Park Side Constr. Contractors, Inc. v. Bryan's Quality Plus, LLC

Decision Date20 December 2017
Docket NumberIndex No. 600492/14,2016–10331
Citation68 N.Y.S.3d 90,156 A.D.3d 804
Parties PARK SIDE CONSTRUCTION CONTRACTORS, INC., plaintiff-respondent, v. BRYAN'S QUALITY PLUS, LLC, defendant third-party plaintiff-appellant, Rossana Storani, et al., defendants-appellants; Darwin National Assurance Company, et al., third-party defendants-respondents.
CourtNew York Supreme Court — Appellate Division

Joseph A. Fazio, Mineola, NY, for defendants-appellants and defendant third-party plaintiff-appellant.

Anthony A. Capetola, Williston Park, N.Y. (Robert Johnson of counsel), for plaintiff-respondent and third-party defendants-respondents.

JOHN M. LEVENTHAL, J.P., CHERYL E. CHAMBERS, JOSEPH J. MALTESE, COLLEEN D. DUFFY, JJ.

DECISION & ORDER

Appeal from a judgment of the Supreme Court, Nassau County (Timothy S. Driscoll, J.), entered November 3, 2016. The judgment, insofar as appealed from, after a nonjury trial, (1) dismissed the counterclaims asserted by the defendants Rossana Storani and Bryan Gallagher and the defendant third-party plaintiff, Bryan's Quality Plus, LLC, as against the plaintiff, (2) dismissed the third-party complaint asserted by the defendant third-party plaintiff, Bryan's Quality Plus, LLC, and (3) directed the defendant third-party plaintiff, Bryan's Quality Plus, LLC, to deliver certain property to the plaintiff.

ORDERED that the judgment is affirmed insofar as appealed from, with costs.

This action arises out of contractual disputes pertaining to two construction projects. In May 2013, Park Side Construction Contractors, Inc. (hereinafter Park Side), entered into subcontracts with Bryan's Quality Plus, LLC (hereinafter BQP), a "piling contractor," for drilling services at a construction site in Brooklyn and another in Manhattan.

In the middle of drilling at the Brooklyn site, BQP encountered difficulties with the soil, which required that it make changes to the means and methods of drilling. When BQP completed the project, it sought additional payments from Park Side to cover expenses arising from the changes, which Park Side rejected.

On the Manhattan site, BQP never had an opportunity to start drilling because there was a stop-work order in effect.

Before it learned of the stop-work order, BQP acquired materials for the project. Park Side made payments for the materials. BQP kept the materials in storage with the expectation that construction would soon commence. However, Park Side hired a different subcontractor to perform drilling on the Manhattan site.

In January 2014, BQP filed notices of mechanic's lien for the sums of $711,637.63 and $410,337, respectively, representing the additional work it performed on the Brooklyn site, and an allegedly unpaid balance for materials provided to, and work performed in connection with, the Manhattan site. The liens were subsequently discharged pursuant to Lien Law § 19(4) by the filing of undertakings in an amount that represented 110% of each lien. Darwin National Assurance Company (hereinafter Darwin) served as surety for Park Side on both lien discharge bonds.

In February 2014, Park Side commenced this action against BQP, its president, Rossana Storani, and her husband, Bryan Gallagher (hereinafter collectively the BQP parties), seeking, inter alia, (1) an order of seizure over the materials that it had purchased for, and which BQP never delivered to, the Manhattan site, (2) a declaration that the mechanic's liens were void pursuant to Lien Law § 39, and (3) damages for the amounts demanded by the liens in excess of the costs of materials or labor actually provided, together with costs and attorneys' fees. The BQP parties asserted counterclaims seeking, inter alia, to foreclose on the mechanic's liens, and damages for Park Side's alleged breach of the subcontracts. In June 2014, BQP commenced a third-party action against, among others, Darwin, as surety to Park Side, to foreclose on the mechanic's liens.

In December 2014, Park Side moved for the summary discharge of the mechanic's liens, arguing that the notices for the liens were fatally flawed because BQP provided a post office box address, rather than the address for its principal place of business in New York State. The BQP parties cross-moved for leave to amend the notices of mechanic's lien nunc pro tunc. In an order entered July 21, 2015, the Supreme Court denied Park Side's motion, and granted the BQP parties' cross motion.

Park Side appealed from that order. Although, for the reasons set forth in our decision and order on the related appeal, that appeal was dismissed (see Park Side Constr. Contr., Inc. v. Bryan's Quality Plus, LLC, 156 A.D.3d 803 [Appellate Division Docket No. 2015–06772; decided herewith] ), the issues raised therein are brought up for review on the appeal herein from the judgment (see CPLR 5501[a][1] ; Matter of Aho, 39 N.Y.2d 241, 248, 383 N.Y.S.2d 285, 347 N.E.2d 647 ).

The BQP parties subsequently moved, inter alia, to strike Park Side's pleadings pursuant to CPLR 3126 for failing to comply with a court order directing the disclosure of certain discovery. The motion was denied. Following a nonjury trial, the Supreme Court determined that Park Side was entitled to an order of seizure over the materials that were intended for the Manhattan site for which it had paid. The court found that there was a lack of credible evidence supporting the other various claims. Accordingly, the court dismissed Park Side's remaining causes of action, all of the counterclaims asserted by the BQP parties, and BQP's third-party complaint.

A judgment was entered, and this appeal by the BQP parties ensued.

Initially, contrary to Park Side's contention, affording the Lien Law its liberal construction to protect the beneficial interests of lienors (see Lien Law § 23 ; Matter of CAFS Mgmt. Corp. v. Q Realty & Dev., Inc., 143 A.D.3d 892, 893, 39 N.Y.S.3d 216; East Coast Mines & Materials Corp. v. Golf Course Props. Co., 228 A.D.2d 545, 644 N.Y.S.2d 326 ), the use of a post office box address rather than the address of a foreign corporation's principal place of business within the state is a nonjurisdictional defect capable of amendment pursuant to Lien Law § 12–a(2) (see Matter of CAFS Mgmt. Corp. v. Q Realty & Dev., Inc., 143 A.D.3d at 893, 39 N.Y.S.3d 216 ; Vitale Dev. Group, Inc. v. Kinsman, 138 A.D.3d 1109, 1111, 30 N.Y.S.3d 325 ; Johnson v. Robertson, 63 A.D.3d 690, 690, 879 N.Y.S.2d 723 ). Thus, the Supreme Court properly denied Park Side's motion to summarily discharge the liens, and granted the BQP parties' cross motion for leave to amend the notices.

In addition, the Supreme Court providently exercised its discretion in denying that branch of the BQP parties' motion which was to strike Park Side's pleadings pursuant to CPLR 3126. In general, the nature and...

To continue reading

Request your trial
15 cases
  • Ewa v. City of N.Y.
    • United States
    • New York Supreme Court — Appellate Division
    • September 2, 2020
    ...I.J.J.A., Inc. v. Daimler Buses of N. Am., Inc. , 172 A.D.3d 819, 820, 101 N.Y.S.3d 70 ; see Park Side Constr. Contrs., Inc. v. Bryan's Quality Plus, LLC , 156 A.D.3d 804, 68 N.Y.S.3d 90 ). The striking of a pleading may be appropriate where there is a clear showing that the failure to comp......
  • Patel v. Garden Homes Mgmt. Corp.
    • United States
    • New York Supreme Court — Appellate Division
    • December 20, 2017
    ...that Garden Homes had a prescriptive easement over a portion of the Patels' property (see id. at 1133–1134, 856 N.Y.S.2d 245 ;see also68 N.Y.S.3d 90 Garden Homes Mobile Home Park Co. LP v. Patel, 100 A.D.3d at 689, 954 N.Y.S.2d 165 ; Greenhill v. Stillwell, 306 A.D.2d 434, 435, 761 N.Y.S.2d......
  • Sun v. Lee
    • United States
    • New York Supreme Court — Appellate Division
    • January 18, 2023
    ...Daimler Buses of N. Am., Inc., 172 A.D.3d 819, 820, 101 N.Y.S.3d 70 ; see Park Side Constr. Contrs., Inc. v. Bryan's Quality Plus, LLC, 156 A.D.3d 804, 806–807, 68 N.Y.S.3d 90 ). The striking of a pleading may be appropriate where there is a clear showing that the failure to comply with dis......
  • Empire Enters. I.J.J.A., Inc. v. Daimler Buses of N. Am., Inc.
    • United States
    • New York Supreme Court — Appellate Division
    • May 8, 2019
    ...it is within the court's discretion to strike or dismiss a pleading (see Park Side Constr. Contrs., Inc. v. Bryan's Quality Plus, LLC, 156 A.D.3d 804, 68 N.Y.S.3d 90 ; Friedman, Harfenist, Langer & Kraut v. Richard Bruce Rosenthal, 79 A.D.3d 798, 914 N.Y.S.2d 196 ). The drastic remedy of di......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT