Pan American Engineering Co., Inc. v. Poncho's Const. Co., 00-197

Decision Date17 September 1980
Docket NumberNo. 00-197,00-197
Citation387 So.2d 1052
PartiesPAN AMERICAN ENGINEERING CO., INC., a Florida Corporation, Appellant, v. PONCHO'S CONSTRUCTION CO., Appellee. /T1-111. .
CourtFlorida District Court of Appeals

Burton L. Bruggeman, Orlando, for appellant.

Linton S. Waterhouse, Orlando, for appellee.

FRANK D. UPCHURCH, Jr., Judge.

Appellee Poncho's Construction Company obtained a judgment enforcing a mechanic's lien for work performed on a sewage collection and storm drainage system. Appellee was a sub-contractor retained by appellant Pan American Engineering Company, Inc., which was the prime contractor, and was to complete all phases of a sub-contract on which a prior sub-contractor had defaulted. The contract between appellant and appellee required all change orders to be in writing and signed by appellant.

The first question raised by this appeal is whether the trial court erred by allowing into evidence both the requests for written change orders and oral testimony in support thereof, when the contract language stated that only written change orders, signed by the contractor, would be honored.

The contract specifically provided:

No changes are to be made, however, except upon written order from the Contractor, and the Contractor shall not be held liable to subcontractor for any extra labor or materials furnished without such written order.

There is solid support for the principle that written contracts can be modified by subsequent oral agreement of the parties, even though the written contract purports to prohibit such modification. Barile Excavating v. Vacuum Under-Drain, 362 So.2d 117 (Fla. 1st DCA 1978); Vitra-Spray of Florida, Inc. v. Gumenick, 144 So.2d 533 (Fla. 3d DCA 1962). In Vitra-Spray, the court held that the possibility of waiver of the contract provision by subsequent dealings of the parties existed which would render it a fraud upon one party for the other to refuse to perform the alleged oral modification.

It is also possible for a subsequent modification to result from the conduct of the parties. Barile Excavating at 119; Fletcher v. Laguna Vista Corp., 275 So.2d 579 (Fla. 1st DCA 1973). In Fletcher, the contractor was awarded $68,000.00 in increased costs following completion of apartments constructed for owner. The owner contended that the total sum payable to the contractor was pursuant to a valid written contract and could not be increased without the owner's written consent. The contractor had presented the owner with two change orders based on increased overhead costs incurred by the contractor in construction of the apartments but owner refused to sign the orders. 1 The First District Court of Appeal affirmed an award to contractor, declaring that the manner in which the parties interpreted the contract through their course of dealings is of great significance. The court found that the owner was aware of some increase in the cost of overhead and never objected and had previously accepted one change order not signed in accordance with the contract. Hence, the parties modified the contract by their course of dealings.

Therefore, the trial court here was not in error in permitting the introduction of the requests for change orders since the written contract could have been modified by them. The essential question is whether there is substantial, competent evidence in the record to support the trial court's determination that a modification or waiver of rights under the contract occurred. See Wiener v. Wiener, 343 So.2d 1319 (Fla. 3d DCA 1977). Because this matter will be remanded for new trial, we need not reach this question.

The second question is whether the trial court abused its discretion by not allowing appellant's counsel to make final oral argument.

At the close of defendant's case, the court gave plaintif...

To continue reading

Request your trial
27 cases
  • Concourse Beauty School, Inc. v. Polakov
    • United States
    • U.S. District Court — Southern District of New York
    • May 9, 1988
    ...order to modify. Linear Corp. v. Standard Hardware Co., 423 So.2d 966, 968 (Fla.Dist.Ct.App.1982); Pan American Engineering v. Poncho's Const., 387 So.2d 1052, 1053 (Fla.Dist.Ct. App.1980); Barile Excavating v. Vacuum Under-Drain, 362 So.2d 117 (Fla.Dist.Ct. App.1978); Fletcher v. Laguna Vi......
  • County of Brevard v. Miorelli Engineering, Inc.
    • United States
    • Florida Supreme Court
    • October 23, 1997
    ...a written change order. See, e.g., Charlotte Harbor, 56 Fla. at 227, 48 So. at 217. See also Pan American Engineering Co., v. Poncho's Construction Co., 387 So.2d 1052, 1053 (Fla. 5th DCA 1980); Doral Country Club, Inc. v. Curcie Bros., Inc., 174 So.2d 749, 750-51 (Fla. 3d DCA 1965). 5 In F......
  • In re General Plastics Corp.
    • United States
    • United States Bankruptcy Courts. Eleventh Circuit. U.S. Bankruptcy Court — Southern District of Florida
    • August 19, 1993
    ...4. Of course, terms in a contract may be modified by the subsequent conduct of the parties. Pan American Engineering Co., Inc. v. Poncho's Construction Co., 387 So.2d 1052, 1053 (Fla. DCA 1980). However, there was no evidence in this case to prove that the parties' course of conduct modifie......
  • KIWANIS CLUB v. de Kalafe
    • United States
    • Florida District Court of Appeals
    • October 14, 1998
    ...Distrib. Sys., Inc., 485 So.2d 1336, 1340 (Fla. 3d DCA), review denied, 497 So.2d 1217 (Fla.1986); Pan Am. Eng'g Co., Inc. v. Poncho's Constr. Co., 387 So.2d 1052, 1053 (Fla. 5th DCA 1980); Wiener v. Wiener, 343 So.2d 1319, 1322 (Fla. 3d DCA 1977). Additionally, as de Kalafe is not a party ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT