Robert F. Felte, Inc. v. White

Decision Date16 March 1973
Citation302 A.2d 347,451 Pa. 137
PartiesROBERT F. FELTE, INC. v. Frank WHITE, et ux., et al. Appeal of GLOBAL FRANCHISE CORPORATION.
CourtPennsylvania Supreme Court

Donald A. Semisch, Willow Grove, for appellees, Frank White et ux.

Before JONES, C.J., and EAGEN, O'BRIEN, ROBERTS, POMEROY, NIX and MANDERINO, JJ.

OPINION OF THE COURT

ROBERTS, Justice.

This controversy arises out of a written contract of sale for a parcel of realty located in Abington, Pennsylvania, between Frank and Minerva White (sellers) and Global Franchise Corporation (buyer). Appellant, Global, is appealing from the decree of the Court of Common Pleas of Montgomery County, awarding $9,000, less counsel fees and costs, to appellees, Frank and Minerva White. The $9,000 represents the funds deposited with Robert F. Felte, Inc., an escrow agent, who originated this action by a complaint in equity * requesting interpleader to determine whether the buyer or seller is entitled to the escrow. On this appeal appellant-buyer contends that the chancellor erred in awarding this sum to the sellers. Upon careful review of the record we agree with appellant and accordingly reverse.

A brief recital of the facts, as found by the chancellor, leading to the interpleader action is necessary to understand the principal issue. On November 29, 1969, the Whites and Global entered into a written agreement of sale for the purchase of property owned by the Whites. The purchase price was $90,000 with a down payment of $9,000 to be paid into an escrow account. Robert F. Felte, Inc., the agent for the sellers, was designated by both parties to be the escrow agent.

The contract of sale contained several conditions relevant to the resolution of this dispute:

'(a) that settlement was to be made on February 15, 1970; that payment in accordance with the contract should be made on that date; and, that time was of the essence;

'(b) that if the buyer defaulted in performing the conditions of the contract or failed to make settlement in accordance with the terms thereof, the sellers had the option of retaining the sum paid into escrow, on account of the purchase price, or of retaining it as liquidated damages for the damages and expenses to which the sellers would be put; and, in the case of the latter, the contract should be null and void;

'(c) that if the mortgage commitment were not obtained by the date of settlement, such date would be extended after said commitment was obtained;

'(d) in the event the agreement were contingent upon securing a mortgage by or for the buyer (as was the case), said mortgage was to be obtained within 90 days from date of owners' approval: in the event said mortgage was not obtained within the specified time limit, then sellers, at their option, might cancel said agreement of sale, and all deposit monies paid on account of the purchase price would be refunded in full;

'(e) that the buyer make reasonable and diligent efforts to obtain the mortgage financing for the amount of $175,000 for the purchase of the property and the construction of the building thereon, from a regional financial institute customarily making such loans; and, that if buyer were unable to obtain such financing after such efforts, that it should submit written notification thereof to sellers, resulting in the agreement becoming null and void; and, buyer should immediately receive the return of its deposit, upon demand, and without interest.'

Prior to the settlement date of February 15, 1970, both parties signed an 'Endorsement to the Agreement of Sale' which provided:

'Settlement to be changed from February 15, 1970, to April 15, 1970, plus 30 days if necessary, to assure enough time for proper zoning if needed.'

In a letter to Felte dated April 27, 1970, the buyer, Global, indicated that settlement would occur on or about May 5, 1970. In anticipation of settlement and start of construction on the property, the Whites and their tenants vacated the premises in the first week of May, 1970.

On May 15, 1970, all parties met for settlement, but Global's agent, Mr. Hertz, indicated that while all the financing arrangements had been made they still needed about ten more days to complete the paper work. Hertz told the parties that 'It (the financing) was in the bag.' At this meeting the parties executed a second extention agreement. The relevant part of this agreement provides:

'The parties agree that settlement is extended to on or before May 25, 1970, 9:00 a.m. In the event settlement is not consummated at that time, the parties agree to a further extension of settlement to on or before June 5, 1970. If such further extention is required, Buyer shall pay retroactive to this date the sum of $15.00 per day, until the date of settlement. Such payment shall cease on the day Buyer is ready, willing and able to make settlement, whether or not settlement is consummated.'

Shortly thereafter Global did receive a verbal commitment from a mortgage lending institution in the amount of $200,000. The chancellor also found that during this period Global had been in touch with eight mortgage bankers and had made a good faith effort to secure financing.

On June 3, 1970, another meeting was held at which Global requested a third delay. The reason given for this delay was that Global had acquired another parcel of real estate and had obtained mortgage financing for a package deal which included the White's property, and that only the paper work needed to be completed on this matter. Subsequently, on that same date the parties signed the following agreement, the focus of this litigation:

'WHEREAS, Buyer desires to extend the date of settlement as originally set in their agreement of November 29, 1969, and extended on May 15, 1970;

'NOW, THEREFORE, intending to be legally bound hereby, it is agreed as follows:

'1. Settlement shall be made on or before July 10, 1970, and time is of the essence.

'2. Buyer shall pay to Sellers, within five days, the sum of $950.00 as compensation for said extension.'

On June 14, 1970, Central Mortgage Company of New Jersey confirmed receipt of Global's application for financing, but on July 8, 1970, Central Mortgage Company rejected Global's application because Central was unable to secure construction and permanent financing. The next day, July 9, 1970, Global requested that Felte return the $9,000 down payment.

Pursuant to these findings of fact the chancellor concluded that:

1) Global made a reasonable and diligent effort to obtain mortgage financing as required by the agreement;

2) The liquidated damages provision of the agreement was proper;

3) The extension agreement of June 3, 1970, to the original contract abrogated the condition of the agreement of sale that if Global were unable to procure the mortgage financing, the contract should become void, and Global should be entitled to the return of the $9,000 down payment, and therefore;

4) Global's failure to consummate settlement on July 10, 1970, was a breach of the agreement which entitled the Whites to retain the $9,000 escrow less counsel fees and costs.

Appellant contends that the financing contingency in the original agreement of November 29, 1969, entitles it to the return of the escrow deposit, and that it at no time agreed to alter or waive that condition. The chancellor construed the provision in the June 3 extention agreement that 'settlement shall be made on or before July 10, 1970, and time is of the essence,' as abrogating the mortgage financing condition of the original agreement. The court reasoned that because Global had, prior to the extension agreement, assured the Whites that Global had secured the mortgage financing it therefore waived that financing condition.

In reaching this conclusion the chancellor stated:

'The only thing that remained to be done before the Whites received the remainder of the purchase price under the contract was some paper work and actual settlement. Therefore, the intention of the parties in entering into the June 3, 1970, extension agreement must be interpreted in the light of these surrounding circumstances. The intention of the parties, when they signed the June 3 agreement which stated that 'settlement shall be made on or before July 10, 1970' and 'time is of the essence' is held to be as follows: 1) that the condition requiring the procurement of mortgage financing had been accomplished; 2) that inasmuch as the condition had been met, this extension agreement vitiated the conditional nature of the contract of November 29, 1969; 3) that the only thing that remained for the complete performance of this contract was some necessary paper work (month and seven days, i.e., from June 3 to ...

To continue reading

Request your trial
35 cases
  • Ggis Ins. Serv. Inc. v. Lincoln Gen. Ins. Co.
    • United States
    • U.S. District Court — Middle District of Pennsylvania
    • February 24, 2011
    ...the meaning of Article XIX “must be determined by its contents alone.” Murphy, 777 A.2d at 429 (quoting Robert F. Felte, Inc. v. White, 451 Pa. 137, 302 A.2d 347, 351 (1973)). The sentence of Article XIX in question can be broken down into two parts. There is first the general statement: “T......
  • In re Garman
    • United States
    • U.S. Bankruptcy Court — Eastern District of Pennsylvania
    • July 6, 2009
    ...parties." Murphy v. Duquesne Univ. of the Holy Ghost, 565 Pa. 571, 590-91, 777 A.2d 418 (2001), see also Robert F. Felte, Inc. v. White, 451 Pa. 137, 143, 302 A.2d 347 (1973). The intent of the parties is to be ascertained from the document itself when the terms are clear and unambiguous. S......
  • Reardon v. Allegheny College
    • United States
    • Pennsylvania Superior Court
    • June 1, 2007
    ...("When a writing is clear and unequivocal, its meaning must be determined by its contents alone."), quoting Robert F. Felte, Inc. v. White, 451 Pa. 137, 302 A.2d 347, 351 (1973) (additional citation omitted). Rather, she contends Allegheny breached its promised procedure by failing to notif......
  • Humans & Res., LLC v. Firstline Nat'l Ins. Co.
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • January 8, 2021
    ...v. Pennsylvania Industries for the Blind and Handicapped, 886 A.2d 706, 711 (Pa. Cmwlth. 2005) (citing Robert F. Felte, Inc. v. White, 451 Pa. 137, 144, 302 A.2d 347, 351 (1973) ). A court should not consider individual terms in isolation, but rather must consider the entire insurance provi......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT