Paul Sardella Const. Co., Inc. v. Braintree Housing Authority

Decision Date21 October 1976
Citation356 N.E.2d 249,371 Mass. 235
PartiesPAUL SARDELLA CONSTRUCTION CO., INC. v. BRAINTREE HOUSING AUTHORITY et al. 1
CourtUnited States State Supreme Judicial Court of Massachusetts Supreme Court

Sally A. Corwin, Boston (Joseph P. Hurley, Braintree, with her), for Braintree Housing Authority.

George Waldstein, Boston, for plaintiff.

Theodore A. Glynn, Jr., Boston, and John W. Gahan, III, Gardner, for Joseph E. Findlen and others, submitted a brief.

Before HENNESSEY, C.J., and REARDON, QUIRICO, BRAUCHER and WILKINS, JJ.

HENNESSEY, Chief Justice.

A judge of the Superior Court ruled, as matter of law, that the Braintree Housing Authority (authority) 2 was liable in damages for breach of contract to Paul Sardella Construction Co. Inc. (Sardella) for wrongfully rescinding the award to Sardella of a contract for the construction of a State-aided housing project for the elderly. 3 The matter was reported to the Appeals Court pursuant to Mass.R.Civ.P. 64, 365 Mass. 831 (1974), for determination of the correctness of the trial judge's rulings. The Appeals Court rendered a decision, holding that the reported rulings were correct. Paul Sardella Constr. Co. v. Braintree Housing Authority, --- Mass.App. --- a, 329 N.E.2d 762 (1975). The case was ordered remanded to the Superior Court for determination of the monetary damages to be assessed against the authority in accordance with the Appeals Court's further holding that the proper measure of damages was the reasonable cost to Sardella of preparing its bid on the project. Both Sardella and the authority petitioned the Appeals Court for a rehearing of the case, which petitions were denied. We allowed the authority's petition for leave to obtain further appellate review. Mass.R.A.P. 27.1, --- Mass. --- (1975).

We summarize the facts, as stated in the opinion of the Appeals Court, --- Mass.App. at --- - --- b, 329 N.E.2d 762, and obtained originally from a stipulation of the parties.

Sometime prior to September 15, 1971, the authority invited bids pursuant to the provisions of the fair competition for bidders of public works act (G.L. c. 149, §§ 44A--44L) for the construction of a State-aided housing project for the elderly. Thereafter, the bids of the subcontractors were opened, with the defendant Mazza found to be the lowest responsible and eligible bidder for the plumbing subcontract. Mazza's subbid was unrestricted with respect to its willingness to enter into a subcontract with any general contractor. On September 15, 1971, the bids of the general contractors were opened, with Sardella found to be the lowest responsible and eligible general bidder. Sardella listed Mazza as its plumbing subcontractor, as did the second lowest bidder. The defendant Findlen, the third lowest bidder, listed Duggan Construction Co., Inc., as its plumbing subcontractor.

On September 29, 1971, Mazza wired the authority purporting to withdraw its subbid on the basis of an alleged clerical error, and confirmed that action by a letter sent the following day.

On October 20, 1971, the authority voted to award the contract to Sardella as the lowest responsible and eligible general bidder. See G.L. c. 149, § 44A. The award was subject to the approval of the Department of Community Affairs. See G.L. c. 121B, § 31. On October 26, 1971, Sardella notified Mazza that it had been selected by the authority as the subcontractor and on November 15 sent Mazza proper subcontracts for its signature.

Mazza failed to execute the subcontracts within five days (G.L. c. 149, § 44I(3)) and returned the unexecuted subcontracts to Sardella an November 22, 1971, notifying Sardella and the authority of its refusal to execute 'due to a bona fide clerical error' in its bid.

Thereafter, the authority reviewed all the other eligible and responsible plumbing subbids and determined that if any one of those bids was to be substituted in place of Mazza's, Findlen's bid would be the lowest general bid. The authority then voted on November 24, 1971, to rescind its award of the general contract to Sardella and to award that contract to Findlen. Sardella was not invited to nor was it represented at the meeting at which such votes were taken. A notice of the decision was mailed to Sardella, and it immediately lodged a protest with the Department of Labor and Industries, which conducted an investigation and held a conference on December 7, 1971. See G.L. c. 149, § 44K. On January 7, 1972, that department rendered its decision upholding the action of the authority in awarding the general contract to Findlen.

At a meeting held on December 15, 1971, the authority found that 'a bona fide clerical error had been made by Mazza' and voted to return Mazza's deposit (which it subsequently did). See G.L. c. 149, § 44B(3). Sardella was not notified of that meeting.

On January 20, 1972, the authority and Findlen executed a contract for the project. The contract was approved by the Department of Community Affairs. Findlen has been paid the contract price, with the exception of a small amount held back pending the completion of certain seeding operations.

Both Sardella and Findlen were eligible and responsible bidders at all material times. 4

We conclude that there was no error. In reaching that conclusion we agree with the result, and in general we agree with the reasoning, of the Appeals Court. However, we expand somewhat on the analysis of the Appeals Court in support of our determination that § 44I(3) is applicable. This extended discussion is recommended because of the ambiguities of the language in two subsections of the statute, as well as the obvious importance to the public and the parties in other cases of the application of the proper statutory provisions in a situation of this type with its potential for recurrence.

Preliminarily, we observe that Sardella could not prevail, at least in the circumstances of this case, if it were determined that § 44I(2) were controlling. That section is obviously designed to cause review of the lowest responsible general bid in the public interest, and with a view toward economy. This is to be accomplished, if at all, by substitution of subbidders, but the language of the section is not mandatory and hardly seems supportive of a claim like Sardella's in this case (e.g., the substitution is to be by 'agreement' and the parties are to 'jointly consider'). Further, in the stipulation of facts proffered by the parties in this case, there is no information from which this court could infer that a substitution of subbidders, whether concerned with plumbing or other trades, would restore Sardella as lowest responsible general bidder. By contrast, application of § 44I(3) protects Sardella's position after disappearance of the subbidder Mazza, and permits only an adjustment of the contract price.

The trial judge framed the crucial issue in this case in this way: '(W)here a sub-bidder of the lowest responsible and eligible general bidder refuses to execute his subcontract, should the procedures of G.L. c. 149, § 44I(2) 5 or 44I(3) 6 be followed?' (emphasis supplied; footnotes added). He concluded that § 44I(3) was the controlling section on the facts of the case, primarily because § 44I(2) could not, in his view, have been applicable for several reasons. The judge acknowledged that there were problems with the application of § 44I(3), but he nevertheless considered the result more equitable than if § 44I(2) were held to apply.

The arguments in support of the application of § 44I(2) are somewhat persuasive. Thus it is the authority's contention that § 44I(3) prescribes a procedure to be followed only after final award of a contract to the general bidder selected as the general contractor. Thus, § 44I(3) addresses itself to a possible adjustment of 'the contract price.' See note 6 supra. This language should be contrasted with the wording of § 44I(2), which speaks of permissible adjustments to the 'general bid price.' See note 5 supra. Similarly, § 44I(2) refers uniformly in several places to the 'general bidder,' whereas by contrast § 44I(3) refers to 'the general bidder selected as the general contractor' (emphasis supplied). It is argued that these two subsections are designed to apply at two different stages in the process of bid selection and award.

From this contention, it is argued that § 44I(3) should not have been held applicable in this case because no final award of the contract was ever made to Sardella. 7 Compare Crenshaw County Hosp. Bd. v. St. Paul Fire & Marine Ins. Co., 411 F.2d 213, 214--215 (5th Cir. 1969), with Peerless Cas. Co. v. Housing Authority of Hazelhurst, 228 F.2d 376, 378--379 (5th Cir. 1955), and Lexington Housing Authority v. Continental Cas. Co., 210 F.Supp. 732, 735 (W.D.Tenn.1962).

Nevertheless, we recognize compelling reasons why § 44I(3) should be applied here. First of all, we agree with the analysis of the Appeals Court. That court reasoned that the judge was correct in ruling that § 44I(3) should have been followed because 'that section specifically provides the proper route to follow where, as here, there is a failure by the selected subbidder to execute a subcontract.'

Mass.App. at --- - --- c, 329 N.E.2d at 762--765. That court further reasoned, and we think correctly, that the problems with this result, which were envisioned by the trial judge in the statement of reasons given for his rulings, were offset by the fact that the authority was 'protected from the impact' (id. at --- d), 329 N.E.2d at 762, of any increased contract price that might result through the operation of § 44I(3) because the authority could retain all or a portion of the bid deposit of a subbidder as liquidated damages if the subbidder 'fail(ed) to perform his agreement to execute a subcontract with the general bidder selected as the general contractor.' G.L. c. 149, § 44B(3), as amended through St.1961, c. 604, § 2.

Convincing support for this result...

To continue reading

Request your trial
34 cases
  • Com. v. Kobrin
    • United States
    • Appeals Court of Massachusetts
    • September 12, 2008
    ... ... (PSE) and PSE-COR Provider, Inc. (PSE-COR), of one count each of Medicaid fraud ... instruction that "regulations have the authority of law," left the jury with the impression that ... ...
  • Owen of Georgia, Inc. v. Shelby County
    • United States
    • U.S. Court of Appeals — Sixth Circuit
    • June 17, 1981
    ...its awards." Paul Sardella Construction Co. v. Braintree Housing Authority, 3 Mass.App. 326, 329 N.E.2d 762 (1975), aff'd 371 Mass. 235, 356 N.E.2d 249 (1976). Indeed, it is doubtful that many contractors would bid at all knowing the deck was stacked against In its solicitation of bids purs......
  • Petricca Const. Co. v. Com.
    • United States
    • Appeals Court of Massachusetts
    • October 5, 1994
    ...continuing interest in pursuing a judgment against the department for bid preparation costs. See Paul Sardella Constr. Co. v. Braintree Hous. Authy., 371 Mass. 235, 243, 356 N.E.2d 249 (1976). More significantly, "we have on occasion answered questions in moot cases where the issue was one ......
  • Abdow v. Attorney Gen.
    • United States
    • United States State Supreme Judicial Court of Massachusetts Supreme Court
    • June 24, 2014
    ... ... Springfield Convention and Visitors Bureau, Inc. Edward L. Sweda, Jr., Boston, for Public Health ... [11 N.E.3d 578] act also transferred the authority to license and regulate the racing industry from ... Co. v. Secretary of the Commonwealth, 403 Mass ... See Paul Sardella Constr. Co. v. Braintree Hous. Auth., 3 ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT