Raymond v. International Business Machines Corp.

Decision Date28 May 1998
Docket NumberNo. 97-9222,97-9222
Citation148 F.3d 63
PartiesDavid RAYMOND, Plaintiff-Appellee, v. INTERNATIONAL BUSINESS MACHINES CORP., Defendant-Appellant.
CourtU.S. Court of Appeals — Second Circuit

James W. Runcie, Ouimette & Runcie, Vergennes, VT, for Plaintiff-Appellee.

Anthony Herman, Covington & Burling, Washington, DC (Jeffrey Huvelle, Bruce P. Smith, Covington & Burling, Theresa K. Mohan, International Business Machines Corp., White Plains, NY, on the brief), for Defendant-Appellant.

Before: MESKILL and CABRANES, Circuit Judges. *

PER CURIAM:

Defendant IBM appeals a jury verdict awarding $869,156 in damages to plaintiff David Raymond, a former IBM technician who brought this action alleging claims under Vermont law for breach of contract, promissory estoppel, and retaliation arising out of his dismissal by IBM. Raymond alleged, among other things, that IBM entered into an implied contract under which he could only be fired for "good cause," and that by firing him without good cause, IBM breached this contract. The case was tried in diversity jurisdiction in the United States District Court for the District of Vermont (J. Garvan Murtha, Chief Judge ), and a verdict was returned on July 14, 1997. The jury found for plaintiff on the breach of contract claim but found for IBM on the retaliation and promissory estoppel claims. On appeal, IBM contends that the district court erred by granting plaintiff's motion for leave to serve a jury demand out of time, by denying IBM's motion for judgment as a matter of law based on insufficiency of the evidence supporting the verdict, and by misinstructing the jury as to the legal standard for finding an implied contract of employment under Vermont law. For the reasons stated below, we affirm the judgment of the district court.

I.

Plaintiff filed this action on May 24, 1995, and accompanied his complaint with a demand for a jury trial, but he concedes that he failed to serve the jury demand upon IBM within ten days, as required by Federal Rule of Civil Procedure 38(b). 1 He characterizes this mistake as a "clerical error," and maintains that he believed at the time that IBM had been served with the jury demand. Both parties proceeded with extensive discovery, filed cross-motions for summary judgment, and otherwise prepared for trial. IBM claims that it learned for the first time in May 1997 that the case had been placed on the district court's jury trial calendar for the following month. Never having been served with a jury demand by plaintiff, IBM moved to have the case tried as a bench trial on the ground that plaintiff had waived a jury trial by failing to comply with the terms of Rule 38(b). Plaintiff responded by moving for an enlargement of the time in which to serve a jury demand pursuant to Federal Rule of Civil Procedure 6(b)(2) and/or for the court to exercise its discretion to order a jury trial pursuant to Federal Rule of Civil Procedure 39(b).

Rule 39(b), which directly concerns the failure to timely serve a jury demand, provides that "notwithstanding the failure of a party to demand a jury in an action in which such a demand might have been made of right, the court in its discretion upon motion may order a trial by a jury." Rule 6(b)(2) addresses generally the failure to conform to time limits specified in the Federal Rules of Civil Procedure. It provides that "[w]hen by these rules ... an act is required or allowed to be done at or within a specified time, the court for cause shown may at any time in its discretion ... upon motion made after the expiration of the specified period permit the act to be done where the failure to act was the result of excusable neglect."

The district court denied IBM's motion for a bench trial and by memorandum endorsement granted plaintiff's Rule 6(b)(2) and Rule 39(b) motions, after which plaintiff served a jury demand upon IBM and the case was tried to a jury. On appeal, IBM contends that, in the absence of a showing by plaintiff that his failure to serve a timely jury demand was caused by something beyond mere inadvertence, it was reversible error for the district court to grant plaintiff's Rule 39(b) and Rule 6(b)(2) motions.

IBM relies principally upon our decision in Noonan v. Cunard Steamship Co., 375 F.2d 69 (1967). In Noonan, the plaintiff had failed to timely serve a jury demand and moved for the court to order a jury trial under Rule 39(b). The district court denied the motion but granted a subsequent motion to dismiss the case without prejudice pursuant to Rule 41(a)(2), 2 permitting the plaintiff to refile the action and to timely serve a jury demand in a new action. Id. at 70. We reversed.

In reversing the dismissal of the action, we observed that it would have been error for the court to have granted the plaintiff's Rule 39(b) motion for a jury trial because "mere inadvertence in failing to make a timely jury demand does not warrant a favorable exercise of discretion under Rule 39(b)." Id. 3 Only a "showing beyond mere inadvertence" would justify Rule 39(b) relief. Id. (emphasis in original). We noted that although it would have been error for the district court to have granted the Rule 39(b) motion, "[t]he interesting question is whether the matter should stand otherwise because relief from the inadvertent failure to make a timely jury demand was here accomplished by permitting dismissal without prejudice." Id. at 70-71. That is, could the district court use its authority under Rule 41(a)(2) to cure the plaintiff's failure to timely serve a jury demand even though it could not do so under Rule 39(b)? We held that it could not because "decisions denying leave to discontinue without prejudice for the sole purpose of overcoming inadvertent failure to make a timely jury demand accord better than an opposite view with the policies of Rule 38(a) insisting on promptness and of Rule 41(a)(2) limiting the former freedom of dismissal of plaintiffs in actions of law." Id. at 71.

IBM argues that because in the instant case there was no showing that anything beyond mere inadvertence accounted for plaintiff's failure to timely serve the jury demand, Noonan precluded the district court from granting a jury trial, whether by way of Rule 39(b) or Rule 6(b)(2). It is true that insofar as plaintiff offers no explanation beyond mere inadvertence for his failure to timely serve the jury demand, the district court erred under Noonan in granting plaintiff's Rule 39(b) motion. However, we do not believe that the district court abused its discretion in granting leave to serve the jury demand out of time pursuant to Rule 6(b)(2).

There is some force to the argument by analogy that if Noonan precludes use of a motion to dismiss under Rule 41(a)(2) in order to circumvent the court's narrow discretion under Rule 39(b), then Rule 6(b)(2) must likewise be foreclosed from use for that very same purpose. However, as the Supreme Court observed in Pioneer Investment Services Co. v. Brunswick Associates Ltd. Partnership, 507 U.S. 380, 113 S.Ct. 1489, 123 L.Ed.2d 74 (1993), Rule 6(b) is "generally applicable to any time requirement found elsewhere in the rules unless expressly excepted." Id. at 389 n. 4, 113 S.Ct. 1489 (emphasis added). The rule specifically excepts its application to certain provisions of the Federal Rules of Civil Procedure, but these exceptions do not include Rule 38(b). Therefore, the plain text of Rule 6(b)(2) suggests that the rule is meant to apply to the time constraint imposed by Rule 38(b). Moreover, in Pioneer, the Supreme Court noted that

[i]t is not surprising ... that in applying Rule 6(b), the Courts of Appeals have generally recognized that 'excusable neglect' may extend to inadvertent delays. Although inadvertence, ignorance of the rules, or mistakes construing the rules do not usually constitute 'excusable' neglect, it is clear that 'excusable neglect' under Rule 6(b) is a somewhat 'elastic concept' and is not limited strictly to omissions caused by circumstances beyond the control of the movant. 4

Id. at 391-92, 113 S.Ct. 1489 (citations and footnotes omitted). In other words, mere inadvertence, without more, can in some circumstances be enough to constitute "excusable neglect" justifying relief under Rule 6(b)(2).

The Supreme Court held that the inquiry into whether a failure to abide by a specified time constraint constitutes "excusable neglect" is "at bottom an equitable one, taking account of all relevant circumstances surrounding the party's omission," including prejudice to the other party, the reason for the delay, its duration, and whether the movant acted in good faith. Id. at 395, 113 S.Ct. 1489. We hold that in light of the Supreme Court's decision in Pioneer, the requirement in Noonan of a showing "beyond mere inadvertence" should not be construed to preclude a district court from granting a Rule 6(b)(2) motion in appropriate circumstances.

Applying the equitable criteria described in Pioneer, we hold that in the circumstances presented, the district court did not abuse its discretion in granting plaintiff's Rule 6(b)(2) motion. IBM does not point to any evidence that would tend to show that plaintiff acted in bad faith. Although the delay in serving the jury demand was considerable, plaintiff points out that memoranda of law filed with the court by both parties, and the court's own summary judgment opinion, appear to assume that the case would ultimately be tried to a jury. Accordingly, there is little indication that IBM suffered prejudice as a result of the delay. In these circumstances, the district court acted well within its discretion under Rule 6(b)(2) in granting plaintiff leave to serve a jury demand out of time.

II.
A. Existence of an Implied Contract

We turn briefly to IBM's other claims on appeal. IBM argues that there was insufficient evidence to support the jury's verdict that IBM had entered into an implied contract under which plai...

To continue reading

Request your trial
39 cases
  • Schwartz v. Twin City Fire Ins. Co., 05 Civ. 7943(PKC).
    • United States
    • U.S. District Court — Southern District of New York
    • May 31, 2007
    ...L.Ed.2d 316 (1990) (citing Boyd v. United States, 271 U.S. 104, 107, 46 S.Ct. 442, 70 L.Ed. 857 (1926)); Raymond v. Int'l Business Machines Corp., 148 F.3d 63, 67-68 (2d Cir. 1998). A new trial is not warranted unless "the instructions were prejudicial and highly confusing." Raymond, 148 F.......
  • Gonsalves v. Nissan Motor in Hawaii
    • United States
    • Hawaii Supreme Court
    • November 27, 2002
    ...noted no "evidence to suggest that [the employer's] actions were not consistent with the disclaimer"); Raymond v. International Bus. Mach. Corp., 148 F.3d 63, 67 (2d Cir.1998) (employer's officials had informed the employee of the company's policy to fire only for cause, and, thus, had form......
  • Baldwin v.United States
    • United States
    • U.S. District Court — Northern Mariana Islands
    • September 26, 2011
    ...F.2d 69, 70 (2d Cir.1967); accord Westchester Day Sch. v. Village of Mamaroneck, 504 F.3d 338, 356–57 (2d Cir.2007); Raymond v. IBM Corp., 148 F.3d 63, 65 (2d Cir.1998). As a preliminary matter, I note that Chief Judge Munson's order was certainly correct that the Ninth Circuit Court of App......
  • Alexander v. Saul
    • United States
    • U.S. Court of Appeals — Second Circuit
    • July 8, 2021
    ...neglect’ justifying relief under Rule 6(b)(1)(B)," Petaway v. Osden , 827 F. App'x 150, 152 (2d Cir. 2020) (citing Raymond v. IBM Corp. , 148 F.3d 63, 66 (2d Cir. 1998) ), and have described "good cause" in the context of Rule 6(b)(1) as a "non-rigorous standard," Manigault v. ABC Inc. , 79......
  • Request a trial to view additional results