Justice BRIAN MORRIS delivered the Opinion of the Court.

¶ 1 Claire Pesarik (Pesarik) appeals from an order of the Eleventh Judicial District Court, Flathead County, granting the motion to dismiss filed by Gabriel R. Perjessy, DDS, and denying Pesarik's motion for enlargement of time. We affirm.

¶ 2 Pesarik presents the following issues for review:

¶ 3 Whether the District Court correctly determined that it lacked authority to grant Pesarik's motion for enlargement of time to serve process upon Perjessy.

¶ 4 Whether the District Court properly concluded that Pesarik had failed to establish excusable neglect to warrant an extension of time to serve process upon Perjessy.

PROCEDURAL AND FACTUAL BACKGROUND

¶ 5 Pesarik filed a complaint against Perjessy on May 27, 2004, in which she alleged medical malpractice arising from several dental procedures. The District Court issued a summons the same day. Pesarik did not serve the summons or otherwise prosecute the case. Pesarik's counsel sent her a letter on March 31, 2006, informing her that he no longer would represent her in the matter. The letter advised Pesarik that the summons and complaint must be served upon Perjessy within three years of filing pursuant to M.R. Civ. P. 4 E. The letter urged her to obtain substitute counsel immediately. Pesarik alleges that she never received the letter.

¶ 6 Pesarik instead asserts that her original counsel notified her orally sometime during the spring or summer of 2006 that he no longer would represent her. Pesarik further claims that she did not know when this change would occur, and, therefore, did not act immediately upon the information. Pesarik obtained substitute counsel by October 2006. Pesarik's new counsel discovered that her original client file did not include the summons issued on May 27, 2004. Pesarik did not immediately request a second summons from the District Court.

¶ 7 Pesarik instead prepared a settlement proposal that she submitted to Perjessy in March 2007. Perjessy acknowledged receipt of the proposal on March 29, 2007. Pesarik did not request a second summons until May 22, 2007. The District Court issued the second summons on May 24, 2007. Pesarik attempted personal service upon Perjessy through the sheriff's office that same day, the Thursday before Memorial Day, but Perjessy had left town on vacation. Pesarik was not able to serve Perjessy until Wednesday, May 30, 2007. The three-year window authorized by Rule 4 E for service of the summons and complaint upon Perjessy expired on May 27, 2007.

¶ 8 Perjessy moved to dismiss on the grounds that Pesarik had failed to accomplish service upon Perjessy within three years of the date on which she originally had filed the complaint. Pesarik moved to enlarge the time for service upon Perjessy pursuant to M.R. Civ. P. 6(b). The District Court granted Perjessy's motion to dismiss and denied Pesarik's motion for enlargement of time. The court first determined that it lacked authority to grant Pesarik an enlarged time to serve the summons upon Perjessy. The court next determined that even if the Rules of Civil Procedure granted it such authority, Pesarik had failed to prove excusable neglect to warrant an enlargement of time. Pesarik appeals.

STANDARD OF REVIEW

¶ 9 We review de novo a district court's conclusions of law to determine whether they are correct. Tungsten Holdings, Inc. v. Kimberlin, 2000 MT 24, ¶ 8, 298 Mont. 176, ¶ 8, 994 P.2d 1114, ¶ 8. We review for an abuse of discretion a district court's decision to grant or deny an enlargement of time pursuant to M.R. Civ. P. 6(b). In re Marriage of Weber, 2004 MT 206, ¶¶ 21, 23, 322 Mont. 324, ¶¶ 21, 23, 95 P.3d 694, ¶¶ 21, 23.

DISCUSSION

¶ 10 Whether the District Court correctly determined that it lacked authority to grant Pesarik's motion for enlargement of time to serve process upon Perjessy.

¶ 11 The District Court based its conclusion that it lacked the authority to enlarge the three-year time limit set forth in M.R. Civ. P. 4 E upon this Court's interpretation of former M.R. Civ. P. 41(e). Rule 41(e) governed the time limit for service of process for actions filed before January 1, 2000.

¶ 12 The District Court cited Otto v. Montana Dept. of Fish, Wildlife & Parks, 2000 MT 333, ¶ 20, 303 Mont. 86, ¶ 20, 15 P.3d 402, ¶ 20, in which this Court determined that the courts lacked authority to enlarge the time period in which a plaintiff must serve a summons. The court noted that Rule 41(e) provided that "the summons `must' be issued within one year of the suit." (Emphasis added). The Court declined to create an excusable neglect exception based upon its conclusion that the plain language of Rule 41(e) rendered the time limit mandatory. Otto, ¶ 20; Janow v. Conoco Pipe Line Co., 2000 MT 242, ¶ 15, 301 Mont. 402, ¶ 15, 10 P.3d 79, ¶ 15.

¶ 13 The District Court analogized Otto's interpretation of former Rule 41(e) to its interpretation of Rule 4 E, the current Rule governing the time limit for service of process. Rule 4 E provides that "[a] plaintiff shall have 3 years after filing a complaint to have a summons issued and accomplish service." (Emphasis added). The District Court determined that Rule 4 E contained language at least as clear and as unambiguous as that of former Rule 41(e). The court concluded that, as in Otto, Rule 4 E's plain language constituted a mandate that did not allow an excusable neglect exception.

¶ 14 Pesarik argues that the District Court incorrectly analogized former Rule 41(e) to current Rule 4 E. Pesarik points to M.R. Civ. P. 6(b). Rule 6(b) provides a district court with discretion to enlarge for cause a time limit set forth under the Rules of Civil Procedure. Specifically, the district court may grant an enlargement of time after the expiration of the time period "where the failure to act was the result of excusable neglect." M.R. Civ. P. 6(b)(2). The rule explicitly prohibits district courts from enlarging the time, however, for taking any action under Rules 50(b) and (c)(2), 52(b), 59(b), (d), (e) and (g), and 60(b). M.R. Civ. P. 6(b)(2).

¶ 15 Perjessy argues that the District Court properly analogized Rule 41(e) to Rule 4 E in light of the rules' similar construction. Rule 41(e) provides that a plaintiff "must" serve the summons and complaint within the specified time period. Rule 4 E provides that a plaintiff "shall" serve the summons and complaint within the specified time period. Perjessy asserts that the reasoning of Otto dictates that Rule 4 E's time limit also must be mandatory and not subject to enlargement upon a showing of excusable neglect. Perjessy further contends, citing Haugen v. Blaine Bank of Montana, 279 Mont. 1, 6, 926 P.2d 1364, 1367 (1996), that the District Court's strict interpretation of Rule 4 E's time limit prevents prejudice to the defendant and bolsters the Rule's purpose of promoting "the diligent prosecution of claims once suit is filed."

¶ 16 Perjessy fails to reconcile, however, the apparent conflict between the District Court's interpretation of the plain language of Rule 4 E and the plain language of Rule 6(b). Rule 6(b)(2) specifically provides for an enlargement of time for any time-limited action under the Rules of Civil Procedure except those explicitly prohibited, including M.R. Civ. P. 50(b) and (c)(2), 52(b), 59(b), (d), (e) and (g), and 60(b). Nothing in Rule 6(b)(2) explicitly prohibits district courts from enlarging the time for taking any action under Rule 4 E. We interpret the expression of one thing in a statute to imply the exclusion of another under the canon expressio unius est exclusio alterius. E.g. Dukes v. City of Missoula, 2005 MT 196, ¶ 15, 328 Mont. 155, ¶ 15, 119 P.3d 61, ¶ 15 (internal citations omitted).

¶ 17 Moreover, this Court will harmonize two statutes relating to the same subject in order to give effect to both. Yellowstone Federal Credit Union v. Daniels, 2008 MT 111, ¶ 18, 342 Mont. 451, ¶ 18, 181 P.3d 595, ¶ 18. Rule 4 E provides for a limited time action. Rule 6(b)(2) authorizes an enlargement of time for any rule for excusable neglect except those specifically prohibited. The two statutes cannot be in harmony if we interpret Rule 4 E's use of "shall" to constitute mandatory language.

¶ 18 Federal courts interpreting identical Fed.R.Civ.P. 6(b)(2) have concluded, as we do, that the rule authorizes courts to enlarge time for service of process upon a showing of excusable neglect. E.g. Dominic v. Hess Oil V.I. Corp., 841 F.2d 513, 517 (3rd Cir.1988); In re Teligent Services, Inc., 324 B.R. 467, 472 (Bkrtcy.S.D.N.Y.2005). Perjessy argues, however, that we cannot analogize the federal rules to the Montana Rules of Civil Procedure in light of the fact that the federal service of process provision, Fed.R.Civ.P. 4(m), includes a "good cause" exception to the time limit for service of process. Rule M.R. Civ. P. 4 E includes no such exception. The federal rule's "good cause" exception has no relevance here, however, as we have not analyzed a district court's authority to enlarge the time period for service of process based upon a general good cause standard. We instead have analyzed the district court's authority based upon the explicit grant contained in M.R. Civ. P. 6(b) that provides for enlargement of time based upon "excusable neglect."

¶ 19 Our decisions interpreting Rule 41(e) have limited relevance here as they interpret a now abolished rule, and, also, because they fail to construe that rule in the context of Rule 6(b). See Otto; Janow. Rules 4 E and 6(b) only harmonize if we con...

To continue reading

Request your trial
7 cases
  • Cini v. Viscomi & Gersh, PLLP (In re Cini)
    • United States
    • United States Bankruptcy Courts. Ninth Circuit. U.S. Bankruptcy Court — District of Montana
    • May 3, 2013
    ...Thus, an enlargement of time was unnecessary to comply with this statute. Furthermore, applying the standards set forth in Pesarik v. Perjessy, 2008 MT 337, ¶ 22, 346 Mont. 236, 194 P.3d 665, the District Court concluded that the delay in the execution sale was not the result of forgetfulne......
  • Cini v. Viscomi (In re Cini)
    • United States
    • United States Bankruptcy Courts. Ninth Circuit. U.S. Bankruptcy Court — District of Montana
    • May 3, 2013
  • Gansat v. State, Dept. of Rev.
    • United States
    • Montana Supreme Court
    • January 13, 2009
    ...GANSAT appeals. STANDARD OF REVIEW ¶ 9 We review de novo an agency's conclusions of law to determine if they are correct. Pesarik v. Perjessy, 2008 MT 337, ¶ 9, 346 Mont. 236, ¶ 9, 194 P.3d 665, ¶ 9. The same standard of review applies to both the District Court's review of the administrati......
  • Frontczak v. Cont'l Res., Inc.
    • United States
    • U.S. District Court — District of Montana
    • September 30, 2013
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT