RP Industries, Inc. v. S & M EQUIP. CO.
Decision Date | 20 August 2004 |
Citation | 896 So.2d 460 |
Parties | R.P. INDUSTRIES, INC. v. S & M EQUIPMENT COMPANY, INC. |
Court | Alabama Supreme Court |
Robert L. Gonce, Young, Norris & Collum-Butler, Florence, for appellant.
Jack G. Kowalski and L. Griffin Tyndall of Burr & Forman, LLP, Birmingham, for appellee.
R.P. Industries, Inc. ("RPI"), appeals from an order of the Lauderdale Circuit Court granting the motion of S & M Equipment Company, Inc. ("S & M"), seeking confirmation of an arbitration award; denying RPI's motion to vacate, modify, or correct the award; and entering a judgment in favor of S & M and against RPI for the "net" amount of the award. We affirm.
The arbitration proceeding arose out of RPI's termination on February 21, 2001, of a paving subcontract it had awarded S & M. On July 9, 2001, S & M sued RPI and several other defendants in the Lauderdale Circuit Court. S & M's complaint asserted claims of breach of contract, "account stated and/or open account," "work and labor done," enforcement of a mechanic's lien on the real estate improved, and a violation of Ala.Code 1975, § 8-29-1 et seq ("the Prompt Pay Act"). S & M expressly claimed interest and attorney fees as a part of its damages.
On February 28, 2002, RPI filed a motion asking the court "to compel the parties to arbitrate this dispute" and to stay all proceedings pending the arbitration "of the merits of the underlying disputes." It attached to its motion, among other things, a copy of the subcontract between RPI and S & M; that subcontract contained an arbitration provision. RPI predicated its right to enforce the arbitration agreement on the provisions of the Federal Arbitration Act, as codified at 9 U.S.C.A. § 1 et seq. ("the FAA").
On March 27, 2002, the trial court entered an order "transferring" the mechanic's lien to a bond that had been filed by RPI and its bond surety. On April 1, 2002, S & M amended its complaint to acknowledge the filing and implementation of the lien-transfer bond and to request that a judgment be rendered against RPI and its surety. In that amendment, S & M reasserted at length all of its prior claims, including the claim that RPI had violated the Prompt Pay Act.
The subcontract between RPI and S & M contained the following arbitration provision:
On April 5, 2002, S & M filed a "Consent to Arbitrate and Stay Litigation" and soon thereafter filed a "Demand for Arbitration" with the American Arbitration Association ("the AAA") under the AAA's Construction Industry Arbitration Rules ("the Rules"). (The parties agree that "the specifications do not address arbitration.") The Demand for Arbitration identified the nature of the dispute by referring to the attached amended complaint and stated the relief sought to be "in excess of $250,000," together with "interest, costs and attorney fees." A preliminary hearing was held at which the parties and representatives of the AAA were present, and on August 29 the AAA wrote the attorneys for S & M and RPI to confirm that the following, in pertinent part, were the terms the parties had agreed to at the hearing:
On February 3, 2003, S & M served on RPI and the three arbitrators the parties had selected its "Motion for Summary Judgment/Arbitration Brief." In that submission, S & M alleged, among other things, that "RPI unjustifiably terminated S & M after substantial completion" and in a section captioned "Damages" included the following statements:
Attached as exhibits to S & M's submission were full reproductions of the cited sections of the Prompt Pay Act (§§ 8-29-3 and 8-29-6) and a voluminous collection of the billings to S & M by its attorneys. The record does not reflect if the summary-judgment-motion aspect of that submission was ever ruled on. For all that appears in the record, RPI filed no opposition to the motion and filed no prehearing brief of its own; it did, however, file a counterclaim, seeking, among other relief, attorney fees on its own behalf.
The three-member arbitration panel conducted an evidentiary hearing February 10 through 13, 2003. On March 12, 2003, a unanimous panel issued an award, stating that it had "heard the allegations and proof of the parties in support of and in response to the claims and counterclaims." It found that RPI had "breached the subcontract agreement by wrongfully terminating the subcontract agreement and failing to pay S & M funds due under the subcontract agreement." The panel also found that "S & M performed defective workmanship on portions of its work," entitling RPI to a partial recovery under its counterclaim. The panel awarded S & M $182,740.35, the net difference between the amount due S & M under the subcontract and the off-setting damages awarded to RPI. Additionally, and central to this appeal, the panel made the following additional awards:
On March 25, 2003, S & M filed in the Lauderdale Circuit Court its motion to confirm the arbitration award, relying upon the FAA, 9 U.S.C. § 9, and asking the trial court to enter a judgment in the amount of the award, including the accrued interest.
On April 25, 2003, RPI filed its response to S & M's motion, which it styled, in the alternative, a motion to vacate, modify, or correct the award. RPI argued that the panel had "exceeded its authority" in awarding S & M interest and attorney fees in addition to the amount due under the subcontract. RPI cited the FAA, 9 U.S.C. §§ 9, 10, and 11, as authority for the relief it sought. FAA, 9 U.S.C. § 10(a)(4) permits the vacation of an arbitration award "[w]here the arbitrators exceeded their powers...." After conducting a hearing, the trial court confirmed the award on June 10, 2003, ordering the following, as pertinent to this appeal:
RPI appealed, reasserting all of the arguments it made in the trial court to the effect that the panel had exceeded its authority in awarding S & M interest and attorney fees under the authority of the Prompt Pay Act. The standard of review applicable to a ruling on a motion to confirm or vacate an arbitration award was discussed in Maxus, Inc. v. Sciacca, 598 So.2d 1376, 1380-81 (Ala.1992):
...
To continue reading
Request your trial-
Tucker v. Ernst & Young, LLP
...9 U.S.C. 10 ]. Catz American Co. v. Pearl Grange Fruit Exchange, Inc., 292 F.Supp. 549 (S.D.N.Y.1968).” ’“[R.P. Indus., Inc. v. S & M Equip. Co., ] 896 So.2d [460,] 464 [ (Ala.2004) ] (quoting Maxus, Inc. v. Sciacca, 598 So.2d 1376, 1380–81 (Ala.1992) ). The standard by which an appellate c......
-
Mun. Workers Comp. Fund, Inc. v. Morgan Keegan & Co.
...§ 10(a), based on Kunis's non-disclosure.”The Fund appeals.II. Standard of ReviewThis Court has stated:“In R.P. Industries, Inc. v. S & M Equipment Co., 896 So.2d 460 (2004), this Court reviewed the trial court's order granting a motion to confirm an arbitration award and denying the opposi......
-
Kitchens v. Turquoise Properties Gulf Inc.Turquoise Properties Gulf Inc. v. Blakely M. Kitchens
...[in 9 U.S.C. § 10]. Catz American Co. v. Pearl Grange Fruit Exchange, Inc., 292 F.Supp. 549 (S.D.N.Y.1968).’ ”R.P. Indus., Inc. v. S & M Equip. Co., 896 So.2d 460, 464 (Ala.2004). “The standard by which an appellate court reviews a trial court's order confirming [or vacating] an arbitration......
-
Hereford v. D.R. Horton, Inc.
...confirmed, and it entered an order in accordance with that finding. Hereford now appeals. Standard of Review In R.P. Industries, Inc. v. S & M Equipment Co., 896 So.2d 460 (2004), this Court reviewed the trial court's order granting a motion to confirm an arbitration award and denying the o......