Sierra Club v. Dominion Cove Point LNG, L.P.

Decision Date28 February 2014
Docket NumberNo. 2429,Sept. Term, 2012.,2429
Citation86 A.3d 82,216 Md.App. 322
PartiesSIERRA CLUB, et al. v. DOMINION COVE POINT LNG, L.P.
CourtCourt of Special Appeals of Maryland

OPINION TEXT STARTS HERE

JoAnne Spalding, San Francisco, CA (Craig Holt Segall, Sierra Club Environmental Law Program, Washington, D.C., Roy L. Mason, Annapolis, MD), all on the brief, for Appellant.

Christopher Handman & Mary Helen Wimberly, Washington, D.C. (David J. Hensler, Ellen S. Kennedy, Hogan Lovells US LLP, Washington, D.C., Robert H. Harvey, Jr., Prince Frederick, MD, Jefferson Wright, Katherine B. Hill, Joshua Gayfield, Miles and Stockbridge, PC, Baltimore, MD), on the brief, for Appellee.

Panel: MEREDITH, KEHOE and HOTTEN, JJ.*

HOTTEN, J.

The Sierra Club, a non-profit California corporation, and the Sierra Club Maryland Chapter (collectively the Sierra Club) bring this appeal in response to the circuit court's ruling in a declaratory judgment action filed by Dominion Cove Point LNG, L.P. (“Dominion”). The Sierra Club challenges Dominion's assertion that an agreement between the two restricting the use of Cove Point permits the exportation of natural gas. The Circuit Court for Calvert County found that the agreement was unambiguous and permitted Dominion to expand its operations to include exportation. The Sierra Club appealed and presents one question for our consideration:

Does the 2005 Agreement between Dominion, Sierra Club and [Maryland Conservation Counsel Inc.] allow Dominion to construct LNG export facilities at the Cove Point site even though export is not included on the list of authorized activities under the Agreement?

For the reasons that follow, we shall affirm the judgment of the circuit court.

FACTUAL AND PROCEDURAL HISTORY

Columbia Gas was Dominion's predecessor in ownership of a 1,017 acre parcel of land in Maryland located at, and referred to as, Cove Point. In 1972, Columbia Gas began to construct a liquid natural gas (“LNG”) import terminal on a portion of the land. Natural gas 1 is liquified in order to transport it because in its gaseous state, it takes up 600 times as much space as LNG. At this time, it was necessary to transport natural gas because it was only available if imported from foreign nations. In 1978, after interested parties expressed concern regarding potential harm to the environment, Columbia Gas, the Sierra Club and the Maryland Conservation Counsel Inc. (“MCC”) entered into an agreement regarding the use of Cove Point. After the 1978 agreement went into effect, Columbia Gas began importing LNG at Cove Point, but suspended operations in 1980. In 1994, Columbia Gas desired to reopen Cove Point to add new “peaking” services. Peaking is a service that allows energy providers to store natural gas for future use by utility companies during peak energy use time periods. Providing peaking services would require Colombia Gas to construct liquification capabilities at the Cove Point facility. The three parties negotiated a new agreement, granting Columbia Gas the ability to liquefy, store and regasify natural gas. In 2002, Dominion purchased Cove Point from Columbia Gas.

2005 Agreement

Between 1994 and 2005, Cove Point was used only to import natural gas and for peaking services. However, in 2005, Dominion sought to expand its Cove Point operations to meet rising domestic natural gas demand. As a result, Dominion, Sierra Club and MCC negotiated a new agreement. It was agreed that the 2005 Agreement would replace in its entirety all previous agreements and understandings regarding use of Cove Point. The agreement provides that Dominion may use the area designated as the LNG Terminal Site solely to perform “LNG Terminal Operations.” Within the Terminal Site, there is an area identified as the Fenced Area, which is where the natural gas tanks are located. The 2005 Agreement defines LNG Terminal Operations as:

LNG Terminal Operations means and is limited to any use or activity related to (i) the construction, operation or maintenance of facilities and equipment associated with the following activities (a) through (j): (a) marine operations involving the importing of LNG; (b) the liquefaction of natural gas; (c) the storage of LNG in tanks; (d) the regasification of LNG; (e) the receipt by tanker and the receipt or delivery by pipeline of LNG, revaporized LNG or natural gas at or from the LNG Terminal Site; (f) the treatment of LNG or revaporized LNG by nitrogen injection or the separation and removal of constituent parts; (g) the provisioning of LNG tankers with water and miscellaneous supplies, provided that the principal method of provisioning LNG tankers shall be by means of shipments of materials and supplies from locations other than the Cove Point Site to the off-shore pier for storage and transfer to LNG tankers docked at the off-shore pier; (h) the recovery and use on the LNG Terminal Site for other LNG Terminal Operations of the cryogenic properties of LNG; (i) the recovery and use on the LNG Terminal Site of waste heat for other LNG Terminal Operations; (j) the generation or cogeneration of electricity within the limitations prescribed herein; and (ii) the construction, operation or maintenance of facilities and equipment directly supporting the foregoing activities (a) through (j), including office buildings, warehouses, maintenance shops, firefighting equipment and utilities.

As discussed more fully, infra, the 2005 Agreement provides for other rules regarding what operations may be performed and in some instances, explicitly prohibits other activities.

Dominion's Proposed Export Project

Since 2005, the domestic natural gas market has changed dramatically. A new procedure known as hydraulic fracturing (“fracking”) has unlocked vast new supplies of natural gas in the United States. Fracking is a process by which gas companiesdrill into layers of shale rock and extract gas reserves from within the rock.2

In response to the new fracking developments, in 2011, Dominion announced plans to expand its Cove Point operations in order to add new export capabilities. Dominion applied to the Federal Energy Regulatory Commission (“FERC”) to obtain permission to construct and operate the exporting facilities. It also sought approval from the federal Department of Energy to export natural gas to foreign countries.

Unlike the practice followed in prior instances of negotiating agreements prior to seeking approval of expansion, Dominion did not approach Sierra Club until several months after it sought federal approval. Sierra Club filed comments protesting the proposed expansion. Dominion then approached the Sierra Club and MCC, as required by the 2005 Agreement, to seek approval for the project. During discussions, the Sierra Club expressed that it did not intend to approve the proposed expansion.3 As a result, Dominion revised its plans and proposed to construct new facilities outside of the Terminal Operations area that is subject to the 2005 Agreement. The Sierra Club then asserted that the 2005 Agreement does not authorize LNG to be exported from the Terminal Site. Dominion thereafter filed an action for declaratory judgment against Sierra Club and MCC in the circuit court.

Circuit Court Proceedings

In the circuit court, the parties filed cross motions for summary judgment. Dominion sought judgment confirming its right to construct new liquefaction facilities within the Fenced Area and its right to transfer LNG from Cove Point to the offshore pier. The Sierra Club argued that the 2005 Agreement does not authorize Dominion to export LNG from the Cove Point facility because the Agreement “limits Dominion to an exclusive list of enumerated activities at Cove Point, and export of LNG is not authorized by that list.”

Following a hearing on the cross motions, the circuit court issued an opinion and order in favor of Dominion. The circuit court reasoned:

In my opinion, subsection (e) of Section 1.01 of the Agreement unambiguously does give Dominion the right to use the Cove Point Facility for the export of LNG. Excluding unnecessary words, subsection (e) of Section 1.1 allows Dominion to carry on activities related to (e) the receipt by tanker and the receipt or delivery by pipeline of LNG, revaporized LNG, or natural gas at or from the LNG Terminal Site ....

To export LNG, Dominion will be transferring the LNG produced by the new liquification facilities by pipeline from the LNG Terminal Site to tankers docked at the offshore pier. From there, the LNG will be shipped to customers in other countries. Subparagraph (e) expressly permits the facility to be used for “receipt by tanker of LNG ... from the Terminal Site.” The Agreement specifically allows for “the delivery by pipeline of LNG from the LNG Terminal Site.” This plainly allows the tankers at the pier to receive LNG from the Terminal Site.

In its summary judgment, the Sierra Club, in various ways, attempts to circumventthe plain language of subsection (e). For the reasons set forth in Dominion's opposition to the Sierra Club's motion, I do not find that any of those arguments are persuasive.

The court ordered that the new liquefaction facilities could be built within the Fenced Area and that Dominion could export LNG from the Terminal Site to the offshore pier. Sierra Club noted a timely appeal. MCC did not join in the appeal.

Additional facts shall be provided, infra, to the extent they prove relevant in addressing the issue presented.

STANDARD OF REVIEW

Summary judgment is proper where the circuit court determines that there are no genuine disputes as to any material fact and that the moving party is entitled to judgment as matter of law. SeeMd. Rule 2–501. Disputes concerning contract interpretation are questions of law and frequently regarded as appropriate for summary judgment. See Sandler v. Executive Mgmt. Plus, 203 Md.App. 399, 423, 38 A.3d 478 (2012) (noting that contract interpretation is a question of law). See also Bank of Montreal v. Signet Bank, 193 F.3d...

To continue reading

Request your trial
33 cases
  • Accokeek, Mattawoman, Piscataway Creeks Cmtys. Council, Inc. v. Md. Pub. Serv. Comm'n
    • United States
    • Court of Special Appeals of Maryland
    • 30 Marzo 2016
    ...COSTS TO BE PAID BY APPELLANT.1 For more details about the history of the Cove Point terminal, see Sierra Club v. Dominion Cove Point LNG, L.P., 216 Md.App. 322, 325–29, 86 A.3d 82 (2014).2 The liquefaction process involves cooling natural gas to approximately negative 260 degrees Fahrenhei......
  • May v. Air & Liquid Sys. Corp.
    • United States
    • Court of Special Appeals of Maryland
    • 3 Octubre 2014
    ...Seaboard Sur. Co. v. Richard F. Kline, Inc., 91 Md.App. 236, 244, 603 A.2d 1357 (1992) ; accord Sierra Club v. Dominion Cove Point LNG, L.P., 216 Md.App. 322, 330, 86 A.3d 82, cert. denied, 438 Md. 741, 93 A.3d 289 (2014). Thus, a court must view the facts, and all reasonable inferences tha......
  • De Landaverde v. Navarro
    • United States
    • Court of Special Appeals of Maryland
    • 26 Julio 2018
    ...judgment as a matter of law. Rowhouses , Inc. v. Smith , 446 Md. 611, 630-31, 133 A.3d 1054 (2016) ; Sierra Club v. Dominion Cove Point LNG , L.P. , 216 Md. App. 322, 330, 86 A.3d 82 (2014). We consider the record " 'in the light most favorable to the non-moving party,' " drawing any reason......
  • Jos. A. Bank Clothiers, Inc. v. J.a.b.-Columbia, Inc., Civil Action No. ELH-15-3075
    • United States
    • U.S. District Court — District of Maryland
    • 15 Diciembre 2017
    ...(1999). Notably, a contract is not ambiguous merely because the parties disagree as to its meaning, Sierra Club v. Dominion Cove Point LNG, L.P., 216 Md. App. 322, 334, 86 A.3d 82, 89 (2014), or "simply because, in litigation, the parties offer different meanings to the language." Diamond P......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT