Monroe M. Tapper & Associates v. US

Citation611 F.2d 354
Decision Date12 December 1979
Docket NumberNo. 329-70.,329-70.
PartiesMONROE M. TAPPER & ASSOCIATES v. The UNITED STATES.
CourtU.S. Claims Court

COPYRIGHT MATERIAL OMITTED

F. Trowbridge vom Baur, Washington, D.C., attorney of record for plaintiff. W. Bruce Shirk, Washington, D.C., for counsel.

R. W. Koskinen, Washington, D.C., with whom was Acting Asst. Atty. Gen., Alice Daniel, Washington, D.C., for defendant.

Before COWEN, Senior Judge, and KUNZIG and SMITH, Judges.

OPINION

KUNZIG, Judge:

This is yet another opinion on plaintiff's claim involving the construction and lease of a Post Office facility in Worchester, Massachusetts.1 After originally filing the claim with the contracting officer in November 1968 plaintiff at last prevailed on the merits and was awarded $26,805.94 by decision of this court dated July 18, 1979, Monroe M. Tapper & Associates v. United States, 602 F.2d 311, 221 Ct.Ct. ___ (1979). Now plaintiff requests interest on its claim from November 1968 until the date of judgment in July 1979, arguing its action falls under the Contract Disputes Act of 1978, Pub.L. No. 95-563, 92 Stat. 23832 (hereinafter "Act" or "Contract Disputes Act") and the interest provisions thereof. For the reasons discussed below we conclude plaintiff, under these circumstances, may not proceed under the Act. Plaintiff's claim for interest must therefore be denied.3

The facts pertinent to plaintiff's request for interest are as follows. In June 1968, plaintiff entered into a contract with defendant for the construction and lease of a Post Office facility in Worchester, Massachusetts. The contract contained the usual Disputes provision (General Provision 12) which gave plaintiff a 30-day period within which to appeal in writing to the Postmaster General a final decision of the contracting officer rendered on a dispute arising under the contract.4

During construction of the facility a controversy arose in September 1968 as to whether the contract specifications permitted the use of earth as opposed to gravel for backfilling utility line trenches. In a letter dated December 23, 1968, the contracting officer notified plaintiff that the specifications required the use of gravel in backfilling the trenches. This letter stated it was "a final decision pursuant to the Disputes Clause of the General Conditions" and was to be "final and conclusive" unless an appeal was effected within 30 days.

Plaintiff persisted in appealing the contracting officer's decision and through differing problems eventually required three separate opinions of this court, it was determined the specifications permitted the use of earth for backfilling utility line trenches and plaintiff was awarded $26,805.94 because defendant had insisted upon the use of gravel.

Plaintiff's motion now before the court seeks to recover interest on the $26,805.94 judgment from the date of the contracting officer's final decision of December 1968 refusing plaintiff's claim. Plaintiff's interest claim, however, must overcome the "ancient doctrine"5 based upon 28 U.S.C. § 2516(a),6 that "interest cannot be recovered against the United States upon unpaid accounts or claims in the absence of an express provision to the contrary in a relevant statute or contract." United States v. Thayer-West Point Hotel Co., 329 U.S. 585, 588, 67 S.Ct. 398, 399, 91 L.Ed. 521 (1947); Cleveland Chair Co. v. United States, 557 F.2d 244, 214 Ct.Cl. 360 (1977). The rule, of course, applies to awards in contract disputes, Poorvu v. United States, 420 F.2d 993, 1004, 190 Ct.Cl. 640, 658 (1970) (Post Office facility construction); Algonac Mfg. Co. v. United States, 428 F.2d 1241, 192 Ct.Cl. 649 (1970); Mar-Pak Corp. v. United States, 203 Ct.Cl. 718, 720 (1973); see Framlau Corp. v. United States, 568 F.2d 687, 694, 215 Ct.Cl. 185, 197 (1977).

Evidently unable to invoke a clause in its contract to support an interest request, plaintiff argues its claim falls within the Contract Disputes Act of 1978 and the provision for the payment of interest on contractors' claims contained in section 12.7 The problem then is whether plaintiff's claim comes within the effective date of the Act. Section 16 of the Act, headed "Effective Date of Act," states:

Sec. 16. This Act shall apply to contracts entered into one hundred twenty days after the date of enactment. Notwithstanding any provision in a contract made before the effective date of this Act, the contractor may elect to proceed under this Act with respect to any claim pending then before the contracting officer or initiated thereafter.

The Contract Disputes Act was enacted on November 1, 1978, and pursuant to the above section had an effective date of March 1, 1979. Because the contract on which plaintiff sues was entered into in June 1968, plaintiff's claim would appear to be ineligible for coverage under the Act and its interest provisions. Yet plaintiff contends it is "electing to proceed" under the Act; plaintiff allegedly has this option because its claim, though the contracting officer rendered a final decision thereon on December 23, 1968, was nevertheless (it argues) "pending before" the contracting officer on the effective date of the Act.

To specify the question before the court, it is whether plaintiff's claim for extra costs incurred by using gravel instead of earth for utility line backfill was "pending before the contracting officer" on the effective date of the Contract Disputes Act of 1978, which was March 1, 1979.8 As noted, plaintiff's claim was rejected by a final decision of the contracting officer on December 23, 1968, appealed to the then Post Office Department Board of Contract Appeals and later to this court. Our decision in Troup Bros. Inc. v. United States, Ct.Cl. No. 64-79, (order filed Aug. 24, 1979) and the language and legislative history of the Contract Disputes Act compel our conclusion that plaintiff's claim was not pending before the contracting officer on the Act's effective date.

Plaintiff in Troup Bros. had liquidated damages assessed against it under a contract for flood control facility construction with the Army Corps of Engineers. The contract was entered into on December 19, 1975, and on January 8, 1979, the contracting officer upheld the assessment in a final decision. Plaintiff in Troup Bros. sought to appeal the contracting officer's decision directly to this court by utilizing section 10(a)(1) of the Contract Disputes Act which permits such direct access, giving a contractor a right to a de novo proceeding in this court. The question was whether the Contract Disputes Act applied to plaintiff's claim. Rejecting plaintiff's contentions, the court recognized that the contracting officer's final decision had been rendered two months before the Act's effective date of March 1, 1979. Therefore, "Since the contracting officer rendered his final decision before the effective date of the Act, the claim at issue was not pending before him on the date the Act became effective nor was it initiated thereafter."9

Troup Bros. announced a straightforward principle which applies to this case. Once a contracting officer has rendered a final decision on a claim, that claim is no longer pending before the officer within the meaning of section 16 of the Contract Disputes Act of 1978. Plaintiff herein argues Troup Bros. is not applicable to this case because it did not deal with a question of interest. The common determinative issue in this case and in Troup Bros. is whether a claim which has been the subject of a contracting officer's final decision was pending before the contracting officer on the Act's effective date. Plaintiff does not suggest the concept of "pending before the contracting officer" should mean one thing when applying section 10(a)(1) of the Act (as in Troup Bros.) and another when applying the Act's interest provisions contained in section 12, nor could we accept such a distinction as tenable. And contrary to plaintiff's assertion, the issue of when a claim is pending before a contracting officer was fully addressed in Troup Bros. That decision guides us now.

Examination of the language and legislative history of the Contract Disputes Act confirms this result. In S.Rep. No. 95-1118, 95th Cong., 2d Sess., reprinted in 1978 U.S.Code Cong. & Admin.News, p. 5235, section 16 of the Contract Disputes Act, "Effective Date of Act," was discussed. The Senate Report commented, inter alia:

The contractor may elect to proceed under this act with respect to any claims pending then before the contracting officer or initiated thereafter. It is not intended that upon the effective date of this act, a claim currently before an agency board can be switched to a court under this act's provisions.

Thus a contractor may proceed under the Act and file suit directly in the Court of Claims with respect to a claim pending before the contracting officer on the effective date of the Act. But the language of the Senate Report explicitly prevents a claim which is before an agency board (that is, one which has been the subject of a contracting officer's final decision) from being switched to the Court of Claims under the Act's provisions. The evident intent of Congress was not to consider a claim which has been the subject of a contracting officer's decision and is on appeal to an agency board as still "pending" before the contracting officer, for the Act permits contractors with claims which are only pending before a contracting officer to proceed in court, yet prohibits such switching if the contracting officer's final decision is on appeal to a board. Again we can see no reason why the meaning of "pending before the contracting officer" should be interpreted differently when determining the applicability of the Act's interest provisions than it is when determining a contractor's right of direct access.

We also believe the plain language of the Act (and the language of the Disputes provision in plaintiff's contract) militates against...

To continue reading

Request your trial
14 cases
  • Sigmon Fuel Co. v. Tennessee Valley Authority
    • United States
    • U.S. Court of Appeals — Sixth Circuit
    • February 4, 1985
    ...the Act. Paragon Energy Corp. v. United States, 645 F.2d 966, 971 n. 7, 227 Ct.Cl. 176 (1981). See Monroe M. Tapper & Associates v. United States, 611 F.2d 354, 357, 222 Ct.Cl. 34 (1979). Section 16 of the Act This Act shall apply to contracts entered into one hundred twenty days after the ......
  • Dewey Electronics Corp. v. U.S.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • October 1, 1986
    ...before the contracting officer." 11 The Nab-Lord decision relied on the prior decision of the court in Monroe M. Tapper & Associates v. United States, 611 F.2d 354, 222 Ct.Cl. 34 (1979). There the court articulated that the evident intent of Congress was "not to consider a claim which has b......
  • BROOKFIELD CONST. CO., INC. v. United States, 555-79C.
    • United States
    • U.S. Claims Court
    • September 23, 1981
    ...Congress wanted to remedy any pre-Act injustice stemming from inability to recover interest. See Monroe M. Tapper & Assoc. v. United States, 222 Ct.Cl. 34, ___, 611 F.2d 354, 360 (1979). This is therefore not a case in which the statutory purpose definitely extends to past transactions as w......
  • Maryland Port Administration v. C. J. Langenfelder & Son, Inc.
    • United States
    • Court of Special Appeals of Maryland
    • January 11, 1982
    ...States, supra; Blackhawk Heating & Plumbing Co., Inc. v. United States, 622 F.2d 539 (Ct.Cl.1980); and cf. Monroe M. Trapper & Associates v. United States, 611 F.2d 354 (Ct.Cl.1979), and Everett Plywood Corporation v. United States, 651 F.2d 723 Maryland has no counterpart to either of the ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT