Pallardy v. Link's Landing, Inc.
Decision Date | 22 April 1976 |
Docket Number | No. 9761,9761 |
Parties | Roy J. PALLARDY and Seth Evans, Plaintiffs-Appellants, v. LINK'S LANDING, INC., Defendant-Respondent. |
Court | Missouri Court of Appeals |
John E. Burruss, Jr., Hendren & Andrae, Jefferson City, for plaintiffs-appellants.
Charles E. McElyea, Ronald K. Carpenter, Phillips & McElyea Corp., Camdenton, for defendant-respondent.
Before STONE, P.J., and HOGAN and FLANIGAN, JJ.
Plaintiffs brought this action claiming that the sum of $11,989.30 remained due them under the terms of a contract pursuant to which plaintiffs performed architectural services for the defendant. Upon trial to the court plaintiffs had judgment in the amount of $2,192.50, plus interest in the sum of $401.15. Plaintiffs appeal, contending for various reasons that the award of damages was inadequate.
In briefest sketch and outline, the background facts are that on June 30, 1969, James Muff, then vice president of Link's Landing, Inc., contacted plaintiff Roy Pallardy, an architect, concerning proposed improvement and expansion of defendant's docking and parking facilities. The improvements included substantial excavation, the construction of retaining walls, the addition of a parking structure and paving. Pallardy proceeded to prepare estimates and a preliminary sketch of the proposed site improvements, and submitted these to Muff in August 1969; there was considerable disagreement about the possible cost of the project. Pallardy originally estimated $363,140 as the total cost of the improvements; Muff, using estimates obtained from local (Camden County) contractors, insisted that the project could be completed for $259,200. On trial Muff indicated that a $250,000 maximum was a prerequisite to his undertaking the venture. Plaintiffs denied that any limit was placed upon construction costs, but admit they were aware Muff undertook the project in the belief it could be completed for approximately $259,000.
On August 15, 1969, Muff signed a 'letter of intent' which Pallardy had written and sent forward for approval. As material here, the letter reads (emphasis is ours):
Muff signed this letter, and on August 24, 1969, requested Pallardy to prepare contracts for the excavation. On September 18 Muff instructed plaintiffs to complete the preliminary drawings, 'bill him for the drawings and hold up.' The project was held in abeyance until April 1970 when Muff requested an artist's rendering for use in obtaining a loan. The artist's rendering was supplied and Muff obtained a loan, $250,000 of which was set aside for the planned site improvements. In August 1970, after receiving preliminary designs, Muff instructed Pallardy to proceed with the project.
Controversy arose after the excavation work had been begun. On November 9 and 10 plaintiffs' designs and specifications for the retaining walls were taken to contractors for bids. The lowest bid obtained was $150,800; plaintiffs' estimate had been $50,640, and defendant rejected plaintiffs' design. Depending on whose viewpoint one accepts, this disparity was a) caused by plaintiffs' failure to ascertain the condition of the subsoil and design the type of wall required, or was b) the result of Muff's desire to complete the project as quickly as possible, which required the plaintiffs to anticipate 'the worst conditions for subsurface materials.' One of the walls was redesigned and constructed at a total cost of $54,000. The other wall was not built.
By December 17 plaintiffs had completed drawings and specifications for the parking structure. These were mailed to a contractor, and computation of the amounts of rock and concrete required indicated that the parking structure would cost $191,000 as compared with plaintiffs' estimated $120,000. Muff complained to Pallardy, who suggested that bids be obtained before the design was changed. Muff said 'to hell with that' and discharged Pallardy's firm. Thereafter plaintiffs requested payment of 1) full fees based on contract prices for the excavation and for construction of one retaining wall: 2) 75% of the fee for one retaining wall (designed but not constructed, based on the estimated cost); 3) 75% of the fee for the parking structure (designed but not constructed, based on the estimated cost); 4) 25% of the fee for paving (based on preliminary work and estimated cost); and 5) sundry expenses, altogether amounting to $15,736.80, with credit allowed for prior payments of $3,747.50. Muff declined to remit this amount and this action followed. After hearing evidence, the trial court made voluntary findings and entered judgment as follows:
'(1) (T)hat Plaintiffs and Defendants (sic) entered into a contract on August 15, 1969, whereby Plaintiffs agreed to provide architectural services for Defendant, and Defendant agreed to compensate Plaintiffs therefor pursuant to the terms of said contract; (2) that the terms of said contract, inter alia, vested Defendant with the right to do, as the project, 'part or all of the work' upon which Plaintiffs were to provide architectural services; (3) that Plaintiffs' compensation for the project, if it progressed beyond feasibility study phase, was to be six (6%) per cent of the cost of the project; (4) that the project . . . consisted of excavation of construction site and construction of one (1) retaining wall at cost of $45,000.00 and $54,000.00 respectively; (5) that the fee to which Plaintiffs are entitled for said project is $5,940.00; (6) that Plaintiffs have heretofore received payments applicable to said fee totaling $3,747.50; (7) that Defendant owes Plaintiffs a balance thereon in the amount of $2,192.50; (8) that Plaintiffs made demand upon Defendant for payment of sum owed for the aforesaid services on February 27, 1971.
...
To continue reading
Request your trial-
Snadon v. Gayer
...560 S.W.2d 884, 886 (Mo.App.1977); Crossgates Home Ass'n. v. Blomquist, 537 S.W.2d 429, 430(1) (Mo.App.1976); Pallardy v. Link's Landing, 536 S.W.2d 512, 515(2) (Mo.App.1976)); and, insofar as the testimony is conflicting, we are to accord deference not only to the trial court's findings de......
-
Corley v. Kiser
...248 S.W.2d 623, 627(8) (Mo.1952) ; Crossgates Home Ass'n. v. Blomquist, 537 S.W.2d 429, 430(1) (Mo.App.1976); Pallardy v. Link's Landing, Inc., 536 S.W.2d 512, 515(2) (Mo.App.1976); State ex rel. Mayfield v. City of Joplin, 485 S.W.2d 473, 476(8) (Mo.App.1972). Where, as here, no specific f......
-
Juengel Const. Co., Inc. v. Mt. Etna, Inc., 42327
...to perform the contract. Ark Construction Co. v. City of Florissant, 558 S.W.2d 418, 423 (Mo.App.1977); Pallardy v. Link's Landing, Inc., 536 S.W.2d 512, 516 (Mo.App.1976); Sides v. Contemporary Homes, Inc., 311 S.W.2d 117, 120 (Mo.App.1958). This amount, which constitutes lost profits, mus......
-
Marriage of Schatz, In re
...S.W.2d 470, 478 (Mo.1972); Weston v. Great Central Insurance Company, 514 S.W.2d 17, 21[1-3] (Mo.App.1974); Pallardy v. Link's Landing, Inc., 536 S.W.2d 512, 515 (Mo.App.1976). If reasonable men could differ as to the propriety of an action taken by the trial court, there has been no abuse ......