Scott v. Ingle Bros. Pac., Inc.

Decision Date27 December 1972
Docket NumberNo. B--3374,B--3374
PartiesH. L. SCOTT, Petitioner, v. INGLE BROS. PACIFIC, INC., Respondent.
CourtTexas Supreme Court

C. J. Humphrey, Amarillo, for petitioner.

Gibson, Ochsner, Adkins, Harlan & Hankins, Michael C. Musick, Amarillo, for respondent.

GREENHILL, Chief Justice.

The question before us is whether the parties had entered into a contract whereby Ingle Bros. Pacific, Inc., agreed to employ H. L. Scott. The trial court held that, as a matter of law, there was a contract of employment; and based on jury findings of a breach of the contract, it entered a judgment for Scott for some $54,210. The court of civil appeals completely disagreed. It held that as a matter of law there was no employment contract. 478 S.W.2d 210. We disagree with both courts. Our holding is that there is an issue of fact as to the intention of the parties. Accordingly, as to this portion of the case which is before us, we reverse the judgment of the court of civil appeals and remand the cause to the district court for a new trial.

The facts are set out in the opinion of the court of civil appeals. As relevant here, Scott owned and operated a mop manufacturing plant in Amarillo. An executive of Ingle indicated a desire to buy Scott's plant. A 'purchase agreement' was entered into on June 16, 1969, whereby Scott agreed to sell to Ingle all inventory and other assets, the trade name, and the manufacturing and marketing rights for $50,000. Of this, $35,000 was to be in cash; and the balance of $15,000 was evidenced by a promissory note.

The 'purchase agreement' continued:

'An Employment Agreement has been prepared wherein H. L. Scott will manage the business for a minimum of five years at an annual salary of $15,000, payable monthly, with a $3,000 increase after the 1st year, provided annual gross sales exceed $200,000.

'A separate lease agreement shall be drawn between H. L. Scott and Ingle as follows: ten year lease at $550 monthly with option to renew for additional 5 years at $550 monthly plus tax increase over 1969 to be added.'

The sale was consummated. The contemplated 'separate lease agreement' was executed, but both parties agreed that no separate employment agreement had been executed before the 'purchase agreement,' and none was executed thereafter. Scott immediately assumed management of the plant at $15,000 per year. The gross sales increased; and Scott's salary was, as indicated in the 'purchase agreement,' raised $3,000 per year after 9 months.

About a year and a half after the 'purchase agreement' was executed, a dispute began when Ingle decided to close the Amarillo plant and move it to New Mexico. Ingle had not paid Scott the $15,000 balance of the purchase price evidenced by the note. Ingle authorized Scott to pay himself a certain sum out of company funds; but on the advice of counsel, Scott paid himself a different amount in a different way. Ingle then fired Scott. Scott brought this suit on the above employment agreement. Ingle took the position that there was no employment contract. The jury found that Scott had been discharged without good cause.

So we return to the problem stated at the outset: was that portion of the 'purchase agreement' dealing with the employment of the seller, Scott, an enforceable contract? This depends upon the intention of the parties. An agreement simply to enter into negotiations for a contract later does not create an enforceable contract. But parties may agree upon some of the terms of a contract, and understand them to be an agreement, and yet leave other portions of an agreement to be made later.

The writing in question says that an employment agreement 'has been prepared.' This was not an accurate statement. None had been, and this is the problem. It is capable of meaning, 'an agreement has been arranged, or has been made, whereby Scott will be employed to manage the plant for $15,000 per year,' et cetera. Or it could mean that the parties contemplated negotiations for an employment contract with those basic terms. Or it could mean that the parties were just wrong in putting the statement in the purchase agreement, and there was no employment contract. It is of significance that Scott did sell the plant to Ingle; and he did begin to manage it as an employee at the beginning salary of $15,000. He did get the $3,000 per year raise, but sooner than the one year stated in the contract. Whether the execution of a separate employment agreement was, and is, essential to a mutuality of assent is a question of the intention of the parties.

In this troublesome area, Corbin on Contracts is helpful. In Section 29, Partial Agreements--'Contracts to Make a Contract,' it is stated that:

'People do business in a very informal fashion. . . . A transaction is complete when the parties meant it to be complete. It is a mere matter of interpretation of their expressions to each other, a question of fact. * * *

'Even though certain matters are expressly left to be agreed upon in the future, they may not be regarded by the parties as essential to their present agreement. Furthermore, the terms left for future settlement may be within definite and prescribed limits.' 1 Corbin on Contracts (1963) 87--91.

The text continues, as relevant here:

'The court will be more ready to find that the apparently incomplete agreement was in fact complete and required the payment and acceptance of a 'reasonable' price or a performance on 'reasonable' terms, in case the parties have already rendered some substantial performance or have taken other material action in reliance upon their existing expressions of agreement. The fact...

To continue reading

Request your trial
133 cases
  • Texas Farmers Ins. Co. v. Soriano
    • United States
    • Texas Court of Appeals
    • 30 Noviembre 1992
    ...issues and instructions to be submitted to the jury, Mobil Chem. Co. v. Bell, 517 S.W.2d 245, 255 (Tex.1974); Scott v. Ingle Bros. Pac., Inc., 489 S.W.2d 554, 557 (Tex.1972), and broad issues are the preferred manner of submission in negligence cases. Island Recreational Dev. Corp. v. Repub......
  • Burk Royalty Co. v. Walls
    • United States
    • Texas Supreme Court
    • 27 Mayo 1981
    ...other occasions, approved broad submissions. Turner v. General Motors Corp., 584 S.W.2d 844, 847 n. 1 (Tex.1979); Scott v. Ingle Bros. Pacific, Inc., 489 S.W.2d 554 (Tex.1972); Haas Drilling Co. v. First National Bank, 456 S.W.2d 886, 889 (Tex.1970); Pate v. Tellepsen Const. Co., 596 S.W.2d......
  • Pitman v. Lightfoot
    • United States
    • Texas Court of Appeals
    • 7 Agosto 1996
    ...(Tex.App.--Corpus Christi 1990, writ denied), or in determining what constitutes necessary and proper issues. Scott v. Ingle Bros. Pacific, Inc., 489 S.W.2d 554, 557 (Tex.1972). Instructions and definitions are proper when they are raised by the written pleadings, supported by the evidence,......
  • Valores Corporativos, S.A. de C.V. v. McLane Co., Inc.
    • United States
    • Texas Court of Appeals
    • 19 Febrero 1997
    ...contract depends upon the parties' intent. Foreca, S.A. v. GRD Dev. Co., 758 S.W.2d 744, 745-46 (Tex.1988); Scott v. Ingle Bros. Pac., Inc., 489 S.W.2d 554, 555 (Tex.1972). While the absence of an intent to be bound without a signed, written agreement may be established as a matter of law, ......
  • Request a trial to view additional results