Pacific Gas and Elec. Co. v. F.E.R.C.

Decision Date08 November 1984
Docket NumberNo. 83-7854,83-7854
Citation746 F.2d 1383
PartiesPACIFIC GAS AND ELECTRIC COMPANY, Southern California Edison Company, San Diego Gas and Electric Company, Petitioners, v. FEDERAL ENERGY REGULATORY COMMISSION, Respondent, California Public Utilities Commission, Sacramento Municipal Utility District, Intervenors.
CourtU.S. Court of Appeals — Ninth Circuit

Glenn West, Howard V. Golub, PG & E, San Francisco, Cal., Charles Daly, S.D. Gas & Electric, Santa Rosa, Cal., Ann P. Cohn, Southern Pacific Edison Co., Rosemead, Cal., for petitioner.

Joshua Z. Rokach, FERC, Washington, D.C., for respondent.

G. Philip Nowak, Washington, D.C., for intervenor Cal. Public Utilities, et al.

Petition for Review of Orders of the Federal Energy Regulatory Commission.

Before GOODWIN, POOLE and BOOCHEVER, Circuit Judges.

GOODWIN, Circuit Judge.

In this appeal from orders of the Federal Energy Regulatory Commission, petitioners challenge the Commission's authority to rule summarily on the interpretation of a contract for electricity transmission service. We affirm the FERC orders.

This dispute concerns a contract between the Sacramento Municipal Utility District (SMUD) and three California investor-owned utilities: Pacific Gas and Electric (PG & E), San Diego Gas and Electric (SDG & E), and Southern California Edison (SCE) (jointly referred to as the California Companies). SMUD and the California Companies entered into an agreement effective August 1, 1967, providing SMUD with electricity transmission service capacity over the Pacific Northwest-Southwest Intertie. 1 Under Article 9 of the agreement, the California Companies have agreed to provide SMUD with transmission service for transmitting energy to or from any Pacific Northwest utility. Three types of power-purchasing arrangements are contemplated by the agreement: (1) electricity purchased from northwest suppliers under long-term contracts (so-called northwest firm power), (2) electricity purchased on a spot basis from northwest utilities (so-called northwest dump power), and (3) electricity available from Canada under Canadian Entitlement Exchange Agreements (so-called Canadian Entitlement Power or CEP).

The agreement requires SMUD to make a request to the California Companies for purchasing electric power or reserving transmission capacity on the Pacific Intertie. Article 10 of the contract requires five years' advance notice for SMUD to change its reservation for firm power transmission capacity.

The contract further contains a so-called anti-yo-yo clause which provides that SMUD may not request an increase in firm power transmission service after any previously requested decrease in service. The effect of the anti-yo-yo clause is to prevent SMUD from continually readjusting its reservation of transmission capacity to reflect its actual use of northwest power. This restriction does not apply with respect to transmission capacity reserved for CEP, however.

This dispute centers on interpretation of Article 10(d) of the agreement, the anti-yo-yo clause, which provides in relevant part:

[SMUD] shall not, with respect to the amount of transmission service to be made available in any month under Article 9(a) and (b) [firm power], be entitled to any change which would become effective within twelve months following the last preceding change, nor shall [SMUD] be entitled to an increase in such amount after any previous decrease in such amount of service. The limitations contained in this paragraph shall not apply to changes required to accommodate changes in amounts of Canadian Entitlement Power [CEP] ... pursuant to the provisions of the Canadian Assignment Agreement.

In late 1967, SMUD requested that PG & E purchase CEP and reserve equivalent transmission service capacity on the Intertie. At times thereafter, in addition to importing CEP, SMUD used some of the CEP transmission capacity to import northwest dump power on a short-term basis. In 1970, SMUD was notified that its allotment of CEP would be completely withdrawn effective April 1975. Because of the withdrawal of CEP, SMUD notified PG & E in 1971 that it would no longer need any Intertie transmission capacity.

In 1973, SMUD gave PG & E a five-year notice that it wished to use the Intertie once again, this time for firm power to be purchased from the Bonneville Power Administration. PG & E refused to grant SMUD access to the Intertie on the ground that SMUD's 1971 request to decrease service capacity to zero had triggered the anti-yo-yo clause. SMUD insisted that, because it had requested the decrease in 1971 only in response to the elimination of its CEP allotment, the anti-yo-yo clause did not apply.

After requesting a series of postponements in the capacity requested for Bonneville power, SMUD requested that service begin in 1982. Also in 1982, SMUD requested an additional increase in capacity effective in 1987. PG & E rejected the request for both the 1982 service and the 1987 increase in service.

Throughout this dispute, the California Companies have contended that as soon as SMUD used its reserved transmission capacity for importing any electric power except CEP (e.g., northwest dump power), the anti-yo-yo clause was triggered, regardless of the purpose for which the capacity was originally reserved. SMUD has argued that the anti-yo-yo clause only governed the transmission capacity reservation; since it reserved capacity for the purpose of CEP, it is irrelevant that it used that capacity to import dump energy from time to time.

On July 30, 1982, SMUD filed a complaint against the California Companies with the FERC, pursuant to Section 306 of the Federal Power Act, 16 U.S.C. Sec. 825e, and Section 1.6 of the FERC Rules, 18 CFR Sec. 385.206. The complaint sought declaration of SMUD's rights under the agreement to transmission service over the Pacific Intertie. SMUD also filed a motion for summary disposition of the cause pursuant to FERC Rule 217, 18 CFR Sec. 385.217, which provides that the FERC may summarily dispose of a proceeding if there is no genuine issue of material fact in dispute.

The Commission, in its "Order Interpreting Contract, Granting Motion for Summary Disposition, and Granting Requests for Declaratory and Other Relief," 23 FERC p 61,042 (1983), found in favor of SMUD. The FERC held that the SMUD decrease in reserved service capacity was a change required exclusively to accommodate its loss of CEP, and, therefore, fell squarely within the Article 10(d) exception to the anti-yo-yo clause. Further holding that its decision turned on the plain, clear language of the contract, the FERC held that the allegations in this case did not warrant a trial-type hearing and that summary disposition was appropriate under Rule 217.

The Commission has interpreted Rule 217 to mean that summary disposition is appropriate if two conditions are met: (1) the proponent must have been afforded a reasonable opportunity to present arguments and factual support (written and oral) and that evidence must be viewed in its most favorable light, and (2) the Commission must find that a hearing is unnecessary and would not affect the ultimate disposition of an issue because there are no material facts in dispute or because the facts presented by the proponent have been accepted in reaching the decision. Coastal States Mktg. Inc. v. Texas-New Mexico Pipeline Co., 25 FERC p 61,164 (1983); see Citizens for Allegan County, Inc. v. FPC, 414 F.2d 1125, 1128-9 (D.C.Cir.1969).

In its review, this court must be satisfied that FERC properly addressed all the relevant factors in dispute and that a formal hearing was unnecessary for the Commission to reach its conclusion. Cerro Wire & Cable Co. v. FERC, 677 F.2d 124, 128-9 (D.C.Cir.1982). We must allow the FERC wide discretion in selecting its own procedures, Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U.S. 519, 524, 98 S.Ct. 1197, 1202, 55 L.Ed.2d 460 (1978), and must defer to the FERC interpretation of its own rules, unless the interpretation is plainly erroneous. Phelps Dodge Corp. v. Fed. Mine Safety & Health Review Comm'n., 681 F.2d 1189, 1192 (9th Cir.1982). Whether or not to grant a full trial-type hearing is a matter within agency discretion. See Sierra Ass'n for Env't v. FERC, 744 F.2d 661, 663 (9th Cir.1984).

Although the limits of FERC Rule 217 are relatively untested in the courts, neither the Administrative Procedures Act nor FERC's own precedents require a hearing where there has been no showing that material facts are in dispute. Georgia-Pacific Corp. v. EPA, 671 F.2d 1235, 1241 (9th Cir.1982). See Sierra Ass'n for Env't., 744 F.2d at 663-4. As long as the agency has considered all the...

To continue reading

Request your trial
23 cases
  • State of Cal. ex rel. State Water Resources Control Bd. v. F.E.R.C.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • April 3, 1992
    ... ... FEDERAL ENERGY REGULATORY COMMISSION, Respondent ... PACIFIC GAS AND ELECTRIC COMPANY, Petitioner, ... FEDERAL ENERGY REGULATORY COMMISSION, Respondent ... Hydropower Ass'n, Inc. Louis E. Vincent for petitioner Pacific Gas and Elec. Co. Henri D. Bartholomot for petitioner Edison Elec. Institute. Denis D. Smaage, Deputy Atty ... hydropower industry representatives challenge the Federal Energy Regulatory Commission's (FERC or Commission) issuance of a license for a small hydroelectric project in California. Petitioners ... ...
  • State of California ex rel. Lockyer v. F.E.R.C.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • May 15, 2003
    ... ... Federal Energy Regulatory Commission, Respondent, ... Pacific Gas and Electric Company, National Energy Group, Respondent-Intervenor ... No. 02-70336 ... FERC Nos. EC01-49-002, EC01-41-002 ...         Before: SILVERMAN and GOULD, Circuit Judges, ... (holding that no hearing is required where FERC can decide as a matter of law); Pacific Gas & Elec. Co. v. FERC, 746 F.2d 1383, 1386 (9th Cir.1984) ... Page 709 ... (holding that no hearing is ... ...
  • Pet v. Department of Health Services
    • United States
    • Connecticut Supreme Court
    • May 10, 1988
    ... ... Pacific Gas & Electric Co. v. Federal Energy Regulatory Commission, 746 F.2d 1383, 1387 (9th Cir.1984) ... ...
  • Hi-Tech Furnace Systems v. Fed. Commun Comm'n.
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • August 8, 2000
    ... ... 104-88, 109 Stat. 803 (1995) ... 12 ... 15 U.S.C. SS 717 et seq. See Public Serv. Comm'n v. FERC, 866 F.2d 487, 488 (D.C. Cir. 1989) (noting distinction between proceedings concerning "proposed ... FPC, 293 F.2d 527, 529 (D.C. Cir. 1961); see also, e.g., Pacific Gas and Elec. Co. v. FERC, 746 F.2d 1383, 1387-88 (9th Cir. 1984); Armstrong, Jones & Co. v. SEC, ... ...
  • Request a trial to view additional results
1 books & journal articles
  • CHAPTER 11 ADMINISTRATIVE PRACTICE BEFORE STATE AND FEDERAL AGENCIES
    • United States
    • FNREL - Special Institute Natural Resources & Environmental Litigation II (FNREL)
    • Invalid date
    ...Cases Before Administrative Law Judges, 13 No. 3 Litigation 47 (1987). [30] Pacific Gas & Elec. Co. v. Federal Energy Regulatory Com., 746 F.2d 1383 (9th Cir. 1984). [31] 5 U.S.C. § 552. [32] Renegotiation Bd. v. Bannercraft Clothing Co., 415 U.S. 1 (1974). [33] NLRB v. Sears, Roebuck & Co.......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT