PITTSBURGH BUILDERS SUPPLY v. WESTMORELAND CONST.

Decision Date04 January 1989
Docket NumberCiv. A. No. 88-955.
Citation702 F. Supp. 106
PartiesPITTSBURGH BUILDERS SUPPLY CO., Plaintiff, v. WESTMORELAND CONSTRUCTION COMPANY, Marco Interior Systems, Inc.; and United States Fidelity & Guaranty Company, Defendants.
CourtU.S. District Court — Eastern District of Pennsylvania

Wm. H. Difenderfer, Pittsburgh, Pa., for plaintiff.

Karen Sirianni, Pittsburgh, Pa., for defendants.

MEMORANDUM

SMITH, District Judge.

This matter was reassigned to this judge on November 14, 1988. Presently before the Court are defendants Westmoreland Construction Company and United States Fidelity and Guaranty Company's joint Motion for Summary Judgment, filed November 14, 1988, and plaintiff Pittsburgh Builders Supply Company's Counter Motion for Summary Judgment, filed November 28, 1988. Plaintiff seeks to hold either moving defendant, or both of them, liable for payment for supplies it delivered as a materialman on a contract for improvements to the Pennsylvania Air National Guard facilities at the Greater Pittsburgh International Airport. Moving defendants seek dismissal of the claim against them. Defendant Westmoreland, a general contractor and the principal on the payment bond, denies that it is contractually obligated to PBS. Defendant USF & G, a surety company, denies that it is liable on its payment bond to PBS because PBS failed to make a timely claim under the Miller Act.

In 1985, defendant Westmoreland received a United States government contract to upgrade the Pennsylvania Air National Guard facilities at the Greater Pittsburgh International Airport. On May 30, 1985, Westmoreland executed a payment bond pursuant to the Miller Act, 40 U.S.C. § 270a et seq., with Westmoreland as principal and defendant USF & G as surety. Westmoreland subcontracted with Marco Interior Systems, Inc., to provide some of the construction services on the airport project. Marco, in turn, entered into a contract with PBS to supply construction materials. PBS delivered materials to Marco until early summer, 1987, at which time it refused to supply any more materials due to Marco's large unpaid balance owed to PBS.

On July 5, 1987, Westmoreland terminated its subcontract with Marco, due apparently to its dissatisfaction with Marco's default in its obligations, and thereafter directly undertook work on the portion of the construction that Marco failed to complete. Westmoreland and PBS entered into a contract for the supply of construction materials, which materials were shipped during the period from July 16, 1987, through July 24, 1987, or July 26, 1987. Westmoreland paid PBS for these materials directly.

The parties dispute what occurred during the formation of this Westmoreland—PBS contract. PBS asserts that it received oral assurances from Westmoreland that the outstanding balance owed to it by Marco would be paid by Westmoreland, and that it relied on Westmoreland's assurance in agreeing to supply Westmoreland with materials after Marco's default. Westmoreland denies this.

The parties also dispute the steps PBS took prior to filing this lawsuit under the Miller Act. PBS claims that on September 1, 1987, it sent a letter by regular U.S. Mail to USF & G, with copies to Westmoreland and to Marco, notifying USF & G that it intended to make a claim on USF & G's payment bond in the amount of Marco's outstanding balance to PBS, of $29,795.35. PBS again sent a letter on October 13, 1987, this time by certified mail, and on October 20, 1987, against making claim on the payment bond. Westmoreland and USF & G deny that any letter was sent to Westmoreland by PBS on September 1, 1987. They assert that the first notice of any claim came to Westmoreland on October 16, 1987, by a copy of PBS's October 13, 1987, letter.

The Miller Act provides, in pertinent part:

Before any contract, exceeding $25,000 in amount, for the construction, alteration, or repair of any public building or public work of the United States is awarded to any person, such person shall furnish to the United States ...:
* * * * * *
(2) A payment bond with a surety or sureties ... for the protection of all persons supplying labor and materials in the prosecution of the work provided for in said contract for the use of each such person.

40 U.S.C. § 270a(a). Since a supplier cannot acquire an enforceable lien against public property of the United States, this section provides that a surety guarantee their payment. In order to proceed against the surety, the Act further provides:

Every person who has furnished labor or material in the prosecution of the work provided for in such contract, in respect of which a payment bond is furnished under sections 270a to 270d of this title and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which such claim is made, shall have the right to sue on such payment bond for the amount, or the balance thereof, unpaid at the time of institution of such suit and to prosecute said action to final execution and judgment for the sum or sums justly due him: Provided, however, That any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the
...

To continue reading

Request your trial
8 cases
  • v. N. Am. Specialty Ins. Co.
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • February 21, 2014
    ...with the statutory period is a jurisdictional prerequisite to the maintenance of any suit”); Pittsburgh Builders Supply Co. v. Westmoreland Const. Co., 702 F.Supp. 106, 109 (W.D.Pa.1989) (“The limitations period of the Miller Act has always been construed to be mandatory and jurisdictional.......
  • U.S. v. Fidelity and Deposit Co. of Maryland
    • United States
    • U.S. District Court — District of New Jersey
    • March 30, 1998
    ...(5th Cir.1987); ACC Roofing, Inc. v. Dix & Sons Constr. Co., 1991 WL 224066, *2 (E.D.Pa.1991); Pittsburgh Builders Supply Co. v. Westmoreland Constr. Co., 702 F.Supp. 106, 108 (W.D.Pa. 1989). Before proceeding to an analysis of the first three elements, we must first determine whether or no......
  • U.S. ex rel. Epc v. Travelers & Cas. & Sur. Co., 02-2313 PHX ROS.
    • United States
    • U.S. District Court — District of Arizona
    • March 21, 2006
    ...Travelers provides no authority that notice to a surety is insufficient under the Miller Act. See Pittsburgh Builders Supply Co. v. Westmoreland Const. Co., 702 F.Supp. 106, 109 (W.D.Pa.1989) (finding notice to surety, but not to general contractor, sufficient under Miller Act for action ag......
  • W.M. v. Scranton Sch. Dist.
    • United States
    • U.S. District Court — Middle District of Pennsylvania
    • September 22, 2022
    ... ... See ... Burbage v. Boiler Eng'g & Supply Co. , 249 A.2d ... 563, 567 (Pa. 1969) (“The right ... ...
  • Request a trial to view additional results
1 books & journal articles
  • Chapter 12 - § 12.3 • PAYMENT BONDS
    • United States
    • Colorado Bar Association Practitioner's Guide to Colorado Construction Law (CBA) Chapter 12 Construction Sureties
    • Invalid date
    ...1989) (concluding that a prime contractor must receive written notice).[80] Pittsburgh Builders Supply Co. v. Westmoreland Constr. Co., 702 F. Supp. 106 (W.D. Pa. 1989).[81] U.S. ex rel. State Elec. Supply Co. v. Hesselden Constr. Co., 404 F.2d 774, 777 (10th Cir. 1968); U.S. ex rel. Automa......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT