Sloane v. Malcolm Price, Inc.

Decision Date30 May 1975
Docket NumberNo. 8794.,8794.
Citation339 A.2d 43
PartiesMartin E. SLOANE et ux., Appellants, v. MALCOLM PRICE, INC., Appellee.
CourtD.C. Court of Appeals

David Melincoff, Washington, D. C., argued for appellants, DeLancey W. Davis and Donald B. Robertson, Washington, D. C., were on the briefs for appellants.

Bardyl R. Tirana, Washington, D. C., for appellee.

Before REILLY, Chief Judge, and KERN and HARRIS, Associate Judges.

HARRIS, Associate Judge:

The disagreement between the parties over a home improvement contract is before the court for the second time. See Malcolm Price, Inc. v. Sloane, D.C.App., 308 A.2d 779 (1973). Mr. and Mrs. Sloane now appeal from a judgment (as amended) to enforce the mechanic's lien of Malcolm Price, Inc. We affirm.

Appellants and appellee contracted in February of 1971 for the renovation of the Sloanes' basement. The agreement called for the Sloanes to pay Price's costs plus 25 percent. The total contract price was estimated to be between $6,850 and $7,850 (including a new boiler). Work began in March. As work progressed, Price submitted two unitemized bills which were paid by the Sloanes. By mid-May, however, the estimated total cost to attain completion of the project had nearly doubled due to increased costs and changes in the original plans.

The Sloanes disputed the higher costs. In response, Price ceased work and submitted a third (this time itemized) requisition. Appellants refused to make further payment. Both parties engaged counsel, who undertook negotiations in an effort to reach a compromise on the amounts due and to arrange for completion of the project. The negotiations formally were broken off on September 13. On November 4, Price filed a notice of a mechanic's lien pursuant to D.C.Code 1973, § 38-102.

Price later sought enforcement of its lien in Superior Court. The Sloanes contended that Price had permitted more than 90 days to elapse after abandoning work, thereby defeating appellee's statutory right to file a mechanic's lien. Appellants' summary judgment motion was granted on that ground. We reversed, holding that summary judgment was inappropriate since the actual date of abandonment was a material factual issue as to which there was a genuine dispute. Malcom Price, Inc. v. Sloane, supra.

A trial was held on remand. The court found, inter alia, (1) that there was a valid cost-plus contract; (2) that the contract included cost estimates but did not guarantee a maximum cost range for the work to be performed; (3) that "abandonment" of work by appellee did not occur prior to September 13, 1971 (thus marking the beginning of the three months provided for filing a mechanic's lien); and (4) that appellee was entitled to enforcement of the lien.

As to the Sloanes' claim that abandonment occurred well before September 13, we find no cause to disturb the trial court's finding. The date of an abandonment, as reflected by our prior decision, is a question of fact dependent on more than the mere cessation of work. See Malcolm Price, Inc. v. Sloane, supra, 308 A.2d at 780. The record shows that between May and September the parties were engaged in efforts (through counsel) to resolve their differences and fulfill their respective obligations under the contract. There is substantial support in the record for the trial court's finding that no abandonment occurred prior to the termination of the mutual efforts to compromise. See D.C.Code 1973, § 17-305.

The Sloanes also claim that the court erred in failing to determine the reasonableness of Price's costs, and in failing to rule that Price had the burden of proving their reasonableness. We disagree for several reasons. First, the suit arises from a claim to enforce a statutory mechanic's lien, and is not a suit on the underlying contract. See generally Fidelity Storage Corp. v. Trussed Concrete Steel Co., 35 App.D.C. 1, 9, 12-13 (1910), appeal dismissed, 325 U.S. 716, 32 S.Ct. 836, 56 L.Ed. 1270 (1911). Although such a lien may be founded on a contract, the right to the lien arises immediately when labor is performed or materials are furnished, or both, as a consequence of which value is added to the structure involved. Ibid.; D.C.Code 1973, § 38-101.1 Only if it is claimed in defense that the labor or materials were not in fact provided, or were defective, may an obligor attempt to defeat a mechanic's lien. See Davis v. Alvord, 94 U.S. 545, 24 L.Ed. 283 (1877). The Sloanes make no claim that the work was not done or the materials were not furnished. To support its claim, Price described the work done and the materials used in the renovation of the basement, and set forth the charge for each element item-by-item. In the face of no demurrer to Price's showing of its performance, a lien properly arose. See, e. g., Bangor Roofing & Sheet Metal Co. v. Robbins Plumbing Co., 151 Me. 145, 116 A.2d 664, 665 (1955); cf. House v. Fissell, 188 Md. 160, 51 A.2d 669, 671 (1947).

Once a lien arises, § 38-101 operates to prescribe the amount thereof. Where the lien arises from work performed pursuant to a valid contract, where there is no dispute over the fact that labor and materials have been expended on and to the benefit of the building in accordance with the contract, and where no expenditure is challenged...

To continue reading

Request your trial
4 cases
  • McBride v. Pizza Hut, Inc.
    • United States
    • D.C. Court of Appeals
    • May 15, 1995
    ...issues must be resolved in favor of the non-moving party. See Malcolm Price, Inc. v. Sloan, 308 A.2d 779, 780 (D.C. 1973), aff'd., 339 A.2d 43 (D.C.1975). In his complaint, appellant alleged defamation and injurious falsehood on the basis of Pizza Hut's statement to DOES that appellant had ......
  • Baldyga Const. Co., Inc. v. Hurff
    • United States
    • New Jersey Superior Court
    • December 22, 1978
    ...Typical of the law in many states is the holding of Malcolm Price, Inc. v. Sloane, 308 A.2d 779 (1973), app. after remand 339 A.2d 43 (1975), wherein the District of Columbia Court of Appeals held that when a contractor abandons a project prior to completion, the applicable time period for ......
  • Baldyga Const. Co., Inc. v. Hurff
    • United States
    • New Jersey Superior Court — Appellate Division
    • July 1, 1980
    ...no basis for support of the trial judge's holding in Malcolm Price, Inc. v. Sloane, 308 A.2d 779 (D.C.App.1973), aff'd on remand 339 A.2d 43 (D.C.App.1975). The District of Columbia opinion involves the construction of sections (§§ 38-102 and 115) of the District of Columbia Code 1967. The ......
  • Moore v. Axelrod
    • United States
    • D.C. Court of Appeals
    • March 18, 1982
    ...is performed and/or materials are furnished as a consequence of which value is added to the structure involved. Sloane v. Malcolm Price, Inc., D.C.App., 339 A.2d 43, 45 (1975). 12. Section 38-107 requires the owner to disclose the terms of the contract between the owner and the general cont......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT