Samara Development Corp. v. Marlow

Decision Date08 February 1990
Docket NumberNo. 72763,72763
Citation556 So.2d 1097
Parties15 Fla. L. Weekly S52 SAMARA DEVELOPMENT CORP., etc., Petitioner, v. Richard MARLOW, Respondent.
CourtFlorida Supreme Court

Kathy Kaplan and Brian J. Sherr of Sherr, Tiballi, Fayne & Schneider, Fort Lauderdale, for petitioner.

Glenn M. Mednick of Gutkin, Miller, Shapiro & Selesner, Boca Raton, for respondent.

EHRLICH, Chief Justice.

We have for review Marlow v. Samara Development Corp., 528 So.2d 420, 422 (Fla. 4th DCA 1988), in which the Fourth District Court of Appeal certified the following question to be of great public importance:

IS A CONTRACT FOR THE SALE OF A CONDOMINIUM IN FLORIDA EXEMPT FROM THE PROVISIONS OF THE INTERSTATE LAND SALES FULL DISCLOSURE ACT, 15 U.S.C. § 1710, WHERE IT PROVIDES FOR COMPLETION WITHIN TWO YEARS BUT RESTRICTS THE BUYER'S REMEDIES FOR BREACH OF THE CONTRACT BY THE SELLERS TO A RETURN OF THE DEPOSIT OR SPECIFIC PERFORMANCE, OR MUST THE CONTRACT ALSO AFFORD THE BUYER THE ALTERNATIVE REMEDY OF A SUIT FOR DAMAGES?

We have jurisdiction. Art. V, § 3(b)(4), Fla. Const. We approve the decision below, and hold that in order for the sale of a condominium in Florida to be exempt from the provisions of the Interstate Land Sales Full Disclosure Act, the contract must unconditionally obligate the developer to complete construction within two years and must not limit the purchaser's remedies of specific performance or damages.

The relevant facts show that on November 23, 1983, Richard Marlow entered into a condominium purchase agreement with Samara Development Corporation (Samara) for the purchase of one of Samara's condominium units in Boca Raton, Florida. Marlow paid Samara a $10,940 deposit, and Samara promised to complete the condominium by June 1, 1984, less than two years from the date of the agreement. As part of the agreement, Marlow was entitled to recover the deposit or to bring an action for specific performance upon a default by Samara. Subsequently, Marlow sued Samara for breach of contract, seeking damages and a rescission of the contract pursuant to the Interstate Land Sales Full Disclosure Act, 15 U.S.C. §§ 1701-20 (1982) (effective August 1, 1968) ("the Act"). Samara responded by arguing that the interpretation of 15 U.S.C. § 1702(a)(2) by the United States Department of Housing and Urban Development (HUD) exempted it from the Act. The trial court granted a summary judgment in favor of Samara. On appeal, the Fourth District Court, relying on its previous decision in Berzon v. Oriole Homes Corp., 497 So.2d 670 (Fla. 4th DCA 1986), reversed and remanded the cause to the trial court with instructions that it deny Samara's motion for summary judgment and grant Marlow's motion for summary judgment, but certified the question to this Court as one of great public importance.

The relevant federal statute is 15 U.S.C. § 1702, which states in pertinent part:

(a) Unless the method of disposition is adopted for the purpose of evasion of this chapter, the provisions of this chapter shall not apply to--

....

(2) the sale or lease of any improved land on which there is a residential, commercial, condominium, or industrial building, or the sale or lease of land under a contract obligating the seller or lessor to erect such a building thereon within a period of two years.

(Emphasis added.)

Samara relies heavily on guidelines published by HUD, the federal agency responsible for administering laws concerning land sales, 1 as evidence that HUD interprets the Act as exempting developers if the contract obligates them to complete the project within two years and does not limit the purchaser's right to specific performance. Samara then correctly notes that the administrative interpretations of a statute by the agency required to enforce that statute are entitled to great weight. See, e.g., Department of Environmental Regulation v. Goldring, 477 So.2d 532 (Fla.1985). However, we do not find that HUD clearly interprets the Act in the way urged by Samara.

The guidelines promulgated in 1979 by HUD's Office of Interstate Land Sales Registration, state that

any conditions which qualify the obligation to complete a building within two years nullify the applicability of the exemption. Likewise, any provision which restricts the purchaser's remedy of specific performance serves to nullify the construction obligation and disqualifies the transaction for the exemption.

Guidelines for Exemptions under the Interstate Land Sales Full Disclosure Act, 44 Fed.Reg. 24,010, 24,012 (1979) (emphasis added) [hereinafter "HUD 1979 Guidelines "]. Unlike Samara, we do not read this language to mean that limitation of the purchaser's remedy of specific performance is the only circumstance which would prevent a transaction from being exempt. The introductions to both the 1979 guidelines and those promulgated five years later in 1984 contain the following language:

Not every conceivable factor of the exemption process is covered in these Guidelines and variations may occur in unique situations. Examples are given, but the examples do not in any way exhaust the myriad possibilities occurring in land development and land sales activity, nor do they set absolute standards.

Guidelines for Exemptions under the Interstate Land Sales Full Disclosure Act, 49 Fed.Reg. 31375, 31376 (1984) (emphasis added) [hereinafter "HUD 1984 Guidelines "]; HUD 1979 Guidelines, supra, 44 Fed.Reg. at 24,010. Therefore, we view the discussion in the 1979 guidelines about limiting specific performance as one example, not exclusive, of a provision which would qualify the obligation to complete the construction within two years thereby preventing application of the exemption.

This interpretation is reinforced by the 1984 guidelines, which state:

Contracts that permit the seller to breach virtually at will are viewed as unenforceable because the construction obligation is not an obligation in reality. Thus, for example, a clause that provides for a refund of the buyer's deposit if the seller is unable to close for any reason within the seller's control is not acceptable for use under this exemption. Similarly, contracts that directly or indirectly waive the buyer's right to specific performance are treated as lacking a realistic obligation to construct.

HUD 1984 Guidelines, supra, 49 Fed.Reg. at 31378 (emphasis added). The position indicated by these guidelines is clearly that the obligation to complete construction within two years must not be illusory, and that limitation of the remedy of specific performance is one example of where the seller would be permitted "to breach virtually at will."

Further, the HUD guidelines clearly indicate that the agency will defer to state contract law to determine in each case whether the required obligation in fact exists. The 1984 guidelines emphasize that

HUD's interpretation of what constitutes a two-year obligation to construct a building relies on general principles of contract law in deciding whether or not the seller has, in fact, an obligation to erect a building within two years. Provisions for purchaser financing and remedies clauses are matters to be decided by the parties to the contract under the laws of the jurisdiction in which the construction project is located.

Id. (emphasis added). 2 We must therefore look to Florida law to determine what is required of the contract in order to ensure that the "obligation" to complete construction is not illusory.

The construction of the Interstate Land Sales Full Disclosure Act has been addressed by several Florida district courts of appeal. Uniformly, they have held that in order for the developer to be "obligated" to complete the building within two years, the obligation must be unrestricted and the contract must not limit the purchaser's right to seek specific performance or damages. We agree.

In Dorchester Development, Inc. v. Burk, 439 So.2d 1032 (Fla. 3d DCA 1983), the Third District Court considered application of the Act where the contract obligated the seller to complete the building within two years but limited the purchaser's remedies to recission and refund of the deposit. The court reasoned that "[w]here the seller is obligated to complete by a time certain, the purchaser is not limited, as here, to the remedy of recission, but he may affirm the contract and seek damages." Id. at 1034. The court further stated that

[s]ince the Act is to be construed to effectuate its remedial purpose of protecting the land sale consumer, we can hardly conclude that a contract which has the effect of limiting the purchaser's remedies conforms to the requirements of the Act.

....

Therefore, because the contracts in the present cause do not contain an unconditional commitment by Dorchester to complete the condominium units within two years, Dorchester is not exempt from the provision of the Act requiring that it furnish a property report to the purchasers in advance of the signing of the contract.

Id. at 1035 (citations omitted). See also Arvida Corp. v. Barnett, 502 So.2d 11 (Fla. 3d DCA 1986), review denied, 511 So.2d 297 (Fla.1987); cf. Marco Bay Assocs. v. Vandewalle, 472 So.2d 472 (Fla. 2d DCA 1985), review denied, 482 So.2d 350 (Fla.1986).

In Berzon v. Oriole Homes Corp., 497 So.2d 670 (Fla. 4th DCA 1986), the Fourth District Court, relying on Dorchester, held that a developer was not exempt from the provisions of the Interstate Land Sales Full Disclosure Act where the agreement specified that construction would be completed within two years but limited the damages available upon a breach of the agreement to a return of the deposit or specific performance. The Fourth District Court's opinion in the instant case is consistent with its prior decision in Berzon.

We note that the Interstate Land Sales Full Disclosure Act was intended to protect the public, and as such should be liberally construed in favor of the public. See Goldring. Further, it is a well-recognized rule of statutory...

To continue reading

Request your trial
45 cases
  • Bruno v. Mona Lisa At Celebration, LLC (In re Mona Lisa at Celebration, LLC)
    • United States
    • U.S. Bankruptcy Court — Middle District of Florida
    • May 16, 2012
    ...decision of the Florida Supreme Court for the proposition that any conditions restricting the two-year obligation are impermissible.66 First, Samara is contrary to the recent binding decisions of the Eleventh Circuit, just discussed. Second, Florida appellate courts repeatedly have limited ......
  • Jankus v. Edge Investors, L.P.
    • United States
    • U.S. District Court — Southern District of Florida
    • April 8, 2009
    ...within two years, and "does not limit the purchaser's remedies of specific performance or damages." Samara Development Corp. v. Marlow, 556 So.2d 1097, 1099-1100 (Fla.1990) (holding that contract which limited purchaser's remedy to recovery of deposit or specific performance upon default by......
  • Normandin v. Eastland Partners, Inc.
    • United States
    • Appeals Court of Massachusetts
    • March 6, 2007
    ...United States, 295 F.2d 481 (9th Cir.1961); Canton v. Monaco Partnership, 156 Ariz. 468, 470, 753 P.2d 158 (1987); Samara Dev. Corp. v. Marlow, 556 So.2d 1097, 1101 (Fla.1990); Threlkeld v. Norris, 300 Ill. 223, 225, 133 N.E. 285 (1921); Davis v. Winter, 168 Md. 613, 618-619, 178 A. 604 (19......
  • Gentry v. Harborage Cottages-Stuart, Lllp
    • United States
    • U.S. District Court — Southern District of Florida
    • February 13, 2009
    ...Agreement 1 does not require the buyer to waive any remedies, including specific performance or damages. See Samara Dev. Corp. v. Marlow, 556 So.2d 1097, 1101 (Fla.1990) (holding that in order for the seller to be obligated to complete construction, the purchase agreement must not limit the......
  • Request a trial to view additional results
2 books & journal articles
  • Florida workers' whistles are not silenced.
    • United States
    • Florida Bar Journal Vol. 74 No. 5, May 2000
    • May 1, 2000
    ...As such, [sections] 448.103(1)(c) was narrowly construed. Golf Channel, 25 Fla. L. Weekly S31, citing Samara Dev. Corp. v. Marlow, 556 So.2d 1097,1100 (Fla. 1990); Farley v. Collins, 146 So. 2d 366, 368 (Fla. (9) All parts of a statute must be read together in order to achieve a consistent ......
  • The Interstate Land Sales Full Disclosure Act's two-year completion exemption.
    • United States
    • Florida Bar Journal Vol. 73 No. 2, February 1999
    • February 1, 1999
    ...rights and, therefore, does not condition the completion guarantee. In 1990, the Florida Supreme Court, in Samara Dev. Corp. v. Marlow, 556 So. 2d 1097 (Fla. 1990), expanded Dorchester by holding that in order for the sale of a condominium unit to be eligible for the two-year completion exe......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT