Panda-Kathleen, L.P./Panda Energy Corp. v. Clark, PANDA-KATHLEE

CourtUnited States State Supreme Court of Florida
Writing for the CourtWELLS; KOGAN; SHAW
Citation701 So.2d 322
Parties22 Fla. L. Weekly S571 P./PANDA ENERGY CORPORATION, Appellant, v. Susan F. CLARK, et al., as the Florida Public Service Commission, and Florida Power Corporation, Appellees.
Decision Date18 September 1997
Docket NumberNo. 88280,PANDA-KATHLEE,L

Page 322

701 So.2d 322
22 Fla. L. Weekly S571
PANDA-KATHLEEN, L.P./PANDA ENERGY CORPORATION, Appellant,
v.
Susan F. CLARK, et al., as the Florida Public Service Commission, and Florida Power Corporation, Appellees.
No. 88280.
Supreme Court of Florida.
Sept. 18, 1997.
Rehearing Denied Nov. 13, 1997.

Page 323

Arthur J. England, Jr., David L. Ross, and Joe N. Unger of Greenberg, Traurig, Hoffman, Lipoff, Rosen & Quentel, P.A., Miami, for Appellant.

Robert D. Vandiver, General Counsel, and Richard C. Bellak, Associate General Counsel, Florida Public Service Commission, Tallahassee; James A. McGee and Jeffrey A. Froeschle, Office of the General Counsel, Florida Power Corporation, St. Petersburg; and Alan C. Sundberg and Sylvia H. Walbolt of Carlton, Fields, Ward, Emmanuel, Smith & Cutler, P.A., St. Petersburg, for Appellees.

WELLS, Justice.

Panda-Kathleen, L.P./Panda Energy Company (Panda) appeals Order No. PSC-96-0671-FOF-E1 of the Florida Public Service Commission (the Commission) regarding Panda's standard-offer contract with Florida Power Corporation (FPC) to provide electricity through the process of cogeneration. We have jurisdiction. Art. V, § 3(b)(2), Fla. Const. For the reasons expressed, we find that the Commission had jurisdiction and affirm the Commission's order, holding that the Commission's jurisdiction is proper and that Order No. PSC 96-0671-FOF-EI is affirmed.

This action was commenced at the Commission on January 25, 1995, when FPC filed a petition for declaratory statement regarding certain aspects of its standard-offer cogeneration contract with Panda. On November 25, 1991, Panda and FPC entered into the standard-offer contract at issue, which required Panda to provide and FPC to purchase 74.9 megawatts of cogenerated electricity at all times while the contract was in effect. The contract was entitled "Standard

Page 324

Offer Contract for the Purchase of Firm Capacity and Energy from a Qualifying Facility Less than 75 megawatts or a Solid Waste Facility." The contract incorporated the Commission's rules pertinent to cogeneration contracts, including rule 25-17.0832, Florida Administrative Code. The contract also incorporated appendices. The Commission approved the contract on October 22, 1992. In re Fla. Power Corp., Docket No. 91142-EQ, Order No. PSC 92-1202-FOF-EQ (F.P.S.C. Oct. 22, 1992).

Among the rules that were incorporated were Commission rule 25-17.0832(3)(a), which referred to "the purchase of firm capacity and energy from small qualifying facilities less than 75 megawatts," and Commission rule 25-17.0832(3)(e)6., which stated:

T]he period of time over which firm capacity and energy shall be delivered from the qualifying facility to the utility [is] ... [a]t a maximum ... equal to the anticipated plant life of the avoided unit, commencing with the anticipated in-service date of the avoided unit[.

The Commission's rules derive from section 366.051, Florida Statutes (1991), which is consistent with the cogeneration provisions of the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. §§ 824-824m (1994), and which provides that qualifying facilities (QFs) such as Panda can sell energy to utility companies at but not exceeding full avoided cost. "Avoided cost" is the cost that a utility avoids by purchasing electrical power from a QF rather than generating the electrical power itself or purchasing the power from another source. Schedule 2 to appendix C of this contract identified the economic plant life of the unit avoided by this contract as equal to twenty years.

FPC's petition before the Commission alleged that Panda proposed to construct a cogeneration facility of 115 megawatts and that, by reason of having typed within a blank space on the contract a contract expiration date of 2025, Panda was asserting the right to capacity payments for a period of time exceeding by ten years the twenty-year economic plant life of the avoided unit. The petition sought an order declaring (1) that the standard offer contract is not available if Panda configures its facility to have a capacity in excess of seventy-five megawatts, and (2) that if the Commission determines that the contract remains available to Panda, FPC has no obligation under the contract to make any payments to Panda after December 2016, the end of the twenty-year life of the avoided unit.

On February 6, 1995, Panda sought to intervene in the declaratory statement proceeding before the Commission. The Commission granted intervention on March 6, 1995. On March 14, 1995, Panda filed a motion for declaratory statement seeking an order declaring Panda's proposed 115-megawatt facility to be consistent with rule 25-17.0832(3)(a) and declaring that the contract the Commission had previously approved provided for a thirty-year time period of payments. On June 29, 1995, Panda filed a petition for a formal evidentiary proceeding and full commission hearing. In their respective pleadings, FPC and Panda each acknowledged the Commission's jurisdiction to adjudicate those issues related to the contract, with Panda specifically asserting in its petition for evidentiary and full commission hearings that "the Commission has the right, and in these circumstances the obligation, to convene and conduct a formal evidentiary proceeding pursuant to section 120.57(1), Florida Statutes."

However, on September 12, 1995, in an apparent change of position, Panda filed a motion to dismiss and motion to stay or abate proceedings. Panda asserted that PURPA preempted the Commission's jurisdiction as to issues involving a standard-offer contract arising after the Commission's initial approval of the contract and that such issues must be decided by a court of competent jurisdiction. By order dated December 27, 1995, the Commission denied Panda's motions. The Commission stated in its order:

The relief FPC has requested here does not conflict with federal regulations or subject Panda to "utility-type" state rate regulation. It seeks an answer to two questions: 1) Under the provisions of Rule 25-17.0832(3)(a), Florida Administrative Code, as applied to the standard offer at issue, is Panda permitted to build a cogeneration

Page 325

facility larger than 75 MW; 2) Under the provisions of Rule 25-17.0832(3)(e)(6), Florida Administrative Code, as applied to the standard offer at issue, is Florida Power obligated to make firm capacity and energy payments to Panda for more than 20 years. Certainly we have the authority to answer those questions.

In re Panda-Kathleen, L.P., Docket No. 950110-EI, Order No. PSC 95-1590-FOF-EI (F.P.S.C. Dec. 27, 1995).

An evidentiary hearing was held in February 1996. The Commission issued an order on May 20, 1996, in which it determined: (1) that Panda's proposed 115-megawatt facility does not comply with rule 25-17.0832, Florida Administrative Code; (2) that FPC is only responsible for firm capacity payments to Panda and eligible for cost recovery of those payments for twenty years in compliance with rule 25-17.0832; (3) that Panda will only be responsible for supplying firm capacity for twenty years; (4) that the contractual milestone dates are extended by a period of time equal to the time necessary for deciding matters in this docket, which was determined to be a period of eighteen months; and (5) that Panda should receive a twenty-year capacity payment stream, using the payment...

To continue reading

Request your trial
5 practice notes
  • Wheelabrator Lisbon v. Public Util. Control, No. 17691.
    • United States
    • Supreme Court of Connecticut
    • August 28, 2007
    ...18. See footnote 9 of this opinion for the text of General Statutes § 22a-207(9). 19. The defendants cite Panda-Kathleen, L.P. v. Clark, 701 So.2d 322 (Fla.1997), cert. denied sub nom. Panda-Kathleen, L.P. v. Florida Power Corp., 523 U.S. 1073, 118 S.Ct. 1514, 140 L.Ed.2d 668 (1998), and In......
  • Florida Power Corp. v. Garcia, No. SC94665.
    • United States
    • United States State Supreme Court of Florida
    • March 1, 2001
    ...and energy to be delivered by the qualifying facility under the contract"). As stated by this Court in Panda-Kathleen, L.P. v. Clark, 701 So.2d 322, 324 (Fla.1997), "`[a]voided cost' is the cost that a utility avoids by purchasing electrical power from a QF rather than generating the electr......
  • WEST FLORIDA ELEC. CO-OPERATIVE ASSOCIATION v. Jacobs, No. SC02-176.
    • United States
    • United States State Supreme Court of Florida
    • October 21, 2004
    ...in the area. It is not this Court's task, however, to reweigh the evidence and the factors considered. See Panda-Kathleen, L.P. v. Clark, 701 So.2d 322, 328 (Fla.1997) (stating that review of commission orders is to determine whether they are supported by competent, substantial evidence or ......
  • Wheelabrator Lisbon, Inc. v. Connecticut Dept. of Public Utility Control, No. CV05-4003405 (CT 3/20/2006), No. CV05-4003405
    • United States
    • Supreme Court of Connecticut
    • March 20, 2006
    ...F.3rd 1178 (3rd Cir. 1995); Crossroads Cogeneration v. Orange and Rockland, 159 F.3rd 129 (3rd Cir. 1998); Panda-Kathleen, L.P. v. Clark, 701 So.2d 322 (FLA. In its petition to DPUC which resulted in the 1991 WLI decision, WLI sought 1) a "declaratory ruling that the Lisbon Trash-to-Energy ......
  • Request a trial to view additional results
5 cases
  • Wheelabrator Lisbon v. Public Util. Control, No. 17691.
    • United States
    • Supreme Court of Connecticut
    • August 28, 2007
    ...18. See footnote 9 of this opinion for the text of General Statutes § 22a-207(9). 19. The defendants cite Panda-Kathleen, L.P. v. Clark, 701 So.2d 322 (Fla.1997), cert. denied sub nom. Panda-Kathleen, L.P. v. Florida Power Corp., 523 U.S. 1073, 118 S.Ct. 1514, 140 L.Ed.2d 668 (1998), and In......
  • Florida Power Corp. v. Garcia, No. SC94665.
    • United States
    • United States State Supreme Court of Florida
    • March 1, 2001
    ...and energy to be delivered by the qualifying facility under the contract"). As stated by this Court in Panda-Kathleen, L.P. v. Clark, 701 So.2d 322, 324 (Fla.1997), "`[a]voided cost' is the cost that a utility avoids by purchasing electrical power from a QF rather than generating the electr......
  • WEST FLORIDA ELEC. CO-OPERATIVE ASSOCIATION v. Jacobs, No. SC02-176.
    • United States
    • United States State Supreme Court of Florida
    • October 21, 2004
    ...in the area. It is not this Court's task, however, to reweigh the evidence and the factors considered. See Panda-Kathleen, L.P. v. Clark, 701 So.2d 322, 328 (Fla.1997) (stating that review of commission orders is to determine whether they are supported by competent, substantial evidence or ......
  • Wheelabrator Lisbon, Inc. v. Connecticut Dept. of Public Utility Control, No. CV05-4003405 (CT 3/20/2006), No. CV05-4003405
    • United States
    • Supreme Court of Connecticut
    • March 20, 2006
    ...F.3rd 1178 (3rd Cir. 1995); Crossroads Cogeneration v. Orange and Rockland, 159 F.3rd 129 (3rd Cir. 1998); Panda-Kathleen, L.P. v. Clark, 701 So.2d 322 (FLA. In its petition to DPUC which resulted in the 1991 WLI decision, WLI sought 1) a "declaratory ruling that the Lisbon Trash-to-Energy ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT