Sigmon Fuel Co. v. Tennessee Valley Authority

Decision Date04 February 1985
Docket Number83-5843,Nos. 83-5700,s. 83-5700
Citation754 F.2d 162
Parties32 Cont.Cas.Fed. (CCH) 73,260 SIGMON FUEL COMPANY, Plaintiff-Appellant v. TENNESSEE VALLEY AUTHORITY, Defendant-Appellee.
CourtU.S. Court of Appeals — Sixth Circuit

William G. Cockrill (argued), McCord & Cockrill, Knoxville, Tenn., for plaintiff-appellant.

Herbert S. Sanger, Jr., Gen. Counsel, Tennessee Valley Authority, James E. Fox, Assoc. Gen. Counsel, Robert C. Glinski, Edwin W. Small (argued), Knoxville, Tenn., for defendant-appellee.

Before MARTIN and CONTIE, Circuit Judges, and CELEBREZZE, Senior Circuit Judge.

CONTIE, Circuit Judge.

Sigmon Fuel Company appeals the district court orders denying Sigmon's motions for prejudgment interest pursuant to the Contract Disputes Act, 41 U.S.C. Secs. 601-613, and attorneys' fees pursuant to the Equal Access to Justice Act, 28 U.S.C. Sec. 2412. For the reasons that follow, we affirm.

I.

On June 5, 1978, the Tennessee Valley Authority (TVA) entered into a coal contract with J.L. Thacker, Inc. under which Thacker agreed to perform reclamation to TVA's satisfaction. The contract price of the coal included an amount to cover Thacker's reclamation costs. On July 7, 1978, Thacker assigned its right to proceeds under the contract to Sigmon Fuel and TVA approved the assignment. Thacker presented invoices for the coal to Sigmon Fuel which then advanced money to Thacker. TVA subsequently made payment directly to Sigmon Fuel on the invoices.

In May 1980, TVA determined that Thacker's reclamation work was inadequate and refused to pay for coal shipped in November 1979. On September 15, 1981, Sigmon Fuel filed a complaint seeking to recover the proceeds due on the invoices pursuant to the Assignment of Claims Act of 1940, 31 U.S.C. Sec. 203 and 41 U.S.C. Sec. 15. The district court granted TVA's motion for summary judgment, 531 F.Supp. 80, but this court reversed the order of the district court and ordered that summary judgment be entered in favor of Sigmon Fuel. 709 F.2d 440. After the district court entered judgment, Sigmon Fuel moved that the judgment be amended to include an award of $77,233.90 in prejudgment interest and $15,164.41 in attorneys' fees. The district court denied both motions, and Sigmon Fuel appealed.

II.

Sigmon Fuel's motion for prejudgment interest cited as support the Prompt Payment Act of 1982, 31 U.S.C. Secs. 3901-3906, the Contract Disputes Act, and "other applicable law." The district court determined that the provisions of the Prompt Payment Act were not available to Sigmon Fuel since the Act only applies to claims under contracts executed on or after October 1, 1982, and Sigmon Fuel does not challenge this determination on appeal. The district court also determined that Sigmon Fuel could not recover interest pursuant to the Contract Disputes Act since Sigmon was not a "contractor" as defined by 41 U.S.C. Sec. 601(4) and that the Act's provision for interest, 41 U.S.C. Sec. 611, only applied to claims brought under the Act. On appeal, Sigmon contends that the Contract Disputes Act and federal common law require an award of prejudgment interest.

A.

Sigmon's contention that federal common law authorizes an award of interest was not presented to the district court nor did the district court consider such contention. Sigmon's reference to "other applicable law" does not squarely present the argument that Sigmon was entitled to interest pursuant to federal common law. In the interests of judicial economy and the finality of judgments, and mindful of our role as an appellate court, we have declined to review arguments not presented to the district court in the first instance. In re White Motor Corp., 731 F.2d 372, 375 (6th Cir.1984); American Meat Institute v Pridgeon, 724 F.2d 45, 46 (6th Cir.1984); Lyle v. Koehler, 720 F.2d 426, 428-29 (6th Cir.1983); Brown v. Marshall, 704 F.2d 333, 334 (6th Cir.), cert. denied, --- U.S. ----, 104 S.Ct. 120, 78 L.Ed.2d 119 (1983); Wolfel v. Sanborn, 666 F.2d 1005, 1007 (6th Cir.1981), cert. denied, 459 U.S. 1115, 103 S.Ct. 751, 74 L.Ed.2d 969 (1983); Bannert v. American Can Company, 525 F.2d 104, 111 (6th Cir.1975), cert. denied, 426 U.S. 942, 96 S.Ct. 2662, 49 L.Ed.2d 394 (1976). Therefore, since Sigmon Fuel failed to press its entitlement to interest under federal common law before the district court, we do not consider that argument on appeal.

B.

Sigmon challenges the district court's determination that Sigmon was not entitled to recover interest pursuant to the Contract Disputes Act because Sigmon was not a "contractor" covered by the Act. 1 41 U.S.C. Sec. 611 provides in pertinent part:

Interest on amounts found due contractors on claims shall be paid to the contractor from the date the contracting officer receives the claim pursuant to section 605(a) of this title from the contractor until payment thereof.

However, 41 U.S.C. Sec. 611 only applies where the "contractor" has elected to proceed under the Act. Paragon Energy Corp. v. United States, 645 F.2d 966, 971 n. 7, 227 Ct.Cl. 176 (1981). See Monroe M. Tapper & Associates v. United States, 611 F.2d 354, 357, 222 Ct.Cl. 34 (1979). Section 16 of the Act provides:

This Act shall apply to contracts entered into one hundred twenty days after the date of enactment. Notwithstanding any provision in a contract made before the effective date of this Act, the contractor may elect to proceed under this Act with respect to any claim pending then before the contracting officer or initiated thereafter.

Pub.L. No. 95-563 Sec. 16. The Act was enacted on November 1, 1978, and applies to all contracts entered into after March 1, 1979. Therefore, even if Sigmon is a "contractor", the Act is applicable only if Sigmon elected to proceed under the Act.

Sigmon never filed a claim in this case as required by 41 U.S.C. Sec. 605(a) but attempted to intervene in the administrative proceeding between Thacker and TVA regarding TVA's termination of the coal contract due to inadequate reclamation. Sigmon's motion to intervene was denied by the TVA Board of Contract Appeals on the ground that Sigmon was not a "contractor" within 41 U.S.C. Sec. 601(4) which defines a "contractor" as "a party to a Government contract other than the Government." Sigmon did not appeal the decision of the board of contract appeals. 2

The Contract Disputes Act is a waiver of sovereign immunity, and must, therefore, be strictly construed. Erickson Air Crane Co. of Washington, Inc. v. United States, 731 F.2d 810, 813 (Fed.Cir.1984) ("The government consents to be sued only by those with whom it has privity of contract."); Fidelity Construction Company v. United States, 700 F.2d 1379, 1383 (Fed.Cir.), cert. denied, --- U.S. ----, 104 S.Ct. 97, 78 L.Ed.2d 103 (1983). See United States v. New York Rayon Importing Co., 329 U.S. 654, 658-59, 67 S.Ct. 601, 603-04, 91 L.Ed. 577 (1947); Rawlins v. United States, 686 F.2d 903, 914 (Ct.Cl.1982). Sigmon's decision to proceed by a direct action in district court, rather than to appeal the decision of the TVA Board of Contract Appeals constitutes an election not to proceed under the Act. Therefore Sigmon is not entitled to an award of prejudgment interest as provided by 41 U.S.C. Sec. 611. 3

III.

The district court denied Sigmon's application for attorneys' fees on the ground that TVA's position in the case was substantially justified. 28 U.S.C. Sec. 2412(d)(1)(A) provides:

Except as otherwise specifically provided by statute, a court shall award to a prevailing party other than the United States fees and other expenses, in addition to any costs awarded pursuant to subsection (a), incurred by that party in any civil action (other than cases sounding in tort) brought by or against the United States in any court having jurisdiction of that action, unless the court finds that the position of the United States was substantially justified or that special circumstances make an award unjust. 4

A party that prevails in a case is entitled to attorneys' fees, Bittner v. Sadoff & Rudoy Industries, 728 F.2d 820, 830 (7th Cir.1984); Ramos v. Haig, 716 F.2d 471, 473 n. 3 (7th Cir.1983), unless the government shows that its position was substantially justified. Ferrell v. Pierce, 743 F.2d 454, 466 (7th Cir.1984); Timms v. United States, 742 F.2d 489, 492 (9th Cir.1984); United States v. 341.45 Acres of Land, 741 F.2d 1034, 1049 (8th Cir.1984); Nichols v. Pierce, 740 F.2d 1249, 1259 (D.C.Cir.1984); Blitz v. Donovan, 740 F.2d 1241, 1244 (D.C.Cir.1984); Ashburn v. United States, 740 F.2d 843, 850 (11th Cir.1984); Berman v. Schweiker, 713 F.2d 1290, 1293 n. 9 (7th Cir.1983); Howard v. Heckler, 581 F.Supp. 1231, 1233 (S.D.Ohio 1984). Whether or not the government's position is substantially justified is judged by the reasonableness of the government's position. 5 Wyandotte Savings Bank v. NLRB, 682 F.2d 119, 120 (6th Cir.1982). See Washington Urban League v. FERC, 743 F.2d 166, 168 (3rd Cir.1984); Timms, 742 F.2d at 492; 341.45 Acres of Land, 741 F.2d at 1049; Ashburn, 740 F.2d at 850; Ramos v. Haig, 716 F.2d at 473; Citizens Coalition for Block Grant Compliance v. City of Euclid, 537 F.Supp. 422, 426 (N.D.Ohio 1982), aff'd, 717 F.2d 964 (6th Cir.1983). H.R.Rep. No. 96-1418, 96th Cong., 2d Sess. 10, reprinted in 1980 U.S.Code Cong. & Ad.News 4953, 4984. "The government must therefore show that there is a reasonable basis in truth for the facts alleged in the pleadings; that there exists a reasonable basis in law for the theory it propounds and that the facts alleged will reasonably support the legal theory advanced." United States v. 2,116 Boxes of Boned Beef, 726 F.2d 1481, 1487 (10th Cir.1984).

This court has recently held that the proper standard of review in this type of case is whether the district court abused its discretion. Westerman, Inc. v. NLRB, 749 F.2d 14 at 17 (6th Cir.1984). In this context, however, the term "abuse of discretion" takes on a special meaning. Spencer...

To continue reading

Request your trial
89 cases
  • Milan Exp. Co., Inc. v. Western Sur. Co.
    • United States
    • U.S. Court of Appeals — Sixth Circuit
    • 22 Septiembre 1989
    ...1352 issue in the district court, this court will not address the issue, for the first time, on appeal. See, e.g., Sigmon Fuel Co. v. TVA, 754 F.2d 162, 164-65 (6th Cir.1985) (explaining that courts of appeals generally refuse to consider issues not passed upon by district courts).Plaintiff......
  • U.S. v. Marion L. Kincaid Trust
    • United States
    • U.S. District Court — Eastern District of Michigan
    • 3 Noviembre 2006
    ...the government has the burden of proof in establishing that its position was "substantially justified." Sigmon Fuel Co. v. Tennessee Valley Auth., 754 F.2d 162, 166 (6th Cir.1985) (citing Berman v. Schweiker, 713 F.2d 1290, 1293 n. 9 (7th Cir.1983)). "Substantial justification" is found whe......
  • Barna v. Bd. of Sch. Dirs. of the Panther Valley Sch. Dist.
    • United States
    • U.S. Court of Appeals — Third Circuit
    • 7 Diciembre 2017
    ...counsel to their strategic choices. See Wheatley v. Wicomico Cty., 390 F.3d 328, 334–35 (4th Cir. 2004) ; Sigmon Fuel Co. v. Tenn. Valley Auth., 754 F.2d 162, 164 (6th Cir. 1985). Accordingly, once parties choose their arguments, they may only pursue those arguments. See Fleishman v. Cont'l......
  • Pierce v. Underwood, 86-1512
    • United States
    • U.S. Supreme Court
    • 27 Junio 1988
    ...Inc. v. United States, 757 F.2d 247, 252-253 (CA Fed.1985); Hicks v. Heckler, 756 F.2d 1022, 1024-1025 (CA4 1985); Sigmon Fuel Co. v. TVA, 754 F.2d 162, 167 (CA6 1985); Boudin v. Thomas, 732 F.2d 1107, 1117 (CA2 1984); United States v. 2,116 Boxes of Boned Beef, 726 F.2d 1481, 1486 (CA10), ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT