School Bd. of Seminole County v. GAF Corp.

Decision Date14 April 1982
Docket NumberNos. 79-457,80-205 and 80-208,s. 79-457
Citation413 So.2d 1208
Parties4 Ed. Law Rep. 688 SCHOOL BOARD OF SEMINOLE COUNTY, Florida, Appellant/Cross-Appellee, v. GAF CORPORATION, etc., et al., Appellee/Cross-Appellants.
CourtFlorida District Court of Appeals

Ned N. Julian, Jr., Sanford, for appellant/cross-appellee.

No appearance for appellee/cross-appellant, GAF Corp.

Stephen D. Feinberg, of Akerman, Senterfitt & Eidson, Orlando, for appellee, Eoghan N. Kelley.

SHARP, Judge.

The School Board of Seminole County appeals from adverse summary judgments in three suits which asserted against Kelley liability for improperly designing or supervising the construction of roofs for three schools in Seminole County. The three schools, Idyllwilde Elementary, Forest City Elementary, and Teague Middle School, were all designed by Kelley and had the same basic roof design. They were built in the same two-year time span (1969-1971), and the roofs of all three schools required extensive repairs and eventual replacement. The actions were consolidated on appeal because the legal issues and facts involved in all three appeals are basically similar.

The lower court ruled that the four-year statute of limitations 1 applied to these causes of action against Kelley, and that the record showed, as a matter of law, that the School Board discovered or should have discovered the design defects in the roofs more than four years before it filed its lawsuits, in July of 1977. We agree that section 95.11(3)(c) applies to these cases rather than the two-year statute. 2 The language of the four-year statute is much more specifically applicable to these suits against Kelley than the two-year statute, which generally references "professional malpractice" suits. 3 However, we disagree that the record established conclusively, in these cases, that the four-year statute had run against the School Board by July of 1977. Accordingly, we reverse. 4

In order to sustain a summary judgment holding that a cause of action is barred by a statute of limitations, such as section 95.11(3)(c), the record must conclusively demonstrate that the appellant discovered or should have discovered the injury or the negligent act of the appellee giving rise to the injury. First Federal Savings and Loan Association of Wisconsin v. Dade Federal Savings and Loan Association., 403 So.2d 1097 (Fla. 5th DCA 1981); Mott v. Fort Pierce Memorial Hospital, 375 So.2d 360 (Fla. 4th DCA 1979); Tobin v. Dannheisser, 372 So.2d 970 (Fla. 1st DCA 1979). Further, the reviewing court must draw every possible inference in favor of the party against whom the summary judgment is made. Wills v. Sears, Roebuck & Co., 351 So.2d 29 (Fla.1977).

In these cases the record established that Kelley was the architect and designer for a number of schools in Seminole County before and after the three included in these law suits. Idyllwilde, Forest City and Teague were designed and supervised in their construction by Kelley and they all had a "round" open-school plan developed by Kelley. All three developed roof leaks during the first two years following completion of construction. These repairs were made by the contractors, under the two-year construction warranties.

In 1973 the warranty period had expired on Idyllwilde, because it was built first, and the leaks became increasingly severe and persistent at that school. School Board employees conferenced on Idyllwilde's roof with the roofing sub-contractor, resulting in the January 31, 1973 Memorandum from a Mr. Muse (Head of Maintenance) to his supervisor, Mr. Carlton (Head of the School Plants). In the memorandum Mr. Muse said the roof was leaking because:

[T]here were no provisions made in the roof itself to prevent the material from cracking due to expansion .... This problem could be very serious and I am concerned because we have three other schools constructed with practically the same roof design. (He admitted that he was referring to Teague and Forest City).

Kelley's failure to design proper expansion joints in the roof systems was one of the School Board's alleged reasons for the roof "failures" at the three schools. Other correspondence from Mr. Carlton and the admissions in his depositions show he was aware in early 1973 that the roofs on all three schools had severe leaking problems, and he was concerned as to whether or not the defects were covered by the GAF bond on the roofs.

However, from the beginning of the leaks through 1975, the School Board called upon Kelley to handle, coordinate and devise plans to repair the roofs. Repairs were made repeatedly, without cost to the School Board. The record is replete with correspondence during 1973 and 1974 from the School Board to Kelley reporting leaks and problems, and correspondence from Kelley assuring the School Board that the roof problems were being handled and "permanent repairs" were being made under his direction, together with the roof bonding company. 5

By the end of 1974, the leaks became "critical" and in 1975, School Board employees concluded the roofs required extensive repairs or replacement. More repairs by Kelley and GAF were attempted, but in March of 1976 GAF refused to make any further repairs because GAF claimed the problem was "structural" or design related, and not covered under its bond.

The School Board claimed it was not told by Kelley or GAF that the roof leaks really were caused by "design" or "structural" defects not covered by the bond until March of 1976, although Mr. Carlton admitted he may have been so informed by a GAF representative in 1975. Kelley admitted he knew GAF's position in 1974. He also admitted he realized the School Board was relying on his expertise, knowledge and capacity to resolve the roof problems until 1976. The School Board witnesses also confirmed they had relied on Kelley during that time to determine the cause of the leaks and to repair them. During 1973 and 1974 they were told many possible theories as to why the roofs were leaking.

Under the circumstances as established in this record, where a "client" is relying on a "professional" to resolve and cure a problem within the ambit of their professional relationship, and where the professional continuously works on the problem and assures the client the problem is being solved, we think it is a question of fact resolvable by a jury, as to when the client knew or should have known his problem was permanent and irreparable. Swagel v. Goldman, 393 So.2d 65 (Fla.3d DCA 1981); Burnside v. McCrary, 382 So.2d 75 (Fla.3d DCA 1980). Had the roof problems been reparable as Kelley assured the School Board they were, the appellant would have had no cause of action against Kelley. The Board's reliance on Kelley as the professional to diagnose and plan the repairs may reasonably have prevented the Board from discovering the permanency of the alleged design defects earlier. We distinguish K/F Development & Investment Corp. v. Williamson Crane & Dozer Corp., 367 So.2d 1078 (Fla.3d DCA 1979), cert. denied, 378 So.2d 350 (Fla.1979), because that case did not deal with a client-professional relationship. Nor do we conclude that it is necessary for us to adopt the "continuous treatment" doctrine embraced in other states 6 because those principles are already encompassed in Florida's statutory concept of commencing the running of the statute of limitations when an injury is discovered or should have been discovered.

REVERSED.

FRANK D. UPCHURCH, Jr., J., concurs and concurs specially with opinion.

COWART, J., dissents with opinion.

FRANK D. UPCHURCH, Jr., Judge, concurring specially.

While I concur with Judge Sharp, I would go further and recognize the "continuing treatment" doctrine. It is unrealistic to expect a potential claimant, who has engaged a professional, to immediately consider suit when he first discovers an error, omission, or unexpected result, especially, as here, when the professional makes every effort to have the condition corrected. To expect the School Board here to sue their architect on whose judgment and advice they had relied when he was diligently working to have the defective roofs repaired is unrealistic.

These circumstances, in my opinion, are far different from those where the injury or damage is apparent, permanent and unrepairable, although the cause may be uncertain. Aware that his rights have been invaded, it is not unrealistic to impose the burden on the claimant to inquire who, how, and what caused the damage.

COWART, Judge, dissenting:

I respectfully dissent. In Florida the applicable statute of limitations has always been deemed to have commenced to run from the date the cause of action arises. This means the date the plaintiff can first sue for the legal wrong involved. That event can often, if not usually, be identified and determined as a matter of law without the resolution of any genuine issue of fact and, hence, is often properly the subject of a summary judgment.

No rule of law requires that defects resulting from negligence be permanent or non-repairable in order to be actionable. Whether or not a construction deficiency is covered by a bond does not affect the accrual of a cause of action against a...

To continue reading

Request your trial
9 cases
  • Larson & Larson, P.A. v. Tse Industries
    • United States
    • Florida Supreme Court
    • November 5, 2009
    ...get competent help and sue, or be forever barred from asserting his stale claim. Sch. Bd. of Seminole County v. GAF Corp., 413 So.2d 1208, 1213 (Fla. 5th DCA 1982) (Cowart, J., dissenting), quashed sub nom. Kelley v. Sch. Bd. of Seminole County, 435 So.2d 804 (Fla.1983); see Kelley, 435 So.......
  • Board of Trustees of Santa Fe Community College v. Caudill Rowlett Scott, Inc.
    • United States
    • Florida District Court of Appeals
    • December 21, 1984
    ...period, citing Kelley v. School Board of Seminole County, 435 So.2d 804 (Fla.1983), which overrules School Board of Seminole County v. GAF Corporation, 413 So.2d 1208 (Fla. 5th DCA 1982), upon which appellant had relied in the trial court. Appellees also cite Havatampa Corporation v. McElvy......
  • Moore, By and Through Moore v. Morris
    • United States
    • Florida District Court of Appeals
    • January 4, 1983
    ...view, the judgment below should be reversed. Johnson v. Mullee, 385 So.2d 1038 (Fla. 1st DCA 1980); see, School Board of Seminole County v. GAF Corp., 413 So.2d 1208 (Fla. 5th DCA 1982); Swagel v. Goldman, 393 So.2d 65 (Fla. 3d DCA 1981), and cases 1 The infant was born on July 9, 1973. The......
  • Fort Lauderdale v. ROSS, SAARINEN, BOLTON & WILDER
    • United States
    • U.S. District Court — Southern District of Florida
    • October 26, 1992
    ...causing an obvious problem before the statute of limitations commences to run." Id. (criticizing School Bd. of Seminole County v. GAF Corp., 413 So.2d 1208 (Fla. 5th Dist.Ct.App.1982)).3 In Conquistador, unit owners took control of a condominium in 1974 and discovered roof leaks by 1976. Du......