Pittsburg Bridge Co. v. St. Louis Transit Co.

Decision Date23 February 1909
Citation116 S.W. 467,135 Mo. App. 579
PartiesPITTSBURG BRIDGE CO. v. ST. LOUIS TRANSIT CO.
CourtMissouri Court of Appeals

Appeal from St. Louis Circuit Court; Warwick Hough, Judge.

Action by the Pittsburg Bridge Company against the St. Louis Transit Company.

From a judgment for plaintiff, defendant appealed to the Supreme Court, which certifies the cause to the Court of Appeals. Affirmed.

See, also, 205 Mo. 176, 103 S. W. 546.

Boyle, Priest & Lehmann and Crawley & Jamison, for appellant. Abbott & Edwards, for respondent.

NORTONI, J.

This is a suit by a contractor for the balance due on a building contract. The contract contained a provision to the effect that, if the work was not completed by the 15th day of August, the defendant owner should be entitled to $50 per day as liquidated damages for delays after the date mentioned. It appears that the plaintiff's claim is conceded. The defendant counter-claims for the amount of $4,300 alleged to have accrued to it as liquidated damages because of 86 days' delay after August 15th in completing the building. The cause was tried before the circuit court without a jury. Plaintiff recovered the full amount sued for. The court found, however, for the defendant on the counterclaim to the extent of 37 days' delay, and on account of such delay, diminished plaintiff's claim at the rate of $50 per day, in all $1,850. From this judgment the defendant appealed to the Supreme Court. That court determined it was without jurisdiction in the premises, and therefore certified the cause here. The reasons therefor will appear by reference to Pittsburg Bridge Co. v. St. Louis Transit Co., 205 Mo. 176, 103 S. W. 546. It appears from the written contract in evidence that the plaintiff agreed and undertook to furnish the steel and iron, and to erect a structure for an engine room, pumproom, and boiler house for defendant in the city of St. Louis. Plaintiff agreed to complete the work by the 15th day of August, while among other things the defendant agreed on its part to erect and complete the foundations for the buildings by the 15th day of July. It is also stipulated, in event the foundation walls were not completed by July 15th, the plaintiff should have an extension of time for the completion of the work on its part equal to the number of days the defendant was in arrears in completing the foundation walls; and, further, if defendant failed to complete the foundations by the 15th day of July, it would notify the plaintiff contractor when completed at least 10 days before it should be required to proceed with the work on its part.

As before stated, the contract contained a stipulation for liquidated damages in the sum of $50 per day for each and every day the plaintiff was in default after August 15th in completing the work. It was admitted on the trial that the plaintiff was 86 days in default when the work was finally completed. There is no controversy whatever about this matter. The entire controversy in the case arises with respect to whether or not there was just cause shown for 49 days of the delay. As before stated, the circuit court found that, although the plaintiff consumed 86 days beyond the time limit to complete the work specified in the contract, it was justified to the extent of 49 days' delay because of the default of the defendant in completing the foundation walls and the consequent 10 days' notice due plaintiff...

To continue reading

Request your trial
5 cases
  • Gillioz v. State Highway Com'n
    • United States
    • Missouri Supreme Court
    • July 11, 1941
    ... ... 15 Am. Jur., p ... 696; 17 C. J. 964-965, sec. 263; Missouri Bridge & Iron ... Co. v. Stewart, 134 Mo.App. 618; Pittsburg Bridge ... Co ... St. Louis Transit Co., 135 Mo.App. 579; Ward ... v. Haren, 139 Mo.App. 8; ... ...
  • Bates v. Dana
    • United States
    • Missouri Supreme Court
    • November 22, 1939
    ... ... 41; Liggett v ... Levy and Union Natl. Bank, 233 Mo. 590; Pittsburg ... Bridge Co. v. St. Louis Transit Co., 135 Mo.App. 579; ... Douglas v ... ...
  • Weinsberg v. St. Louis Cordage Company
    • United States
    • Missouri Court of Appeals
    • February 23, 1909
    ... ... presume that the employee was not negligent. Goff v. St ... Louis Transit Co., 98 S.W. 49. (2) This was a case in ... which there was a legal duty owing by the defendant ... ...
  • Weinsberg v. St. Louis Cordage Co.
    • United States
    • Missouri Court of Appeals
    • February 23, 1909
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT