Palm Beach County v. Trinity Industries, Inc., 94-3510

Decision Date25 October 1995
Docket NumberNo. 94-3510,94-3510
Citation661 So.2d 942
Parties20 Fla. L. Weekly D2379 PALM BEACH COUNTY, a political subdivision of the State of Florida, Appellant, v. TRINITY INDUSTRIES, INC., a Delaware corporation, Appellee.
CourtFlorida District Court of Appeals

Anne' Desormier-Cartwright and Denise J. Bleau, West Palm Beach, for appellant.

Paul A. Turk, Jr. of Paul A. Turk, Jr., P.A., West Palm Beach, for appellee.

GUNTHER, Chief Judge.

Appellant, Palm Beach County, defendant below (the County), appeals a final judgment entered after the trial court granted Appellee's, Trinity Industries, Inc., plaintiff below (Trinity), motion for summary judgment as to liability. Because no genuine issue of material fact exists as to liability, we affirm the final judgment.

The County posted a notice of bid for a contract for the furnishing and/or installing of guardrail for various job sites at any location within Palm Beach County. In the bid specifications, the scope provided that the term of the contract should be for dates certain to run twelve months with an option to renew for an additional twelve months. The bid specifications also revealed that the estimated annual expenditure would be $245,000.00.

Subsequently, the Palm Beach County Board of County Commissioners entered into a price agreement with Palm Beach Guardrail and Erosion Control (Palm Beach Guardrail) that set forth the duration of the agreement to run from August 20, 1991 through August 22, 1992 and the estimated dollar value at $247,000.00. Trinity entered this scenario as a subcontractor who provided materials to Palm Beach Guardrail for installation at one of the County's significant job sites. When Palm Beach Guardrail could no longer provide services to the County under the price agreement, the County entered into a price agreement with Rawls & Associates, Inc. to "complete the term of the original price agreement with Palm Beach Guardrail."

In sum, Palm Beach Guardrail performed work for the County worth $196,565.84 pursuant to the price agreement. In fulfilling the time remaining in the original contractual agreement, Rawls & Associates, Inc., provided services to the County in the amount of $39,701.99. Thus, the total work received by the County pursuant to their notice of bid for the furnishing and/or installing of guardrail was in the amount of $236,267.83.

Trinity obtained a default judgment against Palm Beach Guardrail. However, collection of that judgment proved unsuccessful because Palm Beach Guardrail lacked assets. Trinity then filed an action against the County alleging that the County had failed to require Palm Beach Guardrail to post a bond in accordance with section 255.05, Florida Statutes (1991). In the parties' undisputed statement of facts, it is conceded that the County did not require the contractor, Palm Beach Guardrail, to submit a payment and performance bond under section 255.05(1)(a). The parties also stipulated that the estimated annual amount of the guardrail contract between the County and Palm Beach Guardrail was for $250,000.00.

Section 255.05(1)(a), Florida Statutes (1991), requires, in pertinent part:

Any person entering into a formal contract with the state or any county, city, or political subdivision thereof, ... for the construction of a public building or public work shall be required, before commencing the work, to execute, deliver to the public owner, and record in the public records of the county where the improvement is located, a payment and performance bond with a surety insurer authorized to do business in this state as surety....

The statute further exempts those contractors whose contracts fall under $200,000.00 from obtaining a bond:

At the discretion of the official or board awarding such public authority, any person entering into such a contract which is for $200,000 or less may be exempted from executing the payment and performance bond.

This court has noted that the above statute is remedial in nature and therefore, entitled to a liberal construction, within reason, to effect its intended purpose. Fidelity and Deposit Co. of Maryland v. Waldron's Inc., 608 So.2d 119, 120 (Fla. 4th DCA 1992). Historically, the purpose of this section is to protect subcontractors and suppliers by providing them with an alternative remedy to mechanic's liens on public projects. School...

To continue reading

Request your trial
6 cases
  • Thorpe v. Myers
    • United States
    • Florida District Court of Appeals
    • July 15, 2011
  • Martin v. Howard (In re Ansley)
    • United States
    • Florida District Court of Appeals
    • August 17, 2012
  • Aquatic Plant Mgt. v. Paramount Engineering
    • United States
    • Florida District Court of Appeals
    • November 28, 2007
    ...977 So.2d 600 ... AQUATIC PLANT MANAGEMENT, INC., Appellant, ... PARAMOUNT ENGINEERING, INC. and ... " on publicly-owned property in Broward County. Paramount subcontracted with Aquatic Plant ... Palm Beach County v. Trinity Indus., Inc., 661 So.2d ... ...
  • Runyon Enterprises, Inc. v. S.T. Wicole Const. Corp. of Florida, Inc., 95-1633
    • United States
    • Florida District Court of Appeals
    • July 3, 1996
    ... ... a formal contract with the state or any county ... for the construction of a public building ... reason, to effect its intended purpose." Palm Beach County v. Trinity Indus., Inc., 661 So.2d ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT