Premier Finishes, Inc. v. Maggirias

Decision Date15 November 2013
Docket NumberNo. 2D13–1340.,2D13–1340.
Citation130 So.3d 238
PartiesPREMIER FINISHES, INC., and Peter Torres, Petitioners, v. Chris MAGGIRIAS, as Trustee of the Soulos Family Trust dated March 22, 2011, Respondent.
CourtFlorida District Court of Appeals

OPINION TEXT STARTS HERE

Anthony M. Lawhon of Anthony M. Lawhon, P.A., Naples, for Petitioners.

Robert A. DeMarco of Treiser & Collins, P.L., Naples, for Respondent.

BLACK, Judge.

Premier Finishes, Inc., and Peter Torres seek certiorari review of a circuit court order that discharged their claim of lien and lis pendens. The basis for the discharge was a name discrepancy. The order also dismissed their lien foreclosure claim without prejudice. The circuit court departed from the essential requirements of the law by discharging the claim of lien without determining if any adverse effect resulted from the discrepancy between the named lienor on the claim of lien and the named contractor on the contract. We therefore grant the petition for writ of certiorari, quashing the order to the extent that it discharged the claim of lien and lis pendens.

I. Background

In April 2011, Premier Finishes, under the fictitious name PFI Construction, and Peter Torres, owner and president, entered into a contract with the Soulos Family Trust (Owner) to build a house. In August 2012, Premier Finishes and Peter Torres (collectively Petitioners) filed a five-count complaint against Chris Maggirias, trustee of the Soulos Family Trust. The complaint alleged that Premier Finishes had substantially completed its performance pursuant to the contract when Mr. Maggirias “wrongfully terminated” Premier Finishes and failed to pay the outstanding balance due. The Petitioners also recorded a notice of lis pendens. As a result of the actions and inactions of Mr. Maggirias as alleged, Premier Finishes recorded a claim of lien on the property in April 2012, which was attached to the complaint. In count I of the complaint, the only count directly pertinent to our review, the Petitioners sought to foreclose the lien.

In response, Mr. Maggirias filed a motion to dismiss the complaint and discharge the claim of lien and lis pendens. Mr. Maggirias asserted that count I should be dismissed because the complaint and the recorded instruments were filed by Premier Finishes whereas the contract was entered into by PFI Construction. Thus, Mr. Maggirias contends that Premier Finishes is not a party to the contract, is not the “contractor,” and, consequently, is not the proper “lienor” under Florida's Construction Lien Law.1See§ 713.01(8), (18), Fla. Stat. (2010).

A hearing on the motion to dismiss was held on February 18, 2013. It was undisputed that PFI Construction is a fictitious nonentity. Mr. Maggirias reiterated the arguments asserted in the motion to dismiss. He summarized by arguing that since there is no contractor, there can be no contract and that without a valid, enforceable contract, the lien is not enforceable. In response, the Petitioners contended that PFI Construction was not and is not an existing entity but rather that PFI Construction is simply a name used by Premier Finishes, basically an acronym. Further, the Petitioners asserted that though Premier Finishes entered into the contract under the name PFI Construction, Premier Finishes actually completed all of the work pursuant to the contract. Finally, the Petitioners argued that Mr. Maggirias failed to show any prejudice as a result of the potential errors, omissions, or deficiencies in the claim of lien to prevent its enforcement.

The circuit court granted Mr. Maggirias' motion as to count I without prejudice and with leave to amend because [t]here [wa]s no alleged—no proven contract” to which Premier Finishes is a party. Mr. Maggirias requested that the lien and lis pendens be discharged, and over the Petitioners' objections, the court acquiesced, finding “that under the strict reading of [chapter] 713,” Premier Finishes did not “have a basis for the lis pendens or the claim of lien.”

Before the circuit court issued its written order, the Petitioners filed what we have interpreted as a motion for rehearing. The Petitioners asserted in the motion that Premier Finishes is a party to the contract and thus the appropriate party to file the lien, as it simply does business under the name PFI Construction. The Petitioners emphasized that such would be further elucidated by way of the amended pleadings and at rehearing, conceding this fact was not made particularly clear in the initial complaint. However, there is no indication that this motion was considered by the circuit court. In its written order rendered on February 26, 2013, granting Mr. Maggirias' motion as to count I, the circuit court clarified that it was discharging the lien and lis pendens “since [Mr. Maggirias'] Motion to Dismiss Count I has been granted.” The circuit court denied the remaining claims, notably, count II for breach of contract.

In accordance with the circuit court's order, the Petitioners filed an amended complaint alleging that Premier Finishes occasionally does business as PFI Construction,a fictitious name, making the two “entities” one and the same. The Petitioners stressed that Premier Finishes is the actual party to the contract. The Petitioners reasserted the lien foreclosure claim and also added a new count for imposition of an equitable lien. Mr. Maggirias again moved to dismiss the lien foreclosure claim, as well as the equitable lien claim, asserting that there is no legal basis to foreclose a claim of lien that has been discharged.

II. Discussion

The circuit court dismissed the lien foreclosure count and in turn discharged the lien and lis pendens based upon the determination that a contract between Premier Finishes and the Owner was not sufficiently “alleged” or “proven.” Thus, as an introductory matter we must consider whether Premier Finishes is the contractor, defined by section 713.01(8) as the one who contracts with the owner for the purpose of improving real property, such that it is the proper lienor and may be entitled to enforce the claim of lien. See§ 713.01(18)(a) (defining “lienor” as a contractor); see also § 713.05 (explaining that a contractor, as defined in section 713.01(8), who conforms with certain requirements shall have a lien based upon the contract).

It is true that a construction lien can only arise when a valid contract exists between the parties. See Viking Cmtys. Corp. v. Peeler Constr. Co., 367 So.2d 737, 739 (Fla. 4th DCA 1979) ([A] contract is essential to any [contractor]'s lien.”). Thus it seems contradictory for the circuit court to discharge the claim of lien filed by Premier Finishes based upon a contract entered into by PFI Construction, which the circuit court found to be unproven, but, at the same time, permit Premier Finishes to pursue its breach of contract claim based upon the very same contract. Nonetheless, if the contract is enforceable, the lien is legally enforceable provided the additional statutory requirements for a construction lien are met. See Michnal v. Palm Coast Dev., Inc., 842 So.2d 927, 932 (Fla. 4th DCA 2003).

A contract entered into under a fictitious name is valid and enforceable. See§ 865.09(9)(b), Fla. Stat. (2010); Worm World, Inc. v. Ironwood Prods., Inc., 917 So.2d 274, 275 (Fla. 1st DCA 2005). As a fictitious name is merely “a fiction involving the name of the real party in interest,” Riverwalk Apartments, L.P. v. RTM Gen. Contractors, Inc., 779 So.2d 537, 539 (Fla. 2d DCA 2000), the real entity that uses the fictitious name when entering into the contract is the actual party to the contract, see Worm World, 917 So.2d at 275. Thus, if Premier Finishes was the real entity using the fictitious name when entering into the contract, it is the actual party to the contract or the contractor pursuant to section 713.01(8) and is entitled to proceed with a claim of lien against the Owner.2Cf. Trintec Constr., Inc. v. Countryside Vill. Condo. Ass'n, Inc., 992 So.2d 277, 282 (Fla. 3d DCA 2008) (holding that the circuit court's order discharging the lien departed from the essential requirements of the law because the contractor was entitled to proceed with its claim of lien against the condominium association as representative of the unit owners).

As the Petitioners conceded, the relationship between Premier Finishes and PFI Construction was not made clear by way of the initial pleadings. 3Section 713.08(4)(b) permits the amendment of a claim of lien “during the period allowed for recording such claim of lien, provided that such amendment shall not cause any person to suffer any detriment by having acted in good faith in reliance upon such claim of lien as originally recorded.” However, the time period for amendment has expired,4 and thus Premier Finishes could not record an amended claim of lien. See generally Trintec, 992 So.2d at 279, 282 (finding that since the contractor was entitled to a claim of lien but could not record an amended claim of lien outside of the prescribed statutory time window, reinstatement of the lien was necessary to prevent the loss of the contractor's statutory remedy); see also Stunkel v. Gazebo Landscaping Design, Inc., 660 So.2d 623, 625–26 (Fla.1995) (noting that strict compliance with Construction Lien Law's time requirements is necessary since [c]ontracting parties need certainty about when time...

To continue reading

Request your trial
9 cases
  • Rock Hemp Corp. v. Dunn
    • United States
    • U.S. District Court — Western District of Wisconsin
    • December 7, 2021
    ...that uses the fictitious name when entering into the contract is the actual party to the contract." Premier Finishes, Inc. v. Maggirias, 130 So. 3d 238, 241 (Fla. Dist. Ct. App. 2013).4 Some courts recognize an exception to the general rule if the fictitious name "is employed for deceitful ......
  • Rock Hemp Corp. v. Dunn
    • United States
    • U.S. District Court — Western District of Wisconsin
    • December 7, 2021
    ... ... Robert L. Meinders, D.C., Ltd. v. United Healthcare ... Servs., Inc ., 7 F.4th 555, 560 (7th Cir. 2021). The ... conclusion that Rock ... contract is the actual party to the contract.” ... Premier Finishes, Inc. v. Maggirias, 130 So.3d 238, ... 241 (Fla. Dist. Ct ... ...
  • Rock Hemp Corp. v. Dunn
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • October 11, 2022
    ...by Premier Finishes after it entered into a contract with a homeowner under a fictitious business name, PFI Construction. 130 So. 3d 238, 243 (Fla. Dist. Ct. App. 2013). The court found Premier Finishes was "entitled to proceed with the claim of lien" even though the contract named PFI Cons......
  • Fettig's Constr., Inc. v. Paradise Props. & Interiors LLC
    • United States
    • Florida District Court of Appeals
    • November 4, 2020
    ...that certiorari is appropriate to review an order granting a motion to vacate a lien); see also Premier Finishes, Inc. v. Maggirias , 130 So. 3d 238, 239 (Fla. 2d DCA 2013) (finding departure where trial court discharged the claim of lien without determining if any adverse effect resulted f......
  • Request a trial to view additional results
1 books & journal articles
  • Organizing and operating a small business
    • United States
    • James Publishing Practical Law Books Florida Small-Firm Practice Tools - Volume 1-2 Volume 1
    • April 1, 2023
    ...§865.09(12)(a).] A party that has registered a fictitious name can be sued and sue in that name. [ Premier Finishes, Inc. v. Maggirias , 130 So. 3d 238, 241 (Fla. 2d DCA 2013) (action on claim of lien).] ORGANIZING AND OPERATING A SMALL BUSINESS 9-7 Organizing and Operating a Small Business......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT