Precast Structures, Inc. v. City of Houston

Decision Date08 August 1996
Docket NumberNo. 14-95-00688-CV,14-95-00688-CV
Citation942 S.W.2d 632
PartiesPRECAST STRUCTURES, INC., Appellant, v. CITY OF HOUSTON, Appellee. (14th Dist.)
CourtTexas Court of Appeals

Charles J. Wilson, Houston, for appellant.

Russel G. Richardson, Andrea Chan, Houston, for appellee.

Before MURPHY, C.J., and AMIDEI and ANDERSON, JJ.

OPINION ON MOTION FOR REHEARING

AMIDEI, Justice.

The appellee's motion for rehearing is granted. We withdraw our prior opinion dated June 27, 1996, and substitute the following in its place.

Precast Structures, Inc., ("Precast") appeals from a condemnation judgment in favor of the City of Houston ("City"), appellee, awarding the City 1,514 square feet of land out of Precast's business property and awarding Precast $2,032.00 as payment for the land. In nineteen points of error, appellant contends (1) the trial court did not have jurisdiction of the suit filed by the City because the City made no bona fide offer to purchase the property prior to filing suit and, alternately, (2) if there was jurisdiction to try the suit, the trial court erred in refusing to give Precast a jury trial on the issue of damages to the remainder of appellant's property. We affirm in part and reverse and remand in part.

The City of Houston contacted Precast in February, 1991, to purchase 1,514 square feet of the southeast corner of its place of business in southeast Houston. The property was to be used by the City in connection with the construction of a new road named Clearwood. Precast manufactures prestressed concrete beams and pillars used in highway and bridge construction. The City had two appraisers go to the property and prepare estimates on the value of the property. Based on these appraisals, the City offered Precast $951.00 for the tract to be taken. Precast rejected the offer and told the City it would have to relocate its equipment within its property because of the taking of a five foot strip off its southern end near its stress beds. Precast advised the City that by moving the new right-of-way line closer to the stress bed, it would no longer be possible to move long beams from the stress bed to the storage area because the beams would hang out in the street and would cause a traffic hazard. Precast told the City it would cost over $800,000.00 to relocate the stress bed and the highway beam bed.

The City filed a condemnation suit against Precast for the land on November 15, 1991. Two days prior to filing this suit, the City retained another appraiser, William Kvinta, to make a "more complete evaluation" of the property. Kvinta testified that he was strictly a real estate appraiser and was hired by the City to appraise the land for the benefit of the special commissioners appointed by the court. Kvinta appraised the land at $1,411.00 and the value of the damage to the improvements on the land at $10,000.00 for a total of $11,411.00. The commissioners awarded Precast $12,000.00 for the land and damages to the remainder. Precast answered the petition of the City alleging (1) no jurisdiction because of the failure of the City to make a bona fide offer and, alternately, (2) if the court found that it had jurisdiction, Precast suffered damages to the remainder of its land and should be compensated.

The trial court bifurcated the trial to determine the jurisdiction issue first, then the damages. At the jurisdiction portion of the trial, the trial court found that the City complied with Section 21.012(b)(4) of the Texas Property Code, which mandates a finding that the City and Precast "are unable to agree on the damages" before filing a condemnation petition. The court found that the parties could not agree and the court had jurisdiction of the condemnation suit. The court entered an interlocutory judgment finding jurisdiction and then set the case for trial on the damage issue. At the bench trial on the damage issue, the trial court made a preliminary finding that, as a matter of law, Precast suffered "no material and substantial impairment to access." The trial court held there was no fact issue for a jury to decide and therefore, no jury would be called. The trial court refused to admit any evidence on Precast's claim of damage to its remainder. Precast then presented its evidence as a bill of exceptions for review on appeal.

The evidence in the bill of exceptions consists of testimony to the effect that the taking of the land will necessitate the making of numerous improvements on the remainder and will cost $751,000.00. Prior to the taking, Precast used the "old exit" to Easthaven which was located north of the southeast corner of Precast. Precast had used the "old exit" to carry 125-foot beams to Easthaven and then south on Easthaven to Almeda-Genoa. The City built a "new exit" at the southeast corner which allows the trucks to exit the plant directly on to Clearwood. Clearwood bisected Easthaven and eliminated Easthaven as a route for Precast. Clearwood now joins Precast's property at the southeast corner, replacing Easthaven as an access from Precast at that location. However, using this "new exit" to Clearwood creates a dangerous condition by having truck traffic too close to the "working end" of the stress beds where people are working and hydraulic jacks are located pulling up to 1,000,000 pounds of stress. Relocation of the "working end" of the stress bed is necessary and will cost $351,000.00. To use this new exit, traffic will now have to be routed through the plant, which will require more radius for turning special trucks. The piling bed in the plant will have to be relocated at a cost of $400,000.00 to provide the necessary turning radius. If one of the other exits were used by the special trucks hauling the 125-foot beams, the trucks would have to now negotiate a sharp curve off Easthaven at its intersection with Clearwood, north of the "new exit." The trucks cannot get on Clearwood via Easthaven without going over curbs and off the pavement which could cause the beams to twist, crack and possibly explode. Therefore, Precast contends that it can only use the "new exit" to get the trucks carrying 125-foot beams on to Clearwood. The use of the "new exit" will cost Precast $751,000.00 to relocate stress beds, piling beds, and utilities. The three old exits located north of the new exit (adjoining the remaining part of Easthaven at the eastern boundary of Precast) can still be used by trucks carrying up to 75-foot beams. Trucks using these three old exits will be required to exit Precast on to the remaining part of Easthaven, which now intersects Clearwood, then to turn right on Clearwood and proceed south to Almeda-Genoa.

The evidence further demonstrates that the large trucks carrying the 125-foot beams would now have similar difficulties in turning right on Almeda-Genoa from the new Clearwood street. There was evidence that there were no problems before the taking when the trucks could exit the plant and turn right onto Easthaven, then south on Easthaven to Almeda-Genoa, and then turn right from Easthaven on Almeda-Genoa.

In points of error one through twelve, appellant argues that the City did not make a bona fide offer to purchase Precast's property before filing this suit and that the trial court did not have jurisdiction to try this case. Precast claims that the City was informed that the taking would necessitate the relocation of its beam beds and that the cost to relocate would exceed $800,000.00. Precast further contends that the City hired appraiser, Kvinta, "to make a determination as to what would be fair compensation" to Precast because the property needed "more complete evaluation." Precast claims that by hiring Kvinta to further appraise the property more completely, the City cannot claim that it made the $951.00 offer in good faith. Kvinta did not finish his appraisal until three months after suit had been filed by the City.

The City argues that it made a bona fide offer to Precast when it offered $951.00 for the tract before it filed suit. The City argues that their real estate supervisor, Ms. Christin Steele, testified that she met with Precast about three times and submitted a written offer to it for the $951.00, but Precast rejected the offer. Ms. Steele testified also that the negotiations with Precast had reached an impasse because the City could not offer the minimum amount Precast had requested for the taking. The City hired Kvinta to make another appraisal after it determined that it would have to pursue the suit. The City approved the condemnation suit by its motion to be effective November 12, 1991. On November 13, 1991, the City retained Mr. Kvinta to appraise the property for the benefit of the meeting of the special commissioners. On November 15, 1991, suit was filed. Mr. Kvinta's written appraisal is dated February 24, 1992. Mr. Kvinta testified he was not qualified to appraise the costs of relocating any equipment on the property and that he had advised the City to use an engineer to determine any costs that might be incurred by Precast to relocate their beam beds. Mr. Kvinta's written appraisal does not show how he arrived at the $10,000.00 damage to improvement figure. The appraisal showed that he valued the improvements on the remainder at $183,410.00 before the taking and $173,410.00 after the taking with no explanation as to how he arrived at the $10,000.00 diminution in value of the improvements. The only explanation given for the diminution in value was stated in his appraisal:

No detailed appraisal was made of the improvements. The estimated value of the improvements is based on the Harris County Appraisal District records. The estimated value of the subject improvements based on Harris County Appraisal District records is $183,610.00.

Kvinta did not testify as to how he arrived at the $10,000.00 figure for diminution in value of the improvements. The appraisal shows no diminution in value to the remaining land by the taking. Kvinta...

To continue reading

Request your trial
12 cases
  • Hubenak v. San Jacinto Gas Transmission Co.
    • United States
    • Texas Supreme Court
    • July 2, 2004
    ...Marburger v. Seminole Pipeline Co., 957 S.W.2d 82, 89 (Tex.App.-Houston [14th Dist.] 1997, pet. denied); Precast Structures, Inc. v. City of Houston, 942 S.W.2d 632, 636 (Tex.App.-Houston [14th Dist.] 1996, no writ); State v. Schmidt, 894 S.W.2d 543, 545 n. 1 (Tex.App.-Austin 1995, no writ)......
  • In the interest of W.D.H.
    • United States
    • Texas Court of Appeals
    • February 15, 2001
    ...233 Mich.App. 438, 443, 592 N.W.2d 751, 754 (1999). In Texas, questions of law are subject to de novo review. Precast Structures, Inc. v. City of Houston, 942 S.W.2d 632, 636 (Tex. App.--Houston [14th Dist.] 1996, no writ) (citing State v. Heal, 917 S.W.2d 6, 9 (Tex. 1996)).4 Congress enact......
  • Jean v. Tyson-Jean
    • United States
    • Texas Court of Appeals
    • May 15, 2003
    ...court's conclusions of law are reviewed de novo as legal questions. State v. Heal, 917 S.W.2d 6, 9 (Tex.1996); Precast Structures, Inc. v. City of Houston, 942 S.W.2d 632, 636 (Tex.App.-Houston [14th Dist.] 1996, no writ). Under de novo review, the reviewing court exercises its own judgment......
  • Butler v. State
    • United States
    • Texas Court of Appeals
    • July 16, 1998
    ...130 L.Ed.2d 21 (1994) (partial, permanent denial of access to public roadway from the remainder is compensable); Precast Structures, Inc. v. City of Houston, 942 S.W.2d 632, 637 (Tex.App.--Houston [14th Dist.] 1996, no writ) (damages directly attributable to impairment of access are compens......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT