Seneca Waste Solutions, Inc. v. Sheaffer Mfg. Co., LLC
Decision Date | 10 December 2010 |
Docket Number | No. 09-0325.,09-0325. |
Citation | 791 N.W.2d 407 |
Parties | SENECA WASTE SOLUTIONS, INC., Appellant, v. SHEAFFER MANUFACTURING CO., LLC and Sheaffer Pen Corporation, A Division of BIC USA Inc., Appellees. |
Court | Iowa Supreme Court |
Brenda L. Myers-Maas, West Des Moines, for appellant.
Benjamin P. Roach of Nyemaster, Goode, West, Hansell & O'Brien, P.C., Des Moines, for appellees.
After hiring a contractor to clean and decontaminate its pen manufacturing plant, the owner of the plant refused to pay more than the "not to exceed" price designated in the cleaning contract. The contractor filed suit, claiming entitlement to a judgment in an amount exceeding the not-to-exceed contract price because the scope of the work defined in the contract was modified by the owner after the written contract was formed. The district court granted summary judgment in favor of the plant owner. On appeal, the court of appeals reversed and remanded. We granted the plant owner's application for further review.
A reasonable fact finder could find the following facts from the summary judgment record. Sheaffer Manufacturing Company operated a pen manufacturing plant in Fort Madison, Iowa. After deciding to cease operations at that location, Sheaffer took bids from several environmental contractors to clean and decontaminate the plant. Seneca Waste Solutions submitted a letter bid on September 7, 2006. Sheaffer offered the contract to Seneca on a time and materials basis but specifically requested the inclusion of a not-to-exceed price of $170,000. Seneca agreed, and the agreement was finalized in a written "Contractor Agreement." The agreement included the following relevant terms:
The "Exhibit A" referred to in the agreement included the first page of Seneca's September 7 letter bid and a "Budgetary T & M Estimate Worksheet prepared for: Sheaffer Pen Plant Closure" ("worksheet").
The first page of the September 7 letter bid provided, in relevant part, as follows:
The "Vendor-Provided Sheaffer Closure/Clean-up Activities" document ("vendor-provided document") referenced in the bid was six pages in length. It included a detailed description of the work to be done and multiple references to the parties' expectation that most of the "rinsate"-washwater collected in the cleaning process-would be transferred to Sheaffer's on-site wastewater treatment facility for treatment and disposal. The contracting parties contemplated that a limited amount of the wastewater (4000 gallons) would be transported off-site and decontaminated by a third party, Heritage Environmental Services. The worksheet prepared by Seneca and referenced in both the letter bid and the written contract is a spreadsheet containing an estimate of the materials and labor needed to complete the cleaning of the facility. The estimate included the sum of $5,186, the cost of the off-site disposal of 4000 gallons by Heritage.
After the contract was executed and about the time Seneca began its work in November 2006, Sheaffer shut down its on-site wastewater treatment facility. Sheaffer directed Seneca to dispose of all wastewater through Heritage. Seneca complied with this directive, but neither Seneca nor Sheaffer requested a written modification to the contract.
On January 5, 2007, as it neared completion of the project, Seneca contacted Michele Pancza, Sheaffer's Environmental Manager, and indicated that it "may be approaching the 'not-to-exceed' price." Pancza communicated this information toother Sheaffer managers in an email message:
On January 15, 2007, Seneca's project manager sent an email message to Pancza summarizing the work left to be done and indicating that the work would be completed later that week. He noted that Seneca was "keeping an eye on the total costs of the project as we near our price cap."
Sheaffer paid Seneca $145,980.87 before receiving the final invoice. By the time Seneca completed its work under the contract, Heritage had treated and disposed of more than 18,000 gallons of wastewater, far in excess of the 4000 gallons contemplated in the estimate attached to Seneca's bid. Seneca submitted invoices to Sheaffer totaling $211,599.47. Sheaffer tendered to Seneca payment in the amount of $24,019.13 as the final payment on the contract, an amount that would have brought Sheaffer's total payments under the contract to $170,000. Seneca rejected the tender and filed suit seeking judgment for the full amount of its invoices.
Both parties moved for summary judgment. The district court granted Sheaffer's motion and dismissed Seneca's claim in its entirety, concluding Seneca was bound by the not-to-exceed price included in the contract. The court further concluded there were no written modifications to the contract which would have allowed Seneca to exceed the price cap. The court also rejected Seneca's contract claim for additional payment under the contract because Seneca's answers to interrogatories revealed the contractor's total billings for subcontracted services, including those provided by Heritage, were less than estimated by the contracting parties.
Seneca appealed, and we transferred the case to the court of appeals. The court of appeals reversed the district court, concluding that while the not-to-exceed clause was unambiguous, the summary judgment record-including documents fully integrated into the contract-engendered a genuine issue of material fact as to the amount owed by Sheaffer to Seneca under the contract. We granted Sheaffer's application for further review.
Iowa R. Civ. P. 1.981(3). If reasonable minds can differ on how an issue should be resolved, then a genuine issue of fact exists. Walderbach v. Archdiocese of Dubuque, Inc., 730 N.W.2d 198, 199 (Iowa 2007). A fact is material "only when...
To continue reading
Request your trial-
Iowa Supreme Court Attorney Disciplinary Bd. v. Morse
...for their appeal. This understanding superseded the general lien provision in the fee agreement. See Seneca Waste Sols., Inc. v. Sheaffer Mfg. Co., 791 N.W.2d 407, 412–13 (Iowa 2010) (discussing contract modification). We addressed attorney liens in Committee on Professional Ethics & Conduc......
-
Pitts v. Farm Bureau Life Ins. Co.
...judgment. “We review a district court's grant of a motion for summary judgment for errors of law.” Seneca Waste Solutions, Inc. v. Sheaffer Mfg. Co., 791 N.W.2d 407, 410–11 (Iowa 2010). A court should grant summary judgment “if the pleadings, depositions, answers to interrogatories, and adm......
-
Clasing v. Hormel Corp.
...of contract terms may be either express or implied from acts or conduct. See Seneca Waste Solutions, Inc. v. Sheaffer Mfg. Co., L.L.C., 791 N.W.2d 407, 413 (Iowa 2010) (citing Passehl Estate v. Passehl, 712 N.W.2d 408, 417 (Iowa 2006)). Iowa courts have long recognized that whether a contra......
-
Chi. Ins. Co. v. City of Council Bluffs
...Iowa 782, 203 N.W. 229, 230 (1925) and the rule that “a contract is to be interpreted as a whole,” Seneca Waste Solutions, Inc. v. Sheaffer Mfg. Co., LLC, 791 N.W.2d 407, 412 (Iowa 2010) (quoting Iowa Fuel & Minerals, Inc. v. Iowa State Bd. of Regents, 471 N.W.2d 859, 863 (Iowa 1991)). Addi......