Rittenhouse & Embree Co. v. Warren Const. Co.

Decision Date16 October 1914
Docket NumberNo. 9451.,9451.
Citation106 N.E. 466,264 Ill. 619
CourtIllinois Supreme Court
PartiesRITTENHOUSE & EMBREE CO. v. WARREN CONST. CO.

OPINION TEXT STARTS HERE

Appeal from Superior Court, Cook County; Charles M. Foell, Judge.

Action by the Rittenhouse & Embree Company against the Warren Construction Company, Darius Miller, and others, to establish a mechanic's lien. Judgment for plaintiffs, and defendant Miller and others appeal. Reversed and remanded, with directions.Sheriff, Dent, Dobyns & Freeman, of Chicago, (J. A. Connell, of Chicago, of counsel), for appellants.

Adams, Crews, Bobb & Wescott, of Chicago (James B. Wescott, of Chicago, of counsel), for appellee.

CRAIG, J.

This is an appeal from a decree of the superior court of Cook county establishing a mechanic's lien in favor of appellee, the Rittenhouse & Embree Company, on certain premises of appellants, the Chicago, Burlington & Quincy Railroad Company and Darius Miller, its president, located at the southwest corner of Jackson boulevard and Clinton street, in the city of Chicago, the property being owned by the Chicago, Burlington & Quincy Railroad Company, although the legal title to the real estate is of record in the name of Darius Miller, president of that company. Appellee was a subcontractor under the Warren Construction Company, to whom a contract was let by the Chicago, Burlington & Quincy Railroad Company, with the knowledge and consent of Miller, for the construction of certain work on the building to be constructed on the above premises. There is no controversy as to the facts, or that appellee took all of the necessary steps to perfect a mechanic's lien under the Mechanic's Lien Law of 1903 (Hurd's Stat. 1913, p. 1559), provided the original contract between the Warren Construction Company and the Chicago, Burlington & Quincy Railroad Company was not of such a character as to waive or bar the lien of a subcontractor, or the provisions of sections 5, 21, and 32 of the Mechanic's Lien Law of this state are not unconstitutional. By their objections before the master in chancery and exceptions before the chancellor to the master's report, as well as by their seventh assignment of error in this court, appellants have questioned the constitutionality of section 5, 21, and 32 of the said Mechanic's Lien Law of this state, and it is by virtue of the seventh assignment of errors that the appeal is brought direct to this court.

The facts in the case, in so far as they are material to be considered in passing upon the questions raised, are substantially as follows: On November 24, 1911, the Chicago, Burlington & Quincy Railroad Company entered into a written contract with the Warren Construction Company to do all of the rough carpentry work required in the construction and completion of the 15-story and basement fireproof office building to be erected on the southwest corner of Jackson boulevard and Clinton street, in the city of Chicago, for the sum of $39,300. By this contract the Warren Construction Company agreed to construct, finish, and deliver to the railroad company, ‘free from all claims, liens and charges, on or before the first day of June, 1912, all of the rough carpentry reqnired in the construction and completion’ of the building, and to furnish good, proper, and sufficient materials, workmanship, and labor of all kinds suitable and sufficient for the finishing and completing of the said work, etc., with the further provision that the amounts to be paid from time to time should in no case exceed 90 per cent. of the value of the work done and materials furnished, the remaining 10 per cent. to be retained as part security for the faithful performance of the contract, and not to be paid until the expiration of 30 days after the completion of the work and the payment of all claims for labor and materials furnished and the return of all drawings and specifications to the architects. The contract also provided that upon request by the architects the Warren Construction Company would furnish, from time to time, statements of all indebtedness for materials and labor furnished, used, or expended upon the said work, and that if at any time during the progress of the work it should allow indebtedness to accrue for labor or materials which might become liens on said building or the ground on which it stands, the railroad company might refuse to make the payments as therein provided for until satisfactory evidence was furnished that said indebtedness had been discharged, and that if such evidence was not furnished within 10 days after demand in writing, the railroad company might withhold the amount of such indebtedness and deduct the same from the amount agreed to be paid to the Warren Construction Company, or, at its option, might declare the entire agreement null and void and take possession of such work and complete the same, in which case the Warren Construction Company agreed to pay all loss or damages occasioned thereby. The Warren Construction Company began work upon the improvement contemplated by the written contract, and in May, 1912, entered into a verbal agreement with appellee to furnish certain lumber and building material to be used in the construction of the building, under which arrangement appellee furnished and delivered, and there was used in the improvement, lumber and building material of the value of $1,209.24. In July following the Warren Construction Company failed, and on August 8, 1912, was adjudicated a bankrupt by the United States District Court for the Northern District of Illinois, leaving its work under the written contract incomplete. Thereafter, by order of the United States District Court, the receiver in bankruptcy of the Warren Construction Company was directed to, and did, abandon the contract. Appellants, pursuant to certain provisions in the contract, then relet the contract to finish the incompleted portion of work contracted for by the Warren Construction Company to the B. J. Regnall Company, by which latter company the work was finally completed.

During the course of the work appellants paid on the contract the following amounts: To the Warren Construction Company $14,486.76, on the account of that company during the interim between the abandonment of the contract and the reletting of the contract for the unfinished work, $3,922.70, and to the B. J. Regnall Company for completing the work $24,400, making a total amount of $43,809.66, or $4,509.66 in excess of the original contract price. In making these various payments appellants did not obtain any statements from the contractor, as provided by section 5 of the Mechanic's Lien Law of 1903. The trial court held that under the provisions of sections 21 and 32 of that act appellants could not claim credit for the payments so made, but, in so far as appellee was concerned, such payments must be regarded as never having been made, and entered a decree allowing a lien in favor of appellee for the sum of $1,306.99. To reverse that decree this appeal has been prosecuted

Appellants contend: (1) That under the contract between the railroad company and the Warren Construction Company the latter company waived all right of lien, and consequently no right to a lien exists in favor of the appellee, a subcontractor; (2) that inasmuch as the improvement cost in excess of the original contract price, appellants cannot be charged with any greater liability than the amount of the original contract price, and that the provisions of sections 5, 21, and 32 of the Mechanic's Lien Law, which are designed to impose a greater liability on the owner, are unconstitutional and void. Appellee contends: (1) That all of the provisions of a written contract must be taken into consideration in construing the instrument, and that when the contract is so construed, the right to maintain a mechanic's lien is clearly recognized in that contract; (2) that sections 5, 21, and 32 of Mechanic's Lien Law do not constitute an unlawful infringement of the free right to...

To continue reading

Request your trial
13 cases
  • Potter v. Davidson
    • United States
    • Oregon Supreme Court
    • March 28, 1933
    ... ... Western Tube ... Co. 240 Ill. 132, 88 N.E. 468; Rittenhouse & Embree ... Co. v. Warren Const. Co., 264 Ill. 619, 106 N.E. 466; ... ...
  • Christopher B. Burke Eng'g, Ltd. v. Heritage Bank of Cent. Ill.
    • United States
    • Illinois Supreme Court
    • November 19, 2015
    ...in agency law of actual and apparent authority of an agent to act on behalf of a principal. See Rittenhouse & Embree Co. v. Warren Construction Co., 264 Ill. 619, 624, 106 N.E. 466 (1914) (“The foundation of the right to a mechanic's lien is a valid contract with the owner of the lot or tra......
  • Black v. Jones
    • United States
    • Illinois Supreme Court
    • October 16, 1914
  • Northwest Water Com'n v. Carlo V. Santucci, Inc.
    • United States
    • United States Appellate Court of Illinois
    • September 29, 1987
    ...arguments are similarly pallid. For example, the Commission puts particular stress upon the case of Rittenhouse & Embree Co. v. Warren Construction Co. (1914), 264 Ill. 619, 106 N.E. 466, wherein our supreme court stated that "the statute which gives a right to a mechanic's lien was not int......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT