Shaw v. Fjellman

Decision Date07 June 1898
Docket Number10,989 - (141)
Citation75 N.W. 705,72 Minn. 465
PartiesJULIUS H. SHAW and Another v. CHARLES FJELLMAN and Others
CourtMinnesota Supreme Court

Appeal by plaintiffs from an order of the district court for Hennepin county, Simpson, J., sustaining the separate demurrers of defendants Busch and Anheuser-Busch Brewing Association to the complaint. Reversed.

SYLLABUS

Contract for Heating Plant -- Guaranty to Maintain -- Repairs after Completion -- Filing of Lien Statement within 90 Days.

The contractor agreed to construct "a plumbing and heating plant" in the building, keep and maintain the plant in good order for one year after it was completed, and execute a written guaranty to that effect. In consideration thereof the owner of the property agreed to pay the contractor a certain sum at the end of such year. The latter performed the contract, and, in doing so, made repairs three times during such year after the plant was completed, the last time being on the last day of the year. The lien statement was filed within 90 days thereafter. Held, as against such owner, the contract is an entirety, and the lien statement was filed in time, although as against third parties acquiring rights in the property for value after the completion of the plant, and without actual notice or knowledge of the contract, it is not an entirety, and the lien statement is not filed in time.

Contract for Heating Plant -- Innocent Purchaser or Incumbrancer -- Burden of Proof.

But held, it does not appear that the respondents are innocent purchasers or incumbrancers for value, without notice.

Counsel cited Harrison v. Homeopathic, 134 Pa. St. 558; Berry v. Turner, 45 Wis. 105; Avery v. Butler, 30 Ore. 287; Flenniken v. Liscoe, 64 Minn. 269.

OPINION

CANTY, J.

This is an action to foreclose a mechanic's lien, and the question raised is whether the lien statement was filed within the statutory time.

The complaint alleges that the defendant Fjellman was the owner of the land on which he was erecting a building; that on March 30, 1895, he entered into an agreement with plaintiffs whereby it was agreed that they should furnish, place, and construct "a full and complete plumbing and heating plant" in the building, complete said plant in a good and workmanlike manner, "keep and maintain the same in good and perfect condition and running order for one year from the date of the completion" of the same and of its acceptance by Fjellman, and execute to him a written guaranty to that effect, and that, in consideration thereof, he agreed that at the end of such year, on the full performance by plaintiffs of said contract on their part, he would pay them the sum of $1,075; that plaintiffs commenced the construction of said plant March 31, 1895, and the same was completed December 31, 1895, and accepted by Fjellman January 10, 1896; that on the latter date plaintiffs executed a written guaranty pursuant to the contract, and, in performance and fulfilment of the same during the year in which said guaranty was in force, furnished labor and material rendered necessary in order to maintain the plant and keep it in repair; that said repairs were furnished January 8, 1896, November 19, 1896, and December 31, 1896, all of which are set out in a bill of particulars made a part of the complaint. The lien statement was filed March 13, 1897.

It is further alleged that the defendants Busch and Anheuser-Busch Brewing Association claim some interest in the property superior to the right of plaintiffs. These two defendants demurred to the complaint on the ground that it does not state a cause of action; and from an order sustaining the demurrer plaintiffs appeal.

The statute (G.S. 1894, § 6236) requires the lien statement to be filed within 90 days after the time of furnishing the last item of the labor or material, and respondents contend that in this case the lien statement was not filed within the 90 days; that, in order to preserve a lien for the labor and material furnished in constructing the plant, a lien statement therefor should have been filed within 90 days after the same was completed; and that the time for filing the lien statement for the same cannot be extended by reason of the labor and material furnished in maintaining the plant and keeping it in repair afterwards.

As against Fjellman, who made the contract, the lien statement was in our opinion filed in time. Of course, the stipulation for maintaining the plant for one year did not of itself extend the time for filing the lien. On the contrary, this...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT