Schellinger Brothers v. City of Sebastopol, A122972.

Decision Date02 December 2009
Docket NumberNo. A122972.,A122972.
CourtCalifornia Court of Appeals Court of Appeals
PartiesSCHELLINGER BROTHERS, Plaintiff and Appellant, v. CITY OF SEBASTOPOL, Defendant and Respondent.

Bingham McCutchen, Geoffrey L. Robinson, Marie A. Cooper and Sean R. Marciniak for Plaintiff and Appellant.

Meyers, Nave, Riback, Silver & Wilson, Julia L. Bond, Edward Grutzmacher; McLaughlin & Hendrickson and Larry McLaughlin for Defendant and Respondent.

OPINION

RICHMAN, J.

It is probably a truism that since adoption of the California Environmental Quality Act (Pub. Resources Code, § 21000 et seq.1; CEQA) in 1970, every developer has at some point before construction starts ground his teeth or clenched her fists in frustration while enduring the often lengthy process leading to certification of an environmental impact report (EIR) for the proposed project. This appeal shows that frustration is not enough to justify premature judicial action that would short-circuit the decisionmaking process intended by CEQA.

In Sunset Drive Corp. v. City of Redlands (1999) 73 Cal.App.4th 215 (Sunset Drive), the Court of Appeal held that a cause of action could be alleged to warrant issuance of a writ of traditional mandate under Code of Civil Procedure section 1085 compelling action by a city council that was refusing to make a decision on whether to certify an EIR. The developer here has seized upon Sunset Drive to support the extraordinary proposition—apparently advanced in earnest for the first time since CEQA was enacted—that a court is authorized to issue a writ of administrative mandamus to compel a city council to certify a proposed EIR, even though the council had decided that the pending draft EIR required recirculation to address new issues.

Certain that the Sunset Drive court never imagined that such a construction would be placed on its opinion, we reject that construction, and thus reject the developer's contention that the one-year time limit for certifying an EIR established by section 21151.5 of CEQA constitutes an ironclad, one-size-fits-all rule that permits no exception. We reach the same conclusion concerning the impact of Government Code section 65589.5: it too cannot be used to halt the decisionmaking process specified by CEQA that is still ongoing. Finally, we conclude that the developer's active participation in that process for more than three years—which included numerous changes in the size and composition of the project—after the date it now claims the city lost its discretionary jurisdiction amounts to laches, an accepted ground for relaxing the directory deadline of section 21151.5.

In light of these conclusions, we affirm the trial court's decision not to interject itself into the still ongoing process of preparing an EIR.

BACKGROUND

The record before us includes 52 volumes of an administrative process that is not yet over. The parties agree that our review is de novo. (Vineyard Area Citizens for Responsible Growth, Inc. v. City of Rancho Cordova (2007) 40 Cal.4th 412, 427 [53 Cal.Rptr.3d 821, 150 P.3d 709] (Vineyard).) Fortunately, our resolution of the issues presented by this appeal will require only the briefest references to that record.

At issue here is the attempt of plaintiff and appellant Schellinger Brothers (Schellinger) to develop half of a site of approximately 20 acres in an area known as Laguna Vista within the limits of defendant City of Sebastopol (City). Schellinger, which is a partnership, does not own the property, but has an option to buy it from the current owner, Scott Schellinger, one of the partners.

Originally, in January 2001, Schellinger submitted an application to construct a project with 182 units of single-residence housing along with a neighborhood commercial center of 16,300 square feet. The City began preparation of an EIR for the project in this form.2

The draft EIR was released for public comment in March 2002. Between April (when Schellinger formally resubmitted its application) and June of 2002, when the draft EIR was completed, Schellinger was continually making changes in the project. By June, when the first public hearing was conducted by the City's planning commission, the project was reduced to 177 units and the size of the commercial office center had been reduced.3 After two public hearings, the planning commission accepted the draft EIR, with modifications.

In August, as the city council was about to consider the draft EIR as approved by the planning commission, Schellinger again retinkered the project, dropping the number of units to 172, as well as making other changes. After two public hearings, and while the council was considering the matter, Schellinger decided to resubmit its project proposal.

Schellinger submitted its new proposal in May 2003. It sought approval of a project reconfigured with 145 units and no commercial center. The City deemed Schellinger's application complete on June 23, 2003.

Thereafter, it became clear that the project implicated the City's open space ordinance, which would ordinarily require an analysis of the project separate from the EIR. However, with no objection from Schellinger, the City council decided to fold the open space analysis into the EIR. The City also decided to recirculate the draft EIR.

In September 2003, the City engaged a firm to prepare the open space analysis and the draft EIR for recirculation. But it was not until November of that year that Schellinger could arrange for that firm to have access to the project site.

The recirculated draft EIR was released for public comment in August 2004. Opposition to the project—which was considerable, as it had been from the beginning—caused the City to propound a large number of requests to Schellinger for additional information. This apparently continued through October 2005.

The recirculated draft EIR was again considered by the planning commission in October and November 2005,4 which recommended conditional approval of the recirculated draft EIR. The city council took up the matter on December 6; the persistent opposition to the project was still vocal, and, at Schellinger's request, the matter was continued to January 2006. In February 2006, the council gave Schellinger the opportunity to submit a comprehensive response to questions and comments from both the council and the public about the project.

In May 2006, matters were approaching the point where the city council had scheduled a vote on the recirculated draft EIR. Apparently in response to the public opposition,5 Schellinger again modified the proposal by reducing the number of units to 125. However, before an actual vote, the City and Schellinger agreed to undergo a mediation of the project controversy.

Almost a year passed before another revised proposal, this one based on the mediation,6 was set to go to the city council. The number of units remained at 125 but the commercial space component was revived, although the square footage was now fixed at 2,335. However, majority support on the city council could not be mustered for the mediated project. Schellinger demanded that "the City comply with its legal duty to approve the 145-unit Laguna Vista Project" as proposed in Schellinger's May 2003 application. The City scheduled a council meeting for June 5, 2007, to consider approving the recirculated draft EIR and the project in its latest form.7 At this point the city council decided that the draft EIR should again be recirculated for further public comment and additional analysis on certain environmental issues.

For Schellinger, this was the final straw. Schellinger refused to pay for what the City termed "further processing," whereupon the City "halted the administrative proceeding."8 Schellinger's next move was to commence this litigation.

On August 31, 2007, Schellinger filed a complaint with seven causes of action. The only ones relevant here are the first, fourth, and fifth causes of action, which were titled "Violation of Anti-NIMBY statute" (Gov. Code, § 65589.5),9 "Breach of Contract Regarding Processing Costs," and "Breach of Mediation Agreement," respectively.

Government Code section 65589.5 states the policy of the state that local government "shall not disapprove a housing development project... for very low, low-, or moderate-income households, ... or condition approval in a manner that renders the project infeasible ...." (Id., subd. (d); see id., subd. (b).) Because its latest proposal for the project "proposes 20% affordable housing," Schellinger alleged that "The City's arbitrary and capricious actions in processing, or purporting to process the Laguna Vista project [application], and its recent decision to continue in the same path by imposing yet another round of inordinate delay, has effectively imposed infeasible conditions."

Schellinger's fourth cause of action alleged an implied-in-fact agreement between it and the City "that Schellinger ... would pay or reimburse the City for the costs of processing the Laguna Vista project [application], and the City would in turn process the project [application] reasonably, competently, and in accordance with law." While Schellinger "performed all its obligations under that contract by making all payments in a timely manner," the City breached it, in that the City "has processed or purported to process the Laguna Vista project [application] unreasonably, in a manner that is arbitrary and capricious, in a manner that unreasonably and without rational cause delayed and hindered the Laguna Vista project." Schellinger alleged that it was thus entitled to damages "including processing costs in excess of those reasonably necessary for lawful, reasonable processing of the Laguna Vista project [application] within the time frame allowed by law, and damages associated with the unlawful and unreasonable delays resulting from the failure to process competently."

Finally, as to the...

To continue reading

Request your trial
25 cases
  • Tiburon Open Space Comm. v. Cnty. of Marin
    • United States
    • California Court of Appeals Court of Appeals
    • May 12, 2022
    ... ... v. City of Los Angeles (2004) 126 Cal.App.4th 1180, 11971198, 24 ... for the project." ( Schellinger Brothers v. City of Sebastopol , supra , 179 Cal.App.4th ... ...
  • Schellinger Bros. v. Cotter, A142201
    • United States
    • California Court of Appeals Court of Appeals
    • August 26, 2016
    ... 2 Cal.App.5th 984 207 Cal.Rptr.3d 82 SCHELLINGER BROTHERS et al., Plaintiffs and Respondents, v. James F. COTTER, Defendant and ... to develop a large tract of real 207 Cal.Rptr.3d 86 property in the City of Sebastopol (the City) it had agreed to purchase from appellant James F ... ...
  • Anderson v. City of S.F.
    • United States
    • California Court of Appeals Court of Appeals
    • January 14, 2013
    ... ... (CEQA Guidelines, § 15000.)" ( Schellinger Brothers v. City of Sebastopol (2009) 179 Cal.App.4th 1245, 1256, fn ... ...
  • Cleveland Nat'l Forest Found. v. San Diego Ass'n of Gov'ts
    • United States
    • California Court of Appeals Court of Appeals
    • November 24, 2014
    ... ... ( Latinos Unidos de Napa v. City of Napa (2013) 221 Cal.App.4th 192, 196, 164 Cal.Rptr.3d ... ( 21168.9, subd. (c); Schellinger Brothers v. City of Sebastopol (2009) 179 Cal.App.4th ... ...
  • Request a trial to view additional results
2 books & journal articles
  • Mcle Self-study Article Public Policies and Legislation Fostering Housing in California
    • United States
    • California Lawyers Association California Real Property Journal (CLA) No. 41-1, March 2023
    • Invalid date
    ...Environmental Quality Act (CEQA), Pub. Res. Code, §§ 21000-21189, see Schellinger Brothers v. City of Sebastopol (1st Dist. 2009) 179 Cal.App.4th 1245; see also, Hernandez and Golub, Major Reforms to Housing Accountability Act Come to California (2018) 36 Cal. Real Prop. J. No. 2, 25.7. Cal......
  • Is the Housing Accountability Act the Solution to California's Housing Crisis?
    • United States
    • California Lawyers Association Environmental Law News (CLA) No. 28-2, September 2019
    • Invalid date
    ...Sup. Court, Order to Enforce Settlement Agreement/Stipulated Order, July 21, 2017.)30. Schellinger Brothers v. City of Sebastopol, 179 Cal. App.4th 1245 (2009) (city could not be compelled by writ of administrative mandate to approve environmental impact statement for housing project while ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT