Rea v. Simmons & Simmons Const. Co., 12775

Decision Date02 February 1955
Docket NumberNo. 12775,12775
CourtTexas Court of Appeals
PartiesW. L. REA, d/b/a W. L. Rea Construction Company, Appellant, v. SIMMONS & SIMMONS CONSTRUCTION CO., Inc., Appellee.

North, Blackmon & White, Corpus Christi, for appellant.

Powell, Wirtz, Rauhut & McGinnis, Robert C. Duke, William A. Brown, Austin, for appellee.

W. O. MURRAY, Chief Justice.

This suit was instituted by Simmons & Simmons Construction Company, Inc., against W. L. Rea, d/b/a W. L. Rea Construction Company, seeking to recover damages for the breach of an unsigned written contract, whereby plaintiff agreed to do outside electrical work at Foster Air Force Base, Victoria, Texas. Plaintiff was the subcontractor, and defendant the general contractor.

The trial was to a jury, and judgment in the sum of $6,870.16 in favor of plaintiff was based upon the answers of the jury to the issues submitted. W. L. Rea, doing business as W. L. Rea Construction Company, has prosecuted this appeal.

The written contract sued upon was signed by appellee but not signed by appellant, and the question here presented is whether the contract, under all the circumstances, was binding upon appellant so as to hold him liable for damages for a breach thereof.

The jury found in answer to Special Issue No. 1, that both Jack Jones, general manager of appellee, and W. C. Bonvillain, general manager of appellant, intended that the written contract would become binding on both parties on July 22, 1952, whether or not actually signed by both parties.

On July 22, 1952, these two agents met for the purpose of negotiating the contract herein sued upon. After much discussion, Bonvillain had his secretary type up the contract here involved and gave several copies of it to Jones. At this point the statement of facts shows the following:

'Q. What did Mr. Bonvillain do with those written terms after they had been reduced to writing? A. He gave them to me.

'Q. What did he tell you when he gave them to you? A. He told me to take them, they were in several copies, take them with me, and obtain a bond, have the contract signed, the documents signed, on behalf of our organization, place with it the bonds so obtained, and return it to the W. L. Rea Construction Company for signature.'

This testimony, given by the general manager of appellee, when considered with other evidence, conclusively establishes that it was the intention of the parties that the contract should be in writing and signed by both parties thereto. The contract is set out in full in the statement of facts. It is a formal and complete contract and occupies six pages of the statement of facts.

The preamble to the contract reads as follows:

'This agreement made the twenty second day of July in the year Nineteen Hundred and fifty two, by and between Simmons & Simmons Construction Company, Inc., hereinafter called the Contractor, and W. L. Rea, an individual doing business as W. L. Rea Construction Company, hereinafter called the Owner, witnesseth, that the Contractor and the Owner for the considerations hereinafter named agree as follows:'

Following this preamble is Article 1, relating to 'Scope of the Work,' Article 2 relates to the 'time of Completion,' Article 3 relates to 'The Contract Sum,' Article 4 relates to 'Progress Payments,' Article 5 relates to 'Acceptance and final Payment,' Article 6 relates to 'The Contract Documents,' and reads as follows:

'The General Conditions of the Contract, the Specifications and the Drawings, together with this Agreement, form the Contract, and they are as fully a part of the Contract as if hereto attached or herein repeated. The following is an enumeration of the Specifications and Drawings:

'All Drawings applicable to the Electrical Distribution System as listed in Contract No. DA-41-243-Eng-1545, Specifications and Addenda one through five.

'In Witness Whereof the parties hereto have executed this Agreement, the day and year first above written.

'W. L. Rea Construction Company

By ________ W. L. Rea, Owner

'Acknowledgement:

'Subscribed to and sworn before me this ___ day _____, 1952.

'Simmons & Simmons Construction Co. Inc.

By Jack D. Jones Jack D. Jones, Sec.-Treas.

'Acknowledgement:

'Subscribed to and sworn before me this 26 day of July, 1952.

'Frances McWilliams

Notary Public

'(Seal: Notary Public County of Travis, Texas)'

This contract shows on its face that it was intended that it should be executed by both parties signing it in the spaces provided for such signatures.

It is undisputed that appellee was to furnish a performance bond in the sum of $27,000.

Jack Jones took these several copies of the written contract with him to Austin. Four days thereafter, on July 26, 1952, he signed the instruments and swore to them before a Notary Public. On the same date he procured a performance bond in the proper amount.

In reply to a question as to what he did with the copies of the contract and the bond, Jack Jones answered as follows:

'I placed it with the required number of copies. I believe there were two or three copies of the document Mr. Bonvillain had given me, signed that document on behalf of Simmons & Simmons Construction Company, placed them in an envelope and mailed them to W. L. Rea Construction Company.'

Three days later Jones received a letter from appellant stating, among other things, that it would be impossible for appellant to enter into the contract.

This evidence, either given by Jack Jones, appellee's general manager, or supplied by documents introduced by appellee, conclusively proves that the parties intended to enter into a written contract to be signed by each of them. Appellee signed the contract but it was never signed by appellant.

In Vol. 1, Williston on Contracts, § 28a, p. 67, this statement is made: 'It is the undoubted rule that where the contract contemplates the execution of it by signing either party has the right to insist upon the condition, and mere acts of performance upon the part of one who has not signed will not validate the contract.'

With reference to part performance by one party, the same section has this to say: '* * * Acts of performance by one party, unless they have been received as such by the other, cannot be evidence that the latter either had previously made an agreement on definite terms, or that he had subsequently assented to a contract.'

This seems to fit the case at bar perfectly. Here undoubtedly the parties intended to make a written contract to be signed by both parties, or else why did they draw up the contract with a number of duplicate copies and why did Jones take copies of the instrument with him to Austin and sign them before a notary public, and why was space provided for Rea to do the same thing, and why did Bonvillain tell Jones to sign the contract, secure a performance bond and return them to appellant for signing? The formal provisions of the contract indicate that it was to be fully executed by both parties signing.

Jones testified that he spent some money getting ready to perform his part of the contract, but he does not show that Rea ever knew anything about this or accepted any benefits as a result thereof. The record affirmatively shows that witnin three days after Jones mailed the contract and bond to appellant, appellant wrote him a letter telling him it would be impossible to enter into the contract.

There is evidence in the record tending to show that an oral contract might have been...

To continue reading

Request your trial
4 cases
  • Simmons & Simmons Const. Co. v. Rea
    • United States
    • Texas Supreme Court
    • December 14, 1955
    ...contract. The trial court rendered judgment for petitioner. The Court of Civil Appeals reversed and rendered judgment for respondent. 275 S.W.2d 747, 750. Respondent was a general contractor holding a contract with the United States government for construction of certain improvements at Fos......
  • Security Finance Co. v. Kone
    • United States
    • Texas Court of Appeals
    • October 30, 1957
    ...on other grounds 154 Tex. 586, 280 S.W.2d 564; Maxey Lumber Co. v. De Graw, Tex.Civ.App., 278 S.W.2d 607; Rea v. Simmons & Simmons Const. Co., Tex.Civ.App., 275 S.W.2d 747, affirmed Tex., 286 S.W.2d There is evidence in the record which would justify a conclusion that Felix Chapa was the so......
  • Wetzel v. Sullivan, King & Sabom, P.C.
    • United States
    • Texas Court of Appeals
    • January 7, 1988
    ...the instruments were not executed and were not intended to be effective without the signatures of all parties. See Rea v. Simmons & Simmons Constr. Co., 275 S.W.2d 747, 751 (Tex.Civ.App.--San Antonio), aff'd, 155 Tex. 353, 286 S.W.2d 415 (1955). Additionally, SKS contends that it did not ra......
  • Harrell v. Bakhaus, 13359
    • United States
    • Texas Court of Appeals
    • July 9, 1958
    ... ... Simmons & Simmons Construction Co. v. Rea, 155 Tex. 353, 286 S.W.2d ... ...

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT