Powers v. Bellows Falls Hydro-Electric Corporation

Decision Date04 November 1947
Citation57 A.2d 114,115 Vt. 243
PartiesWILLIAM S. POWERS, ET AL v. BELLOWS FALLS HYDRO-ELECTRIC CORPORATION
CourtVermont Supreme Court

May Term, 1947.

Opinion on motion to reargue filed February 3, 1948.

Change of Cause of Action.

1. As long as the plaintiff adheres to the contract or injury originally declared upon, an alteration of the modes in which the defendant has broken the contract or caused the injury is not an introduction of a new cause of action; the true test is whether the proposed amendment is a different matter, another subject of controversy, or the same matter more fully and differently laid.

2. In circumstances where a separate suit might be brought each time damages were caused, a suit for damages suffered over a period of years is a different cause of action from that claiming damages suffered over the space of only a few days even though the latter is included in the former.

3. When a pleading is capable of different meanings, it clashes with no rule of construction to construe it in the sense in which the pleader must be understood to have construed it supposing it to be consistent with itself.

TORT based upon negligence. The plaintiff amended the original declaration and the defendant excepted. Cause passed to the Supreme Court before final judgment. Windham County Court September Term, 1946, Blackmer, J., presiding.

Reversed. Motions to reargue and for further relief denied.

Ryan, Smith & Carbine for the defendant.

Barber & Barber for the plaintiffs.

Present: MOULTON, C. J., SHERBURNE, BUTTLES, STURTEVANT and JEFFORDS, JJ.

OPINION
SHERBURNE

The defendant owns and operates a dam constructed in 1927 and 1928 across the Connecticut River between Bellows Falls, Vermont, and North Walpole, New Hampshire, and is engaged in the manufacture and sale of electric current. The plaintiffs own and possess a farm in this state, abutting on the river, at some distance down stream from the dam. They seek to recover for damages alleged to have been caused to their farm and personal property thereon by the operation of such dam, its flash-boards and gates, so as to cause fluctuations in the flow of water past their farm, and so that the stored water released with freshet flows increases the height to which the water attains in overflowing their farm every time a freshet occurs. Although this action was first brought, it is the third proceeding to reach this Court involving these and other plaintiffs similarly situated. See Trybulski v. Bellows Falls Hydro-Elec. Corp., 112 Vt. 1, 20 A.2d 117 and Powers v. Bellows Falls Hydro-Elec. Corp., 114 Vt. 536, 48 A.2d 924.

The original complaint in this action was amended in 1939, into two counts: the first count charged negligence and the second charged a public and private nuisance. Upon this complaint there was a trial by jury from January 16, 1940, to March 23, 1940. During the trial the plaintiffs, with the permission of the court, struck out the second count, and the case was submitted on the issue of negligence only. The trial resulted in a disagreement. Owing largely to the absence of counsel in military service in the late war, nothing further was done until the plaintiffs on October 22, 1946, filed a motion to amend their complaint by substituting two new counts for the counts as amended in 1939. The motion was granted subject to exception as to each count, and subject to that exception the defendant demurred to the new first count, and the demurrer was overruled subject to exception. The cause has been brought here before final judgment, and the only questions briefed are to the allowance of the new count 1, and to the overruling of the demurrer thereto.

The defendant contends that the new count attempts to state a new and entirely distinct cause of action from the complaint sought to be amended, because it seeks to recover on a different set of facts and on a different theory. Among other things it is pointed out that the new count is not based upon negligence but upon some other theory of tort, and that while originally recovery was sought only for the damages suffered in March, 1936, the new count seeks to recover all damages suffered since the construction of defendant's dam in 1927 and 1928.

As long as the plaintiff adheres to the contract or injury originally declared upon, an alteration of the modes in which the defendant has broken the contract or caused the injury is not an introduction of a new cause of action. The true test is whether the proposed amendment is a different matter, another subject of controversy, or the same matter more fully and differently laid. Daley v. Gates, 65 Vt. 591, 592, 27 A. 193; Parker v. Bowen, 98 Vt. 115, 118, 126 A. 522; McCutcheon v. Leonard, 114 Vt. 368, 370, 45 A.2d 200; Johnson v. Hardware Mutual Casualty Co., 109 Vt. 481, 489, 490, 1 A.2d 817.

While the new count may be characterized as somewhat in the nature of a charge of trespass as contrasted with negligence, the "matter" and the "subject of controversy" are the same; and the amendment in this respect cannot be distinguished in principle from the last above cited case, where a complaint in negligence was permitted to be amended into one of bad faith.

As claimed by the defendant recovery was originally sought only for the damages suffered in March, 1936, whereas the new count seeks to recover all damages suffered since the construction of the dam. This presents a more serious question. No question is made by the defendant that the plaintiffs could have originally claimed in one suit all the damages suffered since the construction of the dam. However this may be, they could have brought a separate suit each time any damage was caused. 1 Am Jur Actions, § 117; Wells v. New Haven & Northampton Co., 151 Mass. 46, 23 N.E. 724, 21 Am St Rep 423. It is obvious that a suit for damages suffered over a period of years is a different cause of action form that claiming damages suffered over the space of only a few days, even though the latter is included in the former. In view of the long time that had elapsed before the filing of the new count the following from 34 Am Jur Limitation of Actions, § 260, is very appropriate. "One cannot, under the pretext of amending his pleading, state a new or different cause of action from the one originally stated and thereby avoid the running of the statute of limitations." It was error to allow the new count 1 as an amendment, and the cause must be reversed. It is unnecessary to discuss the other objections to this amendment, or to decide whether the amendment was sufficient to state a cause of action, as raised in the exception to the overruling of the demurrer.

UPON MOTIONS FOR REARGUMENT AND FOR FURTHER RELIEF.

SHERBURNE J. The first ground of the motion for reargument is that the opinion has decided the case upon a ground not briefed or argued. The defendant devoted nearly two pages of its brief to the proposition stated in the opinion "that a suit for damages suffered over a period of years is a different cause of action from that claiming damages over the space of only a few days." Fault is also found because of the citation of 34 Am Jur relative to the statute of limitations. This work was not cited by the defendant, but we know of no rule, in cases where a point has been well made, that limits us to the authorities cited by the excepting party. As a matter of fact, the...