Paine & Nixon Company v. Dahlvick

Decision Date09 February 1917
Docket Number20,123 - (265)
Citation161 N.W. 257,136 Minn. 57
PartiesPAINE & NIXON COMPANY v. OSCAR DAHLVICK
CourtMinnesota Supreme Court

Action in the district court for St. Louis county. The court Dancer, J., ordered judgment in favor of defendant Grande for $91.68, of which sum $58.87 was declared a specific lien upon the premises described in the complaint. His motion for amended findings was denied. From the judgment entered pursuant to the order for judgment, defendant Grande appealed. Affirmed.

SYLLABUS

Mechanic's lien -- evidence -- two unrelated contracts -- extent of lien.

In an action to enforce a mechanic's lien the evidence is held sufficient to sustain a finding that the work done by a lien claimant was done under two separate and unrelated contracts and not as a part of a continuous job and that there was no lien for materials furnished on the contract which was finished more than 90 days prior to the filing of the lien.

Archer & Pickering, for appellant.

Charles Line, for respondent Anderson.

OPINION

DIBELL, C.

Action to enforce a mechanic's lien. Judgment was entered for the defendant Grande against the defendant Dahlvick for $91.68, of which $58.87 was adjudged a lien upon specific property. Grande appeals. His claim is that all of the $91.68 should have been adjudged a lien.

The defendant Anderson was the owner of a lot and building in Virginia. He was making some changes. Dahlvick had the contract for putting in a new front for $350. This contract was completed as early as October 14, 1914, and Dahlvick was paid. Of the material furnished by Grande $32.81 worth was furnished in connection with this front. Later Dahlvick entered into a contract with Anderson for some work in the basement. This work apparently was not in contemplation at the time of the contract for the front. Of the material furnished by Grande $58.87 worth was furnished in connection with this contract. The lien claim of Grande was filed on January 26, 1915. This was within 90 days after the furnishing of the material for the basement, but not within 90 days after the furnishing of the material for the front. The court finds that the contracts for the front and for the basement were separate and distinct, and as a result that the lien claim filed by Grande was not effective as to the material furnished in connection with the front. The only question is whether the finding is sustained by the evidence. If the...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT