Sperry Systems Man. Div. of Sperry Div. v. Engineers Union, 72 Civ. 3626.

Decision Date27 February 1974
Docket NumberNo. 72 Civ. 3626.,72 Civ. 3626.
Citation371 F. Supp. 198
PartiesSPERRY SYSTEMS MANAGEMENT DIVISION OF SPERRY DIVISION, SPERRY RAND CORPORATION, Plaintiff, v. ENGINEERS UNION, INTERNATIONAL UNION OF ELECTRICAL, RADIO AND MACHINE WORKERS, AFL-CIO, CLC, Defendant.
CourtU.S. District Court — Southern District of New York

Poletti Freidin Prashker, Feldman & Gartner, New York City (Herbert Prashker, New York City, and Edward R. Cohen, Austin, Tex., of counsel), for plaintiff.

Vladeck, Elias, Vladeck & Lewis, New York City (Everett E. Lewis, New York City, of counsel), for defendant.

OPINION

BAUMAN, District Judge.

Plaintiff, the Sperry Systems Management Division of the Sperry Rand Corporation (hereinafter referred to as "Sperry") sues, pursuant to Section 301 of the Labor Management Relations Act of 1947, 29 U.S.C. § 185, for an order staying and enjoining arbitration concerning Sperry's right to permit employees of its subcontractors to enter its plant, work alongside its employees, and utilize its equipment. Defendant Engineers Union (hereinafter "the Union") has counterclaimed for an order compelling arbitration pursuant to the terms of the collective bargaining agreement.1

Both parties now seek summary judgment pursuant to Rule 56 of the Federal Rules of Civil Procedure.

I.

Before proceeding to a disposition of these motions, I feel constrained to discuss the basis for jurisdiction invoked here.

In 1957 the Supreme Court held that federal district courts are possessed of jurisdiction under Section 301 of the Labor Management Relations Act to entertain suits brought to compel arbitration under an existing labor contract. Textile Workers Union v. Lincoln Mills, 353 U.S. 448, 77 S.Ct. 912, 1 L.Ed.2d 972 (1957). The case before me presents the other side of the coin; an action to prevent arbitration. Although some courts have held that the language of § 301 does not confer such jurisdiction,2 the prevailing view is clearly otherwise. See Black-Clawson, Inc. v. International Association of Machinists, 313 F.2d 179 (2d Cir. 1962) and the cases collected therein.3 Clearly there is no question that the Union could have initially proceeded under § 301 by an action to compel arbitration. In this day and age it is inconceivable that Congress intended for jurisdiction to depend on the results of a footrace to the courthouse door. The same ultimate questions are involved whether the complaint alleges a "violation" of the contract and requests arbitration or whether it asserts "compliance" and seeks to enjoin improper demands for arbitration. Black-Clawson Co., Inc. v. International Association of Machinists, supra; Application of Contessa Lingerie, Inc., 227 F.Supp. 37 (S.D.N.Y.1964).

The court's jurisdiction has, in my view, been properly invoked, and I therefore proceed to the merits.

II.

The material facts are not disputed. In the fall of 1971 Sperry was awarded a contract by the City of Atlanta, Georgia for the design and implementation of a traffic control system. Sperry selected Industrial Programming Incorporated (hereinafter referred to as "IPI") as the subcontractor responsible for designing the computer programs for the regulation of traffic signals in that city. While it may have had employees of its own who were qualified to complete such work, Sperry, for perfectly valid cost and scheduling reasons, elected to subcontract.4 This resulted in several IPI employees working alongside Sperry employees in its Great Neck plant.

In May 1972 the Union submitted to Sperry a document entitled "Statement of Grievance" and numbered 72-31. The grievance stated:

"The Company has undermined the Union as the Bargaining Agent and the job security and advancement of its members by bringing non-Sperry engineering personnel into the plant to perform bargaining unit work.
"The Union demands that the Company place the above work into the Bargaining Unit or immediately withdraw the above personnel from the Sperry premises." Emphasis added

Upon receipt, Sperry informed the Union that such matters were not "grievable sic or arbitrable" under the collective bargaining agreement, and therefore Sperry would not process the grievance.5 Some three months later, Sperry received a notice that the Union had submitted the Statement of Grievance to arbitration.6 Sperry responded by commencing the instant suit. Its core contention is that the subject matter involved is "specifically excluded" from arbitration under the terms of the collective bargaining agreement.

The agreement at issue contains a broad arbitration clause which reads:

"1. Unless otherwise specifically excluded elsewhere in this Agreement, all disputes, differences and grievances which may arise out of this Agreement including claims arising out of breaches or threatened breaches or violations or threatened violations of this Agreement and which shall not have been satisfactorily settled within two weeks following the procedure herein set forth shall, at the request of either party, be promptly submitted to arbitration." Article XXVI, Section F of the Collective Bargaining Agreement Emphasis added.

Annexed to and part of the agreement is a document entitled "Subcontracting Memorandum" which provides that "decisions as to `make-or-buy' and subcontracting must finally rest with the Company, and shall be the responsibility solely of the Company." It concludes with the following paragraph:

"5. No matter or issue related to or growing out of subcontracting or `make-or-buy' decisions of the Company or the effect of such decisions or concerning this Memorandum, shall be subject to the grievance or arbitration procedure of the contract, under any provision of the contract or any provision of this or any other Memorandum or understanding." Emphasis added

Plaintiff contends that this paragraph clearly covers the situation encompassed by the grievance in question. Defendant disagrees. It argues that it is not challenging Sperry's right to subcontract, and concedes that it has no right to do so under the terms of the agreement. Instead, it contends, it is merely challenging Sperry's right to permit the employees of the outside contractors to work in the Sperry plant:

"The Union does not challenge the Company's right to subcontract the work in question. The gravaman sic of the grievance is where the subcontracted work is to be performed."7 Emphasis added

Thus, as plaintiff's counsel states, it is clear that the issue presented is whether a grievance claiming that subcontracted work may not be performed on the Company's premises by a subcontractor's employees is, within the meaning of the Subcontracting Memorandum, a matter or issue "related to or growing out of" subcontracting or the effect of a decision to contract-out. If the answer is affirmative, the matter is not arbitrable and an order enjoining the arbitration commenced by the Union must be granted. If the answer is that such grievance is not within the meaning of the Subcontracting Memorandum, defendant's counterclaim must be granted.

The parties are not content, however, to have this issue await a trial. Both have moved for summary judgment contending that, because of the clarity of the contractual provisions involved, and the absence of factual differences, there is no need for a trial. I agree.

III.

It is the responsibility of the court to determine whether the parties are bound to arbitrate, and, if so, what issues. John Wiley & Sons, Inc. v. Livingston, 376 U.S. 543, 84 S.Ct. 909, 11 L.Ed.2d 898 (1964); Atkinson v. Sinclair Refining Co., 370 U.S. 238, 82 S.Ct. 1318, 8 L.Ed.2d 462 (1962); Torrington Co. v. Metal Products Union, 347 F.2d 93 (2d Cir. 1965), cert. denied, 382 U.S. 940, 86 S.Ct. 394, 15 L.Ed.2d 351 (1965). Defendant's suggestion that the issue of arbitrability is for the arbitrator is without merit. Absent a clear provision in the collective bargaining agreement requiring otherwise, the decision is for the court. United Steelworkers v. Warrior & Gulf Co., 363 U.S. 574, 80 S.Ct. 1347, 4 L.Ed.2d 1409 (1960); Torrington Co. v. Metal Products Union, supra. We are not confronted with such a provision. On the contrary, the Subcontracting Memorandum specifically provides that "no matter concerning this Memorandum shall be subject to arbitration." Hence, the issue of arbitrability here is clearly for the court.

It is well settled that a party cannot be required to submit to arbitration that which he has not agreed to submit. Consistency with the federal policy favoring arbitration, however, requires that an order to arbitrate a given grievance not be denied "unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute." United Steelworkers v. Warrior & Gulf Co., 363 U.S. 574, 582-583, 80 S.Ct. 1347, 1353, 4 L.Ed.2d 1409 (1960). This rule, affording a strong presumption of arbitrability, has a crucial limitation set out by the Supreme Court in Warrior & Gulf:

"In the absence of any express provision excluding a particular grievance from arbitration, we think only the most forceful evidence of a purpose to exclude the claim from arbitration can prevail . . ." 363 U.S. at 584-585, 80 S.Ct. at 1354. Emphasis added

It follows that if the subject matter of a dispute is expressly excluded from arbitration by a clear and unambiguous exclusionary clause in the collective bargaining agreement, a party to the agreement cannot be compelled to arbitrate such a dispute. International Ass'n of Machinists and Aerospace Workers v. General Electric Co., 406 F. 2d 1046 (2d Cir. 1969); Procter & Gamble Independent Union v. Procter & Gamble Mfg. Co., 298 F.2d 644 (2d Cir. 1962).

It is difficult to imagine a clearer exclusionary clause than the one before me. All matters related to or growing out of subcontracting decisions are excluded from arbitration as are matters related to or growing out of the effects of such decisions. To argue that the...

To continue reading

Request your trial
4 cases
  • DISTRICT 2, MARINE ENG. BEN. ASS'N v. Falcon Carriers, Inc., 74 Civ. 1452 (JMC).
    • United States
    • U.S. District Court — Southern District of New York
    • 22 Abril 1974
    ...under Section 301 to issue an order preventing submission of an issue to arbitration. See also, Sperry Rand Corp. v. Engineers Union, 371 F.Supp. 198, 85 L.R.R.M. 2615 (S.D.N.Y.1974). The point of departure for the court's present inquiry is the so called Steel-workers Trilogy. United Steel......
  • Ben Gutman Truck Serv. v. Teamsters Local No. 600
    • United States
    • U.S. District Court — Eastern District of Missouri
    • 29 Febrero 1980
    ...But, see, Black-Clawson Co., Inc. v. International Ass'n. of Mach., 313 F.2d 179 (2d Cir. 1962); Sperry Systems Man. Div. of Sperry Div. v. Engineers Union, 371 F.Supp. 198 (S.D.N.Y. 1974); Camden Industries Co. v. Carpenters Local Union No. 1688, 246 F.Supp. 252 (D.N.H.1965). Plaintiff see......
  • Garlick Funeral Homes, Inc. v. LOCAL 100, SER. EMP., ETC.
    • United States
    • U.S. District Court — Southern District of New York
    • 3 Mayo 1976
    ...of two proffered interpretations is "patently impossible or unreasonable." Strauss, supra; Sperry Systems Man. Div. of Sperry Div. v. Engineers Union, 371 F.Supp. 198, 203-4 (S.D.N.Y.1974); Jennings v. Westinghouse Electric Corp., 283 F.Supp. 308 (S.D. Given Chief Judge Mishler's injunction......
  • Westvaco Corp. v. United Paperworkers Intern. U., 76 Civ. 3109-CSH.
    • United States
    • U.S. District Court — Southern District of New York
    • 6 Octubre 1976
    ...to grant either remedy under Section 301 of the Labor Management Relations Act, 29 U.S.C. § 185. Sperry Systems Management Division v. Engineers Union, 371 F.Supp. 198, 200 (S.D.N.Y. 1974); Charmers Industries, Inc. v. Liquor Salesmen's Union, 415 F.Supp. 781, 783 I deny Westvaco's motion t......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT