the grading section staked by the Engineer; plus the volume included between the staked backslopes and slopes distant 18 inches outside thereof, measured horizontally; plus the volume above a surface 18 inches below the staked grade of the roadbed, extended to the shoulder slopes. No overbreak beyond these limits will be measured.'

'That Section 11.02 applies to Class 'A', 'B', or 'C' excavation whenever a rock cut is actually made.

'12. That 'grading sections staked by the Engineer' as used in Section 11.02 of the Special Provisions is the cross section of the roadway to which excavation would be made if the markings on the stakes were followed exactly. That 'staked grade of the roadbed' as used in Section 11.02 of the Special Provisions is the top of the finished grade of the roadbed as required by the contract. That 'overbreak' as used in Special Provisions 11.02 is defined under Section 2105.2L5, M.H.D. Specs., as 'that material in rock cuts which is removed outside of the authorized slope lines.'

'14. That under Section 11.02 of the Special Provisions plaintiff in rock cuts, in addition to the volume of excavation within the grading section staked by the engineer, is to be paid for a volume of excavation between the staked backslopes of the roadway and a parallel slope 18 inches beyond that point measured horizontally; and in the roadbed a volume of excavation between the grade to which excavation was required to be made (subgrade or limits of grading section staked by the engineer) and a surface 18 inches below the finished grade of the roadbed extended to the shoulder slopes. That this additional volume allowed under Section 11.02 in backslopes and roadbeds is computed by using as a multiple the severed surface area of the rock at the limits of the staked grading section. That plaintiff in rock cuts is entitled to this additional volume of excavation whether the material is actually excavated or not.

'15. That except in rock cuts plaintiff has been paid in full for all excavation within the grading section staked by the engineer regardless of classification of materials excavated. That in rock cuts plaintiff has been paid for the total volume of excavation within the grading section staked by the engineer, plus an additional volume of excavation not necessarily excavated, as follows:

'(1) At the backslopes--a volume of excavation between the staked backslopes and slopes distant 18 inches outside thereof, measured horizontally.

'(2) In the roadbed--a volume of excavation between the grade to which excavation was required to be made (subgrade) and a surface 18 inches below the staked grade of the roadbed ...

To continue reading

Request your trial
2 cases
  • Lienhard v. State
    • United States
    • Minnesota Supreme Court
    • November 23, 1988
    ...Similarly, when the State waived sovereign immunity a prevailing party could be awarded interest. Otto B. Ashbach & Sons, Inc. v. State, 247 Minn. 573, 579, 78 N.W.2d 446, 450 (1956). Since the rationale for the rule of construction that the State is not bound by a statute unless named ther......
  • Alley Const. Co., Inc. v. State, 44298
    • United States
    • Minnesota Supreme Court
    • July 5, 1974
    ...that the statute is merely a legislative enactment of the principles established in our decision in Otto B. Ashbach & Sons, Inc. v. State, 247 Minn. 573, 78 N.W.2d 446 (1956). In that case, we allowed prejudgment interest on the grounds that the state, having waived immunity and submitted i......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT