Paul W. Abbott, Inc. v. Axel Newman Heating & Plumbing Co.

Decision Date28 February 1969
Docket NumberNo. 41308,41308
Citation282 Minn. 493,166 N.W.2d 323
PartiesPAUL W. ABBOTT, INC., Respondent, v. AXEL NEWMAN HEATING AND PLUMBING COMPANY, Inc., Appellant, City of St. Paul, Respondent.
CourtMinnesota Supreme Court

Syllabus by the Court

1. Where the words of a contract are ambiguous, precontract negotiations may be considered to determine the meaning and intent of the parties.

2. A contractor whose obligations under a contract are fixed by precontract negotiations which clarify a specification which would otherwise be ambiguous may be obligated to a greater quantum of performance by the specification than a third person who contracts with reference to the specifications but without the benefit of the clarifying precontract negotiations.

Stringer, Donnelly & Sharood, St. Paul, for appellant, Bert A. Minwegen, St. Paul, of counsel.

Gearin, Price, Melzarek & Jensen, St. Paul, for respondent, Paul W. Abbott, Inc.

Joseph P. Summers, City Atty., Thomas J. Stearns, Asst. City Atty., St. Paul, for respondent, City of St. Paul.

Heard before KNUTSON, C.J., and MURPHY, ROGOSHESKE, SHERAN and PETERSON, JJ.

OPINION

SHERAN, Justice.

Appeal from an order of the municipal court of the city of St. Paul denying an alternative motion for amended findings or a new trial.

The city of St. Paul, preparing to construct two new fire stations, called for bids for the required plumbing. Axel Newman Heating and Plumbing Company, Inc., the successful bidder, subcontracted the job of insulating the plumbing as required by the city's specifications to Paul W. Abbott, Inc. While the work was in progress, a dispute arose as to whether the specifications issued by the city, on the basis of which Newman secured its contract and Abbott obtained its subcontract for the insulation, required that All the domestic water pinping be insulated or only so much of it as was placed above the finished ceilings of the buildings. The disputed specification, formulated by the city as a basis for the bids, reads:

'All domestic water piping and rainwater piping Installed above finished ceilings under this specification shall be insulated * * *.' (Italics supplied.)

The city contended that the limiting effect of the underlined phrase applies only to 'rainwater piping'; Newman, the contractor, and Abbott, the subcontractor, contended that the phrase 'installed above finished ceilings' applies to both rainwater piping and domestic water piping. It was then agreed by representatives of the three parties that notwithstanding the dispute Abbott could insulate the domestic water piping wherever located and that the question of whether this work was required by the specifications or should be paid for as 'an extra' would be resolved when the job was done. A representative of Newman requested Abbott to proceed on this basis and it did so. It is agreed that the reasonable value of the work done in insulating the domestic water piping which was not 'above finished ceilings' is $772.37.

After the buildings were completed, Abbott sued Newman and the city for recovery of this amount; Newman cross-claimed against the city for its profit and overhead expense on the work; and the city denied liability to either of them. The trial court found in favor of Abbott against Newman but determined, in effect, that the city was liable to neither Abbott or Newman for the disputed work. Newman, appealing, contends in this court that the decision is perverse.

1. Were it not for a discussion with respect to the disputed specification which took place between a representative of the city of St. Paul and a representative of Newman before it submitted its bid for...

To continue reading

Request your trial
6 cases
  • Matter of Sentry Data, Inc.
    • United States
    • United States Bankruptcy Courts. Seventh Circuit. U.S. Bankruptcy Court — Northern District of Illinois
    • May 11, 1988
    ...be used to explain its uncertain terms but not to contradict or nullify its express terms. Paul W. Abbott, Inc. v. Axel Newman Heat. & Plumb. Co., 282 Minn. 493, 495, 166 N.W.2d 323, 325 (1969). All contract negotiations are superseded by a written contract. Hoyt v. Brokaw, 359 N.W.2d 310, ......
  • Lamb Plumbing & Heating Co. v. Kraus-Anderson
    • United States
    • Minnesota Supreme Court
    • August 29, 1980
    ...must be resolved in favor of plaintiff in accordance with the principle we enunciated in Paul W. Abbott, Inc. v. Axel Newman Heating & Plumbing Co., Inc., 282 Minn. 493, 166 N.W.2d 323 (1969). In that case, the City of St. Paul awarded a general contract to Axel Newman to build two firehous......
  • ICC Leasing Corp. v. Midwestern Machinery Co.
    • United States
    • Minnesota Supreme Court
    • August 5, 1977
    ...negotiations may be considered in order to determine the meaning and intent of the parties. Paul W. Abbott, Inc. v. Axel Newman H. & P. Co. Inc., 282 Minn. 493, 166 N.W.2d 323 (1969); Wick v. Murphy, 237 Minn. 447, 54 N.W.2d 805 Evidence of the parties' conversations and conduct during thes......
  • Graber v. Engstrom, 10980
    • United States
    • North Dakota Supreme Court
    • March 19, 1986
    ...to explain its uncertain expressions but not to contradict or nullify its express terms. E.g., Paul W. Abbott, Inc. v. Axel Newman Heat. & Plumb. Co., 282 Minn. 493, 166 N.W.2d 323, 325 (1969); Eggers v. Eggers, 79 S.D. 233, 110 N.W.2d 339, 342 (1961). In addition, the parties' conduct subs......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT