Scholl v. McWilliams Dredging Co.

Decision Date21 July 1948
Docket NumberNo. 133,Docket No. 20828.,133
Citation169 F.2d 729
PartiesSCHOLL v. McWILLIAMS DREDGING CO. et al.
CourtU.S. Court of Appeals — Second Circuit

John F. X. McGohey, U. S. Atty., and Henry L. Glenn, Asst. U. S. Atty., both of New York City, for defendants-appellants McWilliams Dredging Co. and Nick F. Helmers, Inc.

Krisel, Lessall & Dowling, of New York City (Henry Brickman, of New York City, of counsel), for plaintiff-appellee William Scholl.

Before AUGUSTUS N. HAND, CLARK, and WOODBURY, Circuit Judges.

AUGUSTUS N. HAND, Circuit Judge.

The above plaintiff, William Scholl, sued to recover from the defendants McWilliams Dredging Company and Nick F. Helmers, Inc., unpaid overtime compensation for the period of his employment from June 20, 1942, to January 22, 1944, and an additional amount as liquidated damages pursuant to Section 16(b) of the Fair Labor Standards Act of 1938, 52 Stat. 1060, 29 U.S.C.A. § 216(b). The defendants are corporations — McWilliams being organized under the laws of the State of Illinois and Helmers being organized under the laws of the State of New York. As co-adventurers under a War Department contract dated August 2, 1941, these defendants agreed to provide engineering services for construction of certain outlying bases in Greenland. They were required to furnish labor, materials, tools, equipment (including dredging and construction plant), supplies not furnished by the government, and services necessary for the field design, layout, engineering supervision and construction of the installations in Greenland.

The Engineering Department of the defendants carried out the field design, layout, preparation of specifications and the formulation of mechanical requirements including necessary re-design. The completed plans and specifications were submitted for approval to the North Atlantic Division of the U. S. Engineer's Office. From the plans which were approved and returned, schedules of the quantities of materials required were prepared and submitted, together with the applicable specifications, to the Purchasing Department of the defendants for requisition. The approved plans and specifications were then forwarded to the project for use in construction. Materials and equipment were procured by direct government purchase or by the defendants themselves upon receiving prior government approval. A very substantial part of these purchases came from outside the States of New York and Massachusetts. Title to these goods passed to the government and shipment was made to the Corps of Engineers at either Claremont Terminal in New Jersey or a terminal at Framingham, Massachusetts. They were subsequently transported to Greenland on vessels supplied by the government where they were used in the construction. The record does not disclose the specific uses for which the base was intended but there is testimony that the work included the construction of hangars, barracks, mess halls, hospitals, pumping stations, laundries, docks trailways, railways, pipe lines, power stations, and electrical distribution systems.

The plaintiff worked in the New York office of the defendants, designing or drafting plans for the electric light and power layouts for certain of the buildings to be constructed in Greenland. For this work he was supplied with the architect's plan of the particular building, a mechanical plan containing the location of electrically-driven machinery, and other information contained in the specifications, manuals, and directives. Plaintiff also performed some material takeoff work in the New York office, preparing from the approved plans specific lists of the materials which would be required for the particular jobs. These lists were sent to the defendants' Purchasing Department and served as a basis for requisitions. In addition, between August 4, 1943 and sometime in December, 1943, plaintiff made several trips to the Framingham terminal, remaining there on each occasion "a couple of days." While there he was engaged in pointing out and separating those materials to be shipped to the base in Greenland and those to remain at the terminal. In some cases the designation of the materials to be shipped was not accompanied by any breaking of bulk, but in other instances boxes were opened in order to separate the portions of the cargo which were selected to go forward to the base.

The District Court held that the services rendered by the plaintiff were within the coverage of the Fair Labor Standards Act and that they were not of such a nature as to exempt him from the Act as an administrative or professional employee. 52 Stat. 1060, 29 U.S.C.A. §§ 206, 207, 213. If the plaintiff should be held to be covered by the Fair Labor Standards Act the amount of the overtime compensation due him was stipulated to be $551.76, which the District Court awarded him as well as liquidated damages to the same amount, $165.52 as attorneys' fees and $25 costs, making a total of $1,294.04. From a judgment for the plaintiff for that amount the defendants have appealed.

Pertinent portions of Sections 6 and 7 of the Fair Labor Standards Act which govern the wages of employees who are covered by the Act are set forth in the margin.1 The basic question presented is whether plaintiff should be considered as "engaged in commerce or in the production of goods for commerce"2 and shall for that reason be held to come within the provisions of the Act. The answer to this question depends upon the character of this employee's activities and not upon the nature of his employer's business. Overstreet v. North Shore Corp., 318 U.S. 125, 63 S.Ct. 494, 87 L.Ed. 656; Laudadio v. White Const. Co., 2 Cir., 163 F.2d 383. Plaintiff contends that his work was in several respects of such a type as to bring him within the Act.

His first claim is that his work constituted an engagement in commerce because it was directly connected with the construction of an instrumentality of commerce, to wit: the base at Greenland. We believe that at least for the purposes of this Act the base should be considered as being later used as an instrumentality of commerce rather than solely as an instrumentality of war. The record does not disclose the uses to which this base was to be put, but we can safely assume that it was later used for purposes of commerce, as, for example, to facilitate the transportation of persons, mail and articles of commerce in general, and not solely for military purposes such as training of personnel, or for purely combat activities. Such a conclusion meets the tests we applied in other like situations in our recent decisions in Divins v. Hazeltine Electronics Corp., 2 Cir., 163 F.2d 100, and Laudadio v. White Const. Co., supra. The difficulty, however, with treating the plaintiff as covered by the Act is that his work did not relate to repair or even to reconstruction of an existing instrumentality of commerce but to completely new construction. This we recently held in Laudadio v. White Const. Co., supra, did not bring the employee within the Act. A similar result was reached by the First Circuit in Nieves v. Standard Dredging Corp., 152 F.2d 719. See also Kelly v. Ford, Bacon & Davis, 3 Cir., 162 F.2d 555; Wells v. Ford, Bacon & Davis, Inc., 6 Cir., 145 F.2d 240; Brue v. J. Rich Steers, Inc., D.C.S.D.N.Y., 60 F.Supp. 668; Damon v. Ford, Bacon & Davis, D.C.E.D.Pa., 62 F.Supp. 446. Completely new construction has not been regarded as having a close enough relation to actual movements in commerce to subject the employer to the provisions of the Act. The decision in Pederson v. J. T. Fitzgerald Const. Co., 318 U.S. 740, 742, 63 S.Ct. 558, 87 L.Ed. 1119; Id., 324, U.S. 720, is not contrary for the work there consisted of reconstruction and repair of existing facilities of a railroad which had previously been used in interstate commerce. In Walling v. McCrady Const. Co., 3 Cir., 156 F.2d 932, Ritch v. Puget Sound Bridge & Dredging Co., 9 Cir., 156 F.2d 334, and Walling v. Patton-Tulley Transp. Co., 6 Cir., 134 F.2d 945, it was held that even certain new construction work relating to existing instrumentalities of commerce brought the employees of the contractor within the Act. These decisions however expressly stressed that the work was upon instrumentalities which had already been used in interstate commerce, distinguishing the construction of new installations which had not been devoted to commerce before. See Kelly v. Ford, Bacon & Davis, supra. The cases may be of doubtful authority in view of our decision in Laudadio v. White Const. Co., supra, where we held that though work of reconstruction and extensions of existing facilities of interstate commerce at Floyd Bennett Airfield was covered by the Act, work relating to construction of new facilities there was not. However, to deny coverage to the plaintiff in the case at bar is consistent with these decisions for the undertaking upon which plaintiff was working was the construction of a new base that was later to be used for interstate commerce. It might be argued that the moment any part of the Greenland base might be used in commerce, though before completion of the entire installation, employees who worked on the remainder would come within the Act. Such a theory would make the exemption accorded to construction of a new instrumentality of commerce contingent upon the use of any part of the uncompleted base and dependent upon an uncertain test which we do not find recognized by the authorities. We hold that this undertaking for the construction of the Greenland base retains until its completion the status which it had at the beginning. In any event, under our decision in Laudadio v. White Const. Co., supra, the construction of new facilities would not seem to be covered by the Act even though there may also have existed at the same installation other facilities which had been used in commerce.

Plai...

To continue reading

Request your trial
24 cases
  • Hartmaier v. Long
    • United States
    • Missouri Supreme Court
    • March 12, 1951
    ...& Davis, Inc., 3 Cir., 162 F.2d 555, 557, under facts similar to those involved in the instant case. Further, Scholl v. McWilliams Dredging Co., 2 Cir., 169 F.2d 729, 731, states Walling v. McCrady Const. Co., supra; Walling v. Patton-Tulley Transp. Co., 6 Cir., 134 F.2d 945, and Ritch v. P......
  • Mitchell v. Hodges Contracting Company
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • November 14, 1956
    ...that this was "new" construction beyond the coverage of the Act initially and which, adopting the Second Circuit's rule, Scholl v. McWilliams Dredging Co., 169 F.2d 729, did not change (until final completion) merely by interim use from April to This approach was too narrow. Even if (and th......
  • McComb v. Turpin
    • United States
    • U.S. District Court — District of Maryland
    • November 30, 1948
    ...Kelly v. Ford, Bacon & Davis, D.C., 71 F.Supp. 311, 314, affirmed 3 Cir., 162 F.2d 555. In the very recent case of Scholl v. McWilliams Dredging Co., 2 Cir., 169 F.2d 729, 732, the plaintiff employee was engaged as a draftsman in a New York office of engineers preparing plans for a governme......
  • Mitchell v. Vollmer Company
    • United States
    • U.S. Supreme Court
    • June 6, 1955
    ...719, where the employer was dredging a channel for navigation in a previously nonnavigable stream. The Second Circuit in Scholl v. McWilliams Dredging Co., 169 F.2d 729, applied the rule where the employer was engaged in the construction of a new air base in Greenland that had not yet been ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT